Capital Allocations 2005/06 - 2006/07

Agreed Committee 1 paper

Heston and Cranford Area Committee (Monitoring) agreed this item on Thursday 23 March 2006. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

a) The recommendations in the report were agreed. b) Councillor Lal raised concerns over a brick wall in need of repair at the top end of Hogarth Gardens, Heston. Alysse Strachan advised that a bid for the work would be provided to the Committee.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Heston and Cranford Area Committee (Monitoring)

Summary

• To note the release of the Area Committee Capital Budgets for 2005/06 and for 2006/07. • To agree the allocation of the balance of Area Capital funding and identified Section 106s to environmental schemes and an art project.

Recommendations

1.1To agree to allocate £27,000 to the small environmental schemes, funded from £9,000 capital balance available and £18,000 Section 106 contributions from schemes 112, and 276.

1.2To agree to allocate £5,412 as an Area Committee contribution to Urban Art at the Hub on the Beavers Estate from Section 106 scheme 148.

1.3To agree that officers bring forward proposals for spend of the £36,000 allocation (2005-07) for pavement works against members’ priorities.

Background

2.1The Executive, at its meeting on 3rd January 2006, released the remaining ‘frozen’ capital budgets for 2005/06 and 2006/07. The agreed recommendations included:-

1.4To allocate £100k from the Area Committee environmental improvement budget in 2005/06 and £100k in 2006/07 for ‘pavement works of a capital nature’.

1.5To allocate £150k in 2005/06 and £150k in 2006/07 to all 5 Area Committees for environmental improvements, using Methodology A.

2.2The table below shows the allocations of both these budgets across the Area Committees for year 2005-06 and year 2006-07.

1 Area Properties % Allocation £100k Allocation £150k ‘pavement environmental works’ improvements £000 £000

West 22,633 26 26 39 Central 16,148 19 19 29 Heston & Cranford 15,711 18 18 27 Chiswick 13,990 16 16 24

Total 86,904 100 100 150

Notes: Properties based on October 2002 dataset from ONS on domestic households by new ward boundaries.

2.3Definition of Capital

These monies are available for capital expenditure only, and cannot be used for day-to-day revenue running expenses. Expenditure for capital purposes broadly comprises: - • the acquisition of land, buildings, plant, apparatus and vehicles • the construction of roads and buildings • the enhancement of land, roads and buildings

Enhancement should cover at least one of the following objectives: - • lengthening substantially the useful life of the asset • increasing substantially the open market value of the asset • increasing substantially the extent to which the asset can be used.

2.4In allocating these budgets consideration should be given to the availability of S106 funding i.e. the most effective use of the corporate capital allocations is for those schemes for which there is no prospect of S106 funding being available. Corporate funds could also be combined with existing S106 funding to allow a larger scheme to proceed. In all cases expenditure must be contained within identified budget.

3. Capital Monies

Summary Budget £ Unallocated balance brought forward from 2004/05 27,500

Environmental Improvements allocation 2005/06 27,000

Environmental Improvements allocation 2006/07 27,000

Total 81,500

2 Allocated to:- £ Mobile CCT Contribution 30,000 Wheatlands Street Lighting 22,500 Crosslands Ave Street Lighting 20,000

Total: 72,500

Available capital remaining = £9,000

4. Section 106 Information (Source Section 106 Officer)

4.1There is a current total of £95,894 of unallocated Area Committee S106 monies.

Environmental Improvements : £23,412 Traffic & Highways : £7,000 (note: recommended deed of variation) Open Space etc. : £65,482

These are from the following schemes listed. Their terms are set out for the committee’s consideration and matching to local priorities.

4.2Urban Art Project

There is a request for a contribution towards an urban art project (see Appendix 1) in Salisbury Road (the library/youth centre and Sure Start site). Scheme 148 (£5,412) which is particularly relevant, as the contribution must be spent within the Beavers Estate Area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Allocations 2005/06: 2006/07Report 41 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Capital Allocations 2005/06 - 2006/07This decision
  2. Area Committee Capital Allocations and proposalsNoted
  3. Capital AllocationsAgreed
  4. Capital Allocations for the Area CommitteesNoted

More from Hounslow Heston and Cranford Area Committee (Monitoring)

All decisions
MeetingDecisionOutcome
31 Mar 2011 Election of ChairThat Councillor Rajawat should chair the meeting. Decided Open
31 Mar 2011 Impact of the traffic calming measures on traffic flows through Sutton Road (Nick Woods, Head of Traffic and Parking)Resolved : § That the report in response to the Committee’s resolution of revisiting the scheme post implementation b... Noted Open
27 Jan 2011 Minutes of the meeting held on 2 December 2010Agreed subject to the following amendment: Minute 24: Minutes of the meeting held on 9 September 2010 and Matters Ari... Agreed Open
27 Jan 2011 Sustainable Community Strategy (Chris Bates, Assistant Director Policy, Performance and Communications; and Julia Worboys, Planning Policy Team Leader)§ That councillors should pass comments and suggestions on the draft vision document to Heidi Shearn; and § that Coun... Decided Open
27 Jan 2011 Small Grant Applications (Heidi Shearn, Area Coordinator)That the Area Committee allocate the Area Fund to the listed organisations as follows: Integrated Neurological Servic... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies