Resolved
That the area priorities for roads and footways as set out in the programme be agreed as part of the 2003/4 with the request that officers re-inspect the condition of the footway of Parkfield Avenue in particular.
West Area Committee (Planning) agreed this item on Thursday 29 May 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
That the area priorities for roads and footways as set out in the programme be agreed as part of the 2003/4 with the request that officers re-inspect the condition of the footway of Parkfield Avenue in particular.
2.1That members agree their area priorities for roads and footways requiring priority treatment in order to establish an area programme 2003 / 04. 3.0 BACKGROUND
3.1At the West Area committee of 27 February members were unable to agree priorities and asked for an engineers report on several carriageways and footways that they considered a priority.
3.2At the West Area committee of 10 April members expressed concern that there should not be a ‘free for all’ on the maintenance of the footways and carriageways in the area and asked for a further report to explain the reasoning behind the setting of priorities.
4.0ASSESSMENT
4.1Technical assessment of the Borough's network of footways and carriageways is undertaken in accordance with the principles of the United Kingdom Pavement Management System (UKPMS).
4.2Roads are assessed by identifying defects such as:
• % area of disturbed paving stones • % area of cracked paving stones • % length of defective kerb • % length of channel edge deterioration • % area of carriageway with major cracking • % area of carriageway with minor cracking • % area of carriageway with major rutting • % area of carriageway with minor rutting
UKPMS used this information to produce a condition rating for each road.
4.3It is now required that this system be used by all Highway Authorities to support their Borough Spending Plan bids for highway maintenance
4.3Audit Commission Performance Indicators determine that those roads with the highest condition ratings should be prioritised for reconstruction.
5.0PRIORITISED LIST
5.1The Corporate Prioritised List comprises those roads that should be considered for reconstruction in order of priority.
5.4Area Engineers will then undertake a visual inspection of those roads included in the Corporate Prioritised List within their area to check the assessment results and estimated costs. 5.5 Area Engineers will also check the assessment results of any roads not included in the Corporate Prioritised List, but which from local knowledge they know to be in poor condition.
6.0ENGINEERS REPORT
6.1As required by members, an engineers report was undertaken on those footways and carriageways which members feel should be given priority and compared with those of the highest priority as identified by UKPMS
6.2Carriageways identified by UKPMS
Nallhead Road Hanworth Priority No 1 UKPMS Rating 29,887 Estimated Cost £76.8k.
The carriageway surface is severely rutted, cracked and shows signs of edge deterioration.
It is a road of more than local importance and has medium traffic flows.
The resurfacing would be implemented prior to the traffic calming scheme to Nallhead Road / Main Street. Gladstone Avenue Feltham North Priority No 2 UKPMS Rating 28,063 Estimated Cost £45.36k
The carriageway surface is severely rutted, patched, cracked and shows signs of severe edge deterioration.
It is a residential road with low traffic flows.
Saxon Avenue Feltham Central Priority No 3 UKPMS Rating 25,058 Estimated Cost £41.64k
The carriageway surface is severely rotted, cracked and shows signs of edge deterioration and has numerous potholes.
It is the main access road to the Butts Farm Estate with medium traffic flows. Westbourne Road Feltham West Priority No 4 UKPMS Rating 24,769 Estimated Cost £k
The carriageway surface is severely rotted, cracked and shows signs of edge deterioration is extensively patched and shows sign of sub-base deterioration.
It is a residential road with low traffic flows.
Glebelands Road Feltham North Priority No 5 UKPMS Rating 23,152 Estimated Cost £25.32k
The carriageway surface is severely potholed. If this road is not resurfaced it will require extensive patching which may be less economical.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Maintenance ProgrammeReport | 19 pages | DownloadRead as text |
Follow West Area Committee (Planning) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2011 | Rex House, 26-28 Hampton Road West (Hanworth)Resolved – That planning permission for application 00550/F/P15 for the addition of 3 no. rooftop antenna at Rex Hous... | Approved | Open |
| 20 Jan 2011 | Proposed extension of North Feltham Trading Estate CPZResolved – That members agreed that:- (a) Officers carry out a preliminary consultation on the possible extension of ... | Agreed | Open |
| 20 Jan 2011 | 37 Grasmere Close (Feltham)Resolved – That planning permission for application 01556/37/P3 for the erection of single-storey ground floor rear e... | Approved | Open |
| 20 Jan 2011 | 48 Hounslow Road (Feltham)Resolved – That it be considered expedient, having regard to the provisions of the Unitary Development Plan, and all ... | Decided | Open |
| 12 Mar 2009 | Declarations of interest or any communications from membersCouncillor Williams, Hutchison and Bowen sent apologies for their expected late arrivals. Declarations of Interest It... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.