Isleworth and Brentford Area Committee (Planning) decommissioned 25/05/11 agreed this item on Thursday 6 March 2003. Below is the council's own wording, with the papers it was decided on.
That Members agree the priorities identified in the report. 2. That Members expressed some concerns about the process of setting priorities. 3. That Members suggested to Councillor Cadbury as lead Executive member to take the issue to the Executive to consider the process for future years and report back to the Area Committee. 4. That Councillor Reid discuss issues relating to Osterley Road separately with officers.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Isleworth and Brentford Area Committee (Planning) decommissioned 25/05/11
Recommendations
2.1That members agree their area priorities for roads and footways requiring priority treatment in order to establish an area programme 2003 / 04. 3.0 BACKGROUND
3.1In recent years Area Committees have been advised of maintenance priorities and asked to comment on the priorities based on their own perceptions and those of residents, in order to establish the Area Programme.
4.0POLICY FOR ASSESSMENT
4.1Technical assessment of the Borough's network of footways and carriageways is undertaken in accordance with the principles of the United Kingdom Pavement Management System (UKPMS).
4.2It is now required that this system be used by all Highway Authorities to support their bids made to TfL for the maintenance of Principal roads.
5.0CORPORATE PRIORITISED LIST
5.1The Corporate Prioritised List comprises those roads assessment identifies should be considered for reconstruction in order of priority.
5.2Area Engineers undertake a visual inspection of those roads included in the Corporate Prioritised List within their area to check the assessment results and estimated costs.
5.3The Executive of 11 February 2003 agreed that funding be distributed between Area Committees based on the cost of implementing schemes within an area, expressed as a %age of the corporate programme total.
5.6The Executive also agreed that funding allocation be split between road and footway maintenance in proportion to their respective total values. The agreed split will be footways 55% / roads 45%
6.0AREA PROGRAMME TO LOCAL ROADS
6.1Area Committee Members are asked to agree their area priorities as detailed in the draft area programme attached in Appendix 1. This will establish a prioritised list, and those schemes of the highest priority will be implemented from the available budget allocation
6.2If resources were allocated in line with recent years, the available funding for the Isleworth & Brentford area programme area would be £180k
6.3Members will be verbally informed at the meeting of the latest budget information and its affect on the programme. 7.0 PRINCIPAL ROAD PROGRAMME
7.1The Principal Road Programme is entirely funded by TfL who have allocated LB Hounslow with £970k for 2003/04, to be used for assessed priorities.
Financial implications
8.1The Borough Treasurer comments that LBH carries out highway maintenance works to local roads as part of its own Capital Programme and also for Principal Roads on behalf of Transport for London (TFL). In both cases, resources are limited and it is increasingly necessary to allocate them to schemes in strict priority order. as determined by a nationally accepted technical assessment.
8.2The Council’s revenue resources for 2003/04 have yet to be determined but in recent years have been approx £500k for planned maintenance.
9.0ENVIRONMENTAL IMPLICATIONS
9.1Proper maintenance of the Borough's infrastructure is statutory duty and essential in order to improve the quality of life for the Borough's residents, workers and visitors.
9.2Failure to effectively maintain the highway will inevitably result in increased complaints, insurance claims, inconvenience to highway users and will put personal safety at risk.
10.0EQUAL OPPORTUNITY IMPLICATIONS
10.1Implementation of maintenance works will continue to provide a significant improvement to road users, in particular, people with disabilities and those with mobility problems by the installation of dropped kerbs, high visibility paving and tactile paving. Contact: Peter Kent Telephone: 020 8583 4903 Background Papers: This report has been or is due to be Considered by Executive Committee 11 February 2003 Head of Highways Services Highway Maintenance 2003/04 Borough Treasurer This report is relevant to the following wards/areas: Osterley & Spring Grove, Isleworth, Syon, Brentford,
Appendix 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Isleworth and Brentford Area Committee (Planning) decommissioned 25/05/11 at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
Isleworth Town Primary School, IsleworthThat members ’ comments be reported to Sustainable Development Committee if an acceptable scheme can be negotiated. I...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.