CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
Central Hounslow Area Committee (Planning), Thursday 6 March 2003 at 7.30pm

Highway - Maintenance Programme 2003/04

Agreed Planning 1 paper

Central Hounslow Area Committee (Planning) agreed this item on Thursday 6 March 2003. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Resolved – a) To agree their area priorities for roads and footways requiring priority treatment for 2003/04 as set out in Appendix 1.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Central Hounslow Area Committee (Planning)

Recommendations

2.1That members agree their area priorities for roads and footways requiring priority treatment in order to establish an area programme 2003 / 04. 3.0 BACKGROUND

3.1In recent years Area Committees have been advised of maintenance priorities and asked to comment on the priorities based on their own perceptions and those of residents, in order to establish the Area Programme.

4.0POLICY FOR ASSESSMENT

4.1Technical assessment of the Borough's network of footways and carriageways is undertaken in accordance with the principles of the United Kingdom Pavement Management System (UKPMS).

4.2It is now required that this system be used by all Highway Authorities to support their bids made to TfL for the maintenance of Principal roads.

5.0CORPORATE PRIORITISED LIST

5.1The Corporate Prioritised List comprises those roads assessment identifies should be considered for reconstruction in order of priority.

5.2Area Engineers undertake a visual inspection of those roads included in the Corporate Prioritised List within their area to check the assessment results and estimated costs.

5.3The Executive of 11 February 2003 agreed that funding be distributed between Area Committees based on the cost of implementing schemes within an area, expressed as a %age of the corporate programme total.

5.6The Executive also agreed that funding allocation be split between road and footway maintenance in proportion to their respective total values. The agreed split will be footways 55% / roads 45%

6.0AREA PROGRAMME TO LOCAL ROADS

6.1Area Committee Members are asked to agree their area priorities as detailed in the draft area programme attached in Appendix 1. This will establish a prioritised list, and those schemes of the highest priority will be implemented from the available budget allocation

6.2If resources were allocated in line with recent years, the available funding for the Central Hounslow area programme area would be £160K

6.3Members will be verbally informed at the meeting of the latest budget information and its affect on the programme. 7.0 PRINCIPAL ROAD PROGRAMME

7.1The Principal Road Programme is entirely funded by TfL who have allocated LB Hounslow with £970k for 2003/04, to be used for assessed priorities.

7.2Carriageway resurfacing works to Principal Roads in the Central Hounslow Area have been agreed with TfL as follows:

Staines Road from Wellington Road to Frampton Road Wellington Road North from Bath Road to Staines Road London Road from Bridge Road to Thornbury Road

Financial implications

8.1The Borough Treasurer comments that LBH carries out highway maintenance works to local roads as part of its own Capital Programme and also for Principal Roads on behalf of Transport for London (TFL). In both cases, resources are limited and it is increasingly necessary to allocate them to schemes in strict priority order. as determined by a nationally accepted technical assessment.

8.2The Council’s revenue resources for 2003/04 have yet to be determined but in recent years have been approx £500k for planned maintenance.

9.0ENVIRONMENTAL IMPLICATIONS

9.1Proper maintenance of the Borough's infrastructure is statutory duty and essential in order to improve the quality of life for the Borough's residents, workers and visitors.

9.2Failure to effectively maintain the highway will inevitably result in increased complaints, insurance claims, inconvenience to highway users and will put personal safety at risk.

10.0EQUAL OPPORTUNITY IMPLICATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway: Maintenance Programme 2003/04Report 81 KB DownloadRead as text

At this meeting

Whole meeting
9MinutesOn the agenda
10Highway - Maintenance Programme 2003/04This decision
11Highways - Vehicle CrossoversApproved 12Planning Application No 00795/A/P15 - 5 New Road, HounslowOn the agenda 13Planning Application No 00530/76/P4 - 76 Grove Road, IsleworthApproved 14Planning Application No 00477/6/P1 -6 George Street, HounslowOn the agenda 15Planning Application No 00667/77/P5 - 77 Kingsley RoadApproved 16Planning Application No 00401/82/P2 - 82 Elmer Gardens, IsleworthApproved 17Planning Application No 00154/36/P2 - 36 Bridge Road, HounslowRefused 18Planning Application No 01254/335/P2 - 335 Staines RoadRefused 19Planning Application No 01205/125/P1 - 125 Whitton Road,Approved 20Planning Application No 00610/108/P1 - 108 High Street, HounslowAgreed 21Planning Application No 00170/9/P1 - 9 Bulstrode Avenue, HounslowApproved 22Planning Application No 00992/9/P7 - 9 St Stephens RoadApproved 23Planning Application No 01357/9/P1 - 9 Sandra CloseDeferred 24Planning Position Statement - Former Police Public Order Training Centre, Hounslow HeathOn the agenda 25Enforcement Action - 22 Yew Tree Walk, HounslowDecided 26Enforcement Action - 71 Manor Avenue, Hounslow WestDecided 27Enforcement Action - 29 Martindale Road, HounslowDecided 28Enforcement Action - Land to the rear of Hussar Public House 495-497 Staines Road, HounslowDeferred 29Review of Traffic Conditions in Heath Road, Outside Chatsworth Junior and Chatsworth Infant and Nursery SchoolsApproved 30List of Delegated DecisionsOn the agenda 31Results of Planning AppealsOn the agenda 32Any Other BusinessAgreed

On this subject at Hounslow

Search all
  1. Highway - Maintenance Programme 2003/04This decision
  2. Highways Maintenance PFI Contract - appointment of preferred bidder (ENV 166)Agreed
  3. Client Staffing Structure for the Highways Maintenance PFI Contract (ENV 167)Agreed
  4. Highways Maintenance Private Finance InitiativeNoted
  5. Highways Planned Maintenance - Budget VirementAgreed
  6. Pension arrangements for Highways Maintenance PFIAgreed

More from Hounslow Central Hounslow Area Committee (Planning)

All decisions
MeetingDecisionOutcome
10 Feb 2011 Petition - Alleyway Whitton Road, Hounslowa) That the repairs to the alleyway in response to the issues raised in the petition be noted. b) That the officers’ ... Noted Open
10 Feb 2011 266-268 Bath Road, HounslowThat planning application 00083/266-268/P4 for the change of use of 266 Bath Road from A2 (financial and professional... Decided Open
10 Feb 2011 15 Hollygrove Close, HounslowThat planning application 01706/15/P1 for the erection of a single storey rear extension at 15 Hollygrove Close, Houn... Approved Open
10 Feb 2011 89 Kingsley Road, HounslowResolved : That planning application 00667/89/P3 for the erection of a two-storey rear extension to the existing rest... Approved Open
10 Feb 2011 72 St Stephens Road, HounslowThat planning application 00992/72/P4 for the erection of a single-storey rear extension to be approved, subject to t... Approved Open