CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
Executive, Tuesday 24 February 2009 at 7.00pm

Revenue Financial Monitoring - Month Ended 30th November 2008

Noted Executive 1 paper

Executive noted this item on Tuesday 24 February 2009. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

The Executive: Noted the results of the revenue budget monitoring at 30 November 2008. Agreed action to contain out turn within the Council’s corporate budget for 2008-09. The Executive: Noted the results of the revenue budget monitoring at 30 November 2008. Agreed action to contain out turn within the Council’s corporate budget for 2008-09. ACTION BY: Councillor Gerald McGregor, Stephen Fitzgerald, Director of Finance and Hugh Godsland , Chief Accountant.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Executive

Contact: Hugh Godsland Tel: 020 8583 2430 E-Mail: [email protected]

Executive – 24 February 2009

REVENUE FINANCIAL MONITORING - MONTH ENDED 30 NOVEMBER 2008

Report by: Director of Finance

Executive Summary • This report advises Members of the issues arising from revenue budget monitoring at 30 November 2008, and reports on the spending pressures identified. • £4.3M of Improvement Plan Savings in 2008-09 have now been identified by departments and departmental budgets have been adjusted accordingly. • Departments project cumulative overspending of some £2.9M in 2008-09. Action needs to be taken to contain expenditure within approved budgets. • The report then alerts Members to the current state of the Council’s Contingency Provision and re-states the purpose of the Provision. • Only about £1.7M of the 2008-09 Contingency Provision remains uncommitted. Departmental Projected commitments as a result of growth pressures amount to some £6.3M. These growth pressures need to be contained, or funding re-directed from existing budgets to cover the shortfall. • It will be necessary to take and monitor corrective action to address these issues.

1.0RECOMMENDATION That Executive: • Notes the results of revenue budget monitoring at 30 November 2008 • Agrees action to contain out turn within the Council’s corporate budget for 2008-09

2.0BACKGROUND 2.1 This report is a brief review of the Council’s Revenue Budget for 2008-09, based on monitoring carried out at 30 November 2008. At this stage of the year projections of outturn must be regarded as provisional. The impact of the Improvement Plan will potentially have a significant impact on the outturn. The current projection is that a saving of £42m will be achieved over the three-year period, and a substantial amount of further work is required to achieve the £53m target agreed in Stage Gate 4. Members Working Group and CMT will continue to be updated on progress on the achievement of IP savings and on addressing the current shortfall against the Stage Gate 4 target.

2.2The table below compares the approved budget for each department with the department’s projection of its anticipated worst case out turn for 2008-09. The issues that departments will need to address are set out below the table. 2.3 The aggregate reported outturn by departments is an estimated overspend of £2.9M. This variance is against the latest budget shown against each department which have now had the 2008-09 Improvement Plan budget savings taken from them. The Environment and Leisure budgets have also had a total of £3.3M approved additional funding added to them from the contingency.

2.4The table also shows that although there is a projected overspend by departments of £2.9M, there is now £4.3M of funding available (the Improvement Plan savings that have now been removed from departments’ budgets) and there is still £1.7M of contingency fund available.

Table 1 PROJECTED OUT TURN 2008-09 Department Latest Approved Projected Budget Out Turn Variance £000 £000 £000 Corporate Services 1.8 1.8 0 Finance 8.6 8.6 0 Central Unit 0.1 0.1 0 Childrens Services & Lifelong Learning 50.1 52.6 2.5 Leisure Services 16.6 17.8 1.2 Environment 34.0 34.2 0.2 Community Services 63.1 62.1 (1.0) Net Service Spend 174.3 177.2 2.9

Improvement Plan Savings - taken from Depts 4.3 2.5 (1.8) (£4.3M now available to meet IP costs) Contingency Fund (£1.7M still available) 1.7 0 (1.7) Net Service Spend 180.3 179.7 -0.6 (with IP savings and contingency)

3.0MANAGEMENT OF COUNCIL RESOURCES IN FUTURE MONTHS OF 2008-09, 2009-10 AND BEYOND 3.1 Reports will continue to be presented monthly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue Financial Monitoring: Month Ended 30th November 2008Report 18 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Revenue Financial Monitoring - Month Ended 30th November 2008This decision
  2. Monthly Revenue Financial Monitoring -Decided
  3. Monthly Revenue Financial Monitoring -Noted
  4. Monthly Revenue Financial Monitoring - 31 December 2011 (CR12)Noted
  5. Monthly Revenue Financial Monitoring - 30th November 2011 (CR11)Noted
  6. Monthly Revenue Financial Monitoring - 31 October 2011Noted

More from Hounslow Executive

All decisions
MeetingDecisionOutcome
8 Mar 2011 Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. Decided Open
8 Mar 2011 Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... Decided Open
8 Mar 2011 Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. Noted Open
8 Mar 2011 Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... Agreed Open
8 Mar 2011 Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies