Resolved
Resolved - a) To note the report b) To approve the priority Roads (carriageways) and Pavements (footways) as set out on pages 39 and 40 of the report pack.
Central Hounslow Area Committee (monitoring) noted this item on Thursday 29 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - a) To note the report b) To approve the priority Roads (carriageways) and Pavements (footways) as set out on pages 39 and 40 of the report pack.
Contact: Krishnan Radhakrishnan / Satbir Gill Tel: 020 8583 5315 / 4904 E-Mail: [email protected] / [email protected] Central Hounslow Area Committee (Monitoring) – 29 March 2007
HIGHWAYS INFRASTRUCTURE MAINTENANCE PROGRAMME – 2007/08
Report by: Suresh Kamath, Director Street Management & Public Protection
Summary This report advises Members of the Area Committee the process carried out to establish the Highways Infrastructure Maintenance Programme for 2007/08 and to obtain their approval.
1.0RECOMMENDATION 1.1 That the Members note and approve the priority for Roads (carriageways) and Pavements (footways) requiring planned maintenance in order to establish an Area Programme of Work for the financial year 2007/08.
2.0BACKGROUND 2.1 The Executive, on 5th April 2005, agreed:
2.1.1 The process to establish the implementation priorities from 2005/06 and future years until such time as the Hounslow Highways Asset Management Plan (HAMP) is adopted (see section 2.4).
2.1.2 That Area Committees are consulted to establish the Area Programme of Work from their implementation priorities.
2.1.3 That, with limited funds available, planned maintenance be targeted; a. At designated Roads having due regard to traffic flows but also on the basis of Risk Assessment and the functionality of that particular section of the network b. At Pavements determined by the functionality of the footway and the scale of use. The contribution and the importance of the Pavement to the quality of public space and the street scene. Local factors such as age, distribution of population, proximity of schools or other establishments attracting a higher than normal number of pedestrians to the area need to be taken into account.
2.1.4 The apportionment of funding between Roads and Pavements on a ratio of Roads:Pavements 48:52 in line with the estimated backlog of the two assets.
2.2Section 41 of the Highways Act 1980 imposes a statutory on the Council to maintain highways maintainable at public expense, and almost all claims against authorities relating to highway functions arise from the alleged breach of this section. Section 58 provides for a defence against legal action relating to alleged failure to maintain on grounds that the authority has taken such care as in all the circumstances was reasonably required to secure that the part of the highway in question was not dangerous for traffic. 2.3 In addition, The Traffic Management Act 2004 has established a new duty for local traffic authorities to manage their road network with a view to achieving, so far as may be reasonably practicable, having regard to their other obligations, policies and the following objectives; • Securing the expeditious movement of traffic on the authority’s road network, and • Facilitating the expeditious movement of traffic on road networks for which another authority is the traffic authority.
2.4The Highways Asset Management Plan (HAMP) version 1 was adopted by the Executive on 4th April 2006 which sets out objectives, targets for delivery and procedures for efficient management of the asset lifecycle, and a programme of improvements for all parts of the public space which we call the Highway or the Network. The HAMP seeks to balance the needs of customers, who expect a high quality of current service with the desire to preserve the integrity and value of the Street network for future generations. The HAMP is only the first step in adopting Asset Management principles for our street network. The full benefits could be realised in the coming years as we develop and implement the actions set out in our improvement programme when adequate resources are identified.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Maintenance Programme: Satbir GillReport | 29 KB | DownloadRead as text |
Follow Central Hounslow Area Committee (monitoring) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2011 | S.106 Funding for Environmental Improvement SchemesThat the allocation of the sums available for the proposed works, totalling £308,155.19 as set out in Appendix 1 of t... | Approved | Open |
| 20 Jan 2011 | Appointment of Co-opted MembersThat [name removed], [name removed] and [name removed] be appointed at Co-opted Members to Central Hounslow Area Comm... | Decided | Open |
| 18 Mar 2010 | Declarations of Interest and any other Communication from MembersCouncillor Sharma presented a petition in objection to the red bus route opposite Hounslow West Tube station. Action:... | Decided | Open |
| 18 Mar 2010 | Minutes of the meeting held on 3 December 2009Agreed. | Agreed | Open |
| 18 Mar 2010 | Minutes of the meeting held on 21 January 2010Agreed, with the following addition: Councillor L. Davies asked the Area Committee for funding to support the Wii Oly... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.