Resolved
The Executive endorsed the principle of the various projects set out in the report and noted the programme of work set out in Section 6 which will need to be undertaken in the coming months with potential partners.
Executive noted this item on Tuesday 24 February 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive endorsed the principle of the various projects set out in the report and noted the programme of work set out in Section 6 which will need to be undertaken in the coming months with potential partners.
Contact: Michael Jordan Tel: 020 8583 5325 E-Mail: [email protected] FP No. ENV018
Executive – 24 February 2009
BOSTON MANOR SPORTING & HERITAGE REGENERATION AREA
Report by: Cllr. Peter Thompson – Leader
Summary This report alerts the Executive to discussions which are now under way with various organisations about the future of the Council’s Boston Manor House and Park and the adjoining playing fields in the ownership of the London Playing Fields Foundation (LPFF).
The aim of these talks is to find solutions to some, and preferably all, of a number of leisure, sporting and heritage issues. These include: o The need to restore and find a viable future use for Boston Manor House, a Grade 1 listed building, and one of a number of Council properties on English Heritage’s Heritage at Risk Register. o A complementary desire to restore the immediate grounds of the House as part of a wider enhancement of Boston Manor Park in which it sits. o The desire to improve the leisure and sporting facilities available in the Park. o The desire to improve the sporting facilities which are also on offer in the adjoining playing fields which are run by the LPFF and thereby achieve a combined sporting “hub”.
In the past there have been exploratory discussions with officers from a number of relevant heritage and sporting organisations and also with GSK, whose headquarters adjoin the site to the south. The aim of these talks has been to explore the potential for some form of public, private and voluntary sector partnership.
At the same time, there have been continuing discussions about a potential landmark ‘Gateway’ structure which might be constructed on the LPFF playing fields either side of the M4 motorway. The aim here would be to mark and celebrate the visitor’s entry into the heart of Hounslow / London and, at the same time, to generate some rental income for the LPFF to be used to support its sports plans.
GSK’s involvement in these discussions also raises questions concerning car parking as the company is seeking to fully utilise its headquarters and GSK has indicated that current car parking levels are seen as inhibiting this.
1. Recommendations 1.1 That the Executive endorse the principle of these various projects and note the programme of work set out in section 6 which will need to be undertaken in the coming months with potential partners. 2. Background Boston Manor House 2.1 Boston Manor House, which is in Council ownership, is an outstanding example of a Jacobean Manor House dating from 1622 with alterations and wing extensions up until the nineteenth century. It is a Grade 1 listed building which is rightly regarded as an architectural gem of national significance.
2.2Boston Manor House has an interesting history, having been occupied for more than 300 years by the Clitheroe family, and possesses a remarkable range of original features including richly decorated plaster ceilings and other surviving décor and interior design from the 17th century.
2.3Unfortunately, the building has featured on the English Heritage National Register of Buildings at Risk since 2001 and was one of ten cases studies in their 2004 study “Mansions at Risk in Public Parks in London”. English Heritage has now formally written to the Council seeking assurances that the Council will address its heritage responsibilities and undertake essential repairs and renovations.
2.4An initial building conditions survey was carried out by Richard Griffiths Architects during 2007, funded generously by GSK. This noted the House’s structural problems, the lack of sufficient ongoing maintenance and its continuing vulnerability to vandalism. The report sets out a prioritised list of the repair works.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Boston Manor Sporting and Heritage Regeneration AreaReport | 36 KB | DownloadRead as text |
Follow Executive at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Mar 2011 | Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. | Decided | Open |
| 8 Mar 2011 | Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... | Decided | Open |
| 8 Mar 2011 | Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. | Noted | Open |
| 8 Mar 2011 | Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... | Agreed | Open |
| 8 Mar 2011 | Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.