The Cabinet agreed the recommendations of the report as follows: 1. The Cabinet agreed to award the Highways PFI Contract to Vinci Ringway , subject to finalisation of the Project Agreement and to the approval of the Final Business Case by the Department for Transport ( DfT ) and HM Treasury. 2. The Cabinet noted the identity of the Reserve Bidder as Balfour Beatty. 3. The Cabinet confirmed the financial implications of the project set out in the Confidential Part II appendix of the report and to establish a PFI fund to ensure that the future costs of the contract can be met.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.1Award the Highways PFI contract to (to be announced at the Cabinet meeting) subject to finalisation of the Project Agreement and to the approval of the Final Business Case by the DfT and HM Treasury,
1.2To note that identity of the Reserve Bidder (to be announced at the Cabinet meeting)
1.3Confirm the financial implications of the project set out in Confidential Part 2 of the report and to establish a PFI fund to ensure that the future costs of the contract can be met.
Executive summary
This report updates Members on the progress of the Highways Maintenance PFI contract and informs Members how the procurement process has progressed to a point where the Council can announce the identity of the Preferred Bidder to provide highway maintenance services from January 2013 for a period of 25 years. The report describes the features and benefits of the contract, which will help to deliver a huge improvement in Hounslow’s street scene.
Details of project costs are set out in confidential Part 2 of the report.
To ensure commercial confidentiality the identity of the Preferred Bidder and Reserve Bidder will be announced at the meeting following completion of the currently on-going bid evaluation. 2.0 Scope of the Contract, Features and Benefits
2.1Hounslow’s highways infrastructure is in a poor condition and in serious need of capital investment – over £80m in order to bring the network up to acceptable standards. This sum is well in excess of the Council’s funding capability. Therefore, over the last few years the Council has been working on the procurement of a contract to deliver that much needed step change to the street scene. The vehicle for this change is the Highways Maintenance Private Finance Initiative (PFI) contract.
2.2The scope of the project embraces an approach referred to as “fence to fence”, which includes services that have an effect on the overall street scene. The contract therefore includes:
- carriageways and footways, - street lighting, - bridges and structures, - signs and other street furniture - drainage and gullies, - trees and verges, - winter gritting, - street cleansing, - removal of graffiti and fly tipping -related enforcement functions - administration and settlement of insurance claims.
2.4Roads will be restored and maintained to a high standard fit for the 21st century i.e. with smooth skid resistant surfaces and with virtually no potholes, without excessive patches, or cracks, and with many roads resurfaced using modern materials and with good condition of channels between road and footway.
2.5Footways will be re-laid and maintained to a high standard with minimum cracks and trips. Most residential streets will have bituminous surfaces which will reduce trips and reduce maintenance; many areas with paving blocks will be also be resurfaced and some 20% of footways will be strengthened to allow some footway parking.
2.6Street lighting will be brought up to modern standards – old street lighting columns and lanterns will be replaced, and high quality white light will be provided with reduced energy consumption. A Central Management System will enable better monitoring and greater flexibility of lighting levels.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.