London Borough of Hounslow
Cabinet, Tuesday 6 March 2012 at 7.00pm

Highways Maintenance PFI Contract - appointment of preferred bidder (ENV 166)

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 6 March 2012. Below is the council's own wording, with the papers it was decided on.

Item152

Resolved

The Cabinet agreed the recommendations of the report as follows: 1. The Cabinet agreed to award the Highways PFI Contract to Vinci Ringway , subject to finalisation of the Project Agreement and to the approval of the Final Business Case by the Department for Transport ( DfT ) and HM Treasury. 2. The Cabinet noted the identity of the Reserve Bidder as Balfour Beatty. 3. The Cabinet confirmed the financial implications of the project set out in the Confidential Part II appendix of the report and to establish a PFI fund to ensure that the future costs of the contract can be met.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Recommendations

Members are recommended to;

1.1Award the Highways PFI contract to (to be announced at the Cabinet meeting) subject to finalisation of the Project Agreement and to the approval of the Final Business Case by the DfT and HM Treasury,

1.2To note that identity of the Reserve Bidder (to be announced at the Cabinet meeting)

1.3Confirm the financial implications of the project set out in Confidential Part 2 of the report and to establish a PFI fund to ensure that the future costs of the contract can be met.

Executive summary

This report updates Members on the progress of the Highways Maintenance PFI contract and informs Members how the procurement process has progressed to a point where the Council can announce the identity of the Preferred Bidder to provide highway maintenance services from January 2013 for a period of 25 years. The report describes the features and benefits of the contract, which will help to deliver a huge improvement in Hounslow’s street scene.

Details of project costs are set out in confidential Part 2 of the report.

To ensure commercial confidentiality the identity of the Preferred Bidder and Reserve Bidder will be announced at the meeting following completion of the currently on-going bid evaluation. 2.0 Scope of the Contract, Features and Benefits

2.1Hounslow’s highways infrastructure is in a poor condition and in serious need of capital investment – over £80m in order to bring the network up to acceptable standards. This sum is well in excess of the Council’s funding capability. Therefore, over the last few years the Council has been working on the procurement of a contract to deliver that much needed step change to the street scene. The vehicle for this change is the Highways Maintenance Private Finance Initiative (PFI) contract.

2.2The scope of the project embraces an approach referred to as “fence to fence”, which includes services that have an effect on the overall street scene. The contract therefore includes:

- carriageways and footways, - street lighting, - bridges and structures, - signs and other street furniture - drainage and gullies, - trees and verges, - winter gritting, - street cleansing, - removal of graffiti and fly tipping -related enforcement functions - administration and settlement of insurance claims.

2.4Roads will be restored and maintained to a high standard fit for the 21st century i.e. with smooth skid resistant surfaces and with virtually no potholes, without excessive patches, or cracks, and with many roads resurfaced using modern materials and with good condition of channels between road and footway.

2.5Footways will be re-laid and maintained to a high standard with minimum cracks and trips. Most residential streets will have bituminous surfaces which will reduce trips and reduce maintenance; many areas with paving blocks will be also be resurfaced and some 20% of footways will be strengthened to allow some footway parking.

2.6Street lighting will be brought up to modern standards – old street lighting columns and lanterns will be replaced, and high quality white light will be provided with reduced energy consumption. A Central Management System will enable better monitoring and greater flexibility of lighting levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Maintenance PFI Contract: appointment of preferred bidder (ENV 166)Report 114 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Highways Maintenance PFI Contract - appointment of preferred bidder (ENV 166)This decision
  2. Client Staffing Structure for the Highways Maintenance PFI Contract (ENV 167)Agreed
  3. Highways Maintenance Private Finance InitiativeNoted
  4. Highways Planned Maintenance - Budget VirementAgreed
  5. Pension arrangements for Highways Maintenance PFIAgreed
  6. 2009/10 Highways Planned Maintenance Programme; Sub-Committee Deliberations.Approved

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies