Resolved
Resolved That the carriageway and footway priorities listed in Appendix A of the report be agreed, except for Thorncliffe Road carriageway, which would be the first priority instead of Cranford Lane.
Heston and Cranford Area Committee (Monitoring) agreed this item on Thursday 23 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the carriageway and footway priorities listed in Appendix A of the report be agreed, except for Thorncliffe Road carriageway, which would be the first priority instead of Cranford Lane.
Contact: Peter Kent Tel: 020 8583 4903 E-Mail: [email protected]
Heston & Cranford Area Committee - 22 March 2006
HIGHWAYS MAINTENANCE PROGRAMME 2006/07 Report by: Suresh Kamath, Director of Street Management and Public Protection
Summary To advise Members of the required process to establish the Highways Maintenance Programme 2006/07.
1.0RECOMMENDATIONS 1.1 That members agree and approve their priorities for roads and footways requiring priority treatment in order to establish an area programme of work for financial year 2006/07.
2.0BACKGROUND 2.1 On 5 April 2005 the Executive Committee approved the process to establish the local road and footway resurfacing programme and agree apportionment of funding.
2.2Members agreed that the limited funding available for planned maintenance be targeted at roads of more than local importance with high pedestrian and vehicular usage.
2.3Roads of more than local importance are defined in the Local Authorities Association Code of Practice and will include: • Classified non-principal roads • Bus routes • High density vehicle routes • Accident hot spots • High density pedestrian areas • Schools / Old peoples homes • Hospitals / medical centres
2.4These roads are extracted from the Corporate Prioritised List and are listed by order of priority from Condition Factors.
3.0HOW THE ORDER OF PRIORITY IS ARRIVED AT 3.1 Technical assessment of the Borough's network of footways and carriageways is undertaken in accordance with the principles of the United Kingdom Pavement Management System (UKPMS).
3.2The collected data is processed and a condition factor allocated based on the type and extent of the defects identified. The condition factor of each road is used to produce a prioritised list. 4.0 AREA PROGRAMMES 4.1 Draft area programmes are extracted from the Implementation Priorities and submitted to Area Committees for approval.
4.2Members of each Area Committee will have the opportunity to either agree their area priorities or advise of their own perceptions of those roads, which should be included in the Area Programme from the implementation priorities.
4.3This allows Area Committees for example, to propose substituting roads for others of approximately similar priority within their own area but not to impact on resources available to other areas.
4.4This will establish a prioritised list for each Area Committee and those schemes of the highest priority will be implemented as funds are made available throughout the year.
4.5Maintenance priorities for Heston & Cranford are attached
5.0PRINCIPAL ROAD PROGRAMME 5.1 The Principal Road Programme is entirely funded by TfL
5.2Following assessment a 5 year programme of carriageway resurfacing and associated footway re-construction is included in the Borough Spending Plan
5.3The schemes within the Heston & Cranford area included in the Principal Road programme 2006/07 are as follows. A 3006 Bath Road ( Henleys Roundabout to Vic Farm Road ) £350k
6.0FINANCIAL IMPLICATIONS 6.1 The Council’s Revenue resource for 2006/07 is £500k for planned maintenance.
6.2Available funding is apportioned between Area Committees in relation to the value of schemes in a particular area expressed as a % of the total value in the corporate programme.
6.3Funding allocation is split between roads ( 48% ) and footways ( 52% ) in proportion to their respective total values on the programme.
6.4In addition £36k has been allocated to the Heston & Cranford area from the £200k Environmental Improvement budget 2005/07 for ‘pavement works of a Capital nature’
6.5From the above the likely budget allocation for the Heston & Cranford area would be as follows Footways £88.0k Roads £48.0k
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Maintenance ProgrammeReport | 23 KB | DownloadRead as text |
Follow Heston and Cranford Area Committee (Monitoring) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2011 | Election of ChairThat Councillor Rajawat should chair the meeting. | Decided | Open |
| 31 Mar 2011 | Impact of the traffic calming measures on traffic flows through Sutton Road (Nick Woods, Head of Traffic and Parking)Resolved : § That the report in response to the Committee’s resolution of revisiting the scheme post implementation b... | Noted | Open |
| 27 Jan 2011 | Minutes of the meeting held on 2 December 2010Agreed subject to the following amendment: Minute 24: Minutes of the meeting held on 9 September 2010 and Matters Ari... | Agreed | Open |
| 27 Jan 2011 | Sustainable Community Strategy (Chris Bates, Assistant Director Policy, Performance and Communications; and Julia Worboys, Planning Policy Team Leader)§ That councillors should pass comments and suggestions on the draft vision document to Heidi Shearn; and § that Coun... | Decided | Open |
| 27 Jan 2011 | Small Grant Applications (Heidi Shearn, Area Coordinator)That the Area Committee allocate the Area Fund to the listed organisations as follows: Integrated Neurological Servic... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.