Exploring a suitable option for the Gunnersbury Park Estate (ENV 052)

Agreed Executive 1 paper

Executive agreed this item on Tuesday 18 January 2011. Below is the council's own wording, with the papers it was decided on.

Item77

Resolved

The Executive agreed the recommendations of the report as follows: The Executive noted progress on the Gunnersbury Project and adopted the Conservation Management Plan (CMP) as formal guidance. The Executive agreed that suitable consultants are procured in accordance with the Council’s procurement rules by Ealing on behalf of itself and Hounslow Council to fully explore viable options within the aims of the CMP and available funding. The Executive agreed that a project team is established to develop a preferred option. The Executive agreed that this option is brought back to the Executive for ratification and submission of a Major Grant Application to the Heritage Lottery Fund (HLF) in November 2011. The Executive agreed that S106 (scheme 11) can be used to fund the Council’s share of the cost of the development of an application to the HLF. The Executive noted that this process will also consider future governance options. The Executive agreed the recommendations of the report as follows: The Executive noted progress on the Gunnersbury Project and adopted the Conservation Management Plan (CMP) as formal guidance. The Executive agreed that suitable consultants are procured in accordance with the Council’s procurement rules by Ealing on behalf of itself and Hounslow Council to fully explore viable options within the aims of the CMP and available funding. The Executive agreed that a project team is established to develop a preferred option. The Executive agreed that this option is brought back to the Executive for ratification and submission of a Major Grant Application to the Heritage Lottery Fund (HLF) in November 2011. The Executive agreed that S106 (scheme 11) can be used to fund the Council’s share of the cost of the development of an application to the HLF. The Executive noted that this process will also consider future governance options.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Executive

Summary

This report seeks approval to explore viable options and progress the Gunnersbury Park regeneration project in order that an application might be made to the Heritage Lottery Fund in November 2011

If a way forward is not identified the heritage will be increasingly at risk and eventually lost to future generations.

Recommendations

That the Executive:

1.1note progress on the Gunnersbury Project and adopt the Conservation Management Plan (CMP) as formal guidance 1.2 agrees that suitable consultants are procured in accordance with the Council’s procurement rules by Ealing on behalf of itself and Hounslow Council to fully explore viable options within the aims of the CMP and available funding. 1.3 agrees that a project team is established to develop a preferred option 1.4 agrees that this option is brought back to Executive for ratification and submission of a Major Grant Application to the Heritage Lottery Fund (HLF) in November 2011. 1.5 agrees that S106 (scheme 11) can be used to fund the Council’s share of the cost of the development of an application to the HLF 1.6 note that this process will also consider future governance options 2.0 BACKGROUND

The Significance and Current condition of Gunnersbury 2.1 The Gunnersbury Park Estate has twenty-two listed buildings of special architectural or historic interest situated in a landscape which has significant importance in its own right. This combination of important historic buildings and landscape has lead to English Heritage (EH) to describe Gunnersbury as Grade II* in their ‘Parks and Gardens Register’.

2.2Ealing and Hounslow have shared joint ownership of Gunnersbury since 1965 when a joint committee was established to manage the estate. Budgetary constraints have resulted in under investment for many years and led to the decline and poor management of the buildings, landscape, park infrastructure and sports facilities. For this decline to be addressed significant investment is required.

2.3EH describes Gunnersbury as one of the most sensitive and complex cases in the Region. Although the estate is of national significance its increasingly poor condition has led EH to designate it as one of the top 12 ‘at risk’ properties in England with extensive, significant problems, high vulnerability and a trend of decline.

The Conservation Management Plan 2.4 To fully understand the significance and problems of Gunnersbury a Conservation Management Plan (CMP) was undertaken in 2008. This confirmed Gunnersbury is a historic park of national significance and important to the local community for both formal and informal recreation and wildlife.

2.5The CMP also confirmed that despite the parks value it is in decline. A ‘do nothing’ option would result in the significant loss of historic buildings on site, be detrimental to the landscape and would be impossible to reverse. Without timely, effective action now, Gunnersbury, as it exists today will not survive.

2.6The CMP outlined the benefits of tackling the decline and confirmed that a vast amount of resources are required. It recommended that an Options Appraisal be commissioned to identify those resources and an option to deliver the desired benefits.

The Options Appraisal 2.7 Jura Consultants completed an Options Appraisal in 2009 consistent with the principles of the CMP. The brief required the solution to be holistic and tackle all the issues. The solution would also have to be both deliverable and sustainable. 2.8 The Options Appraisal was warmly welcomed by English Heritage. EH is firmly of the view that the repair and long-term sustainable use of heritage assets must be the priority of the preferred option. Some gaps were identified where use of smaller buildings and the repair of the landscape had not been adequately considered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exploring a suitable option for the Gunnersbury Park Estate (ENV 052)Report 208 KB DownloadRead as text

More from Hounslow Executive

All decisions
MeetingDecisionOutcome
8 Mar 2011 Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. Decided Open
8 Mar 2011 Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... Decided Open
8 Mar 2011 Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. Noted Open
8 Mar 2011 Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... Agreed Open
8 Mar 2011 Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... Agreed Open