The Executive: Noted the results of revenue budget monitoring at 31 October 2010 Agreed action to contain out turn within the Council’s corporate budget for 2010-11. The Executive: Noted the results of revenue budget monitoring at 31 October 2010 Agreed action to contain out turn within the Council’s corporate budget for 2010-11.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
This report advises Executive of the issues arising from revenue budget monitoring at 31 October 2010.
Recommendation
That Executive:
• Note the results of revenue budget monitoring at 31 October 2010 • Agree action to contain out turn within the Council’s corporate budget for 2010-11
Background
2.1This report is a brief review of the Council’s Revenue Budget for 2010-11, based on monitoring carried out for the period ending 31 October 2010.
2.2The report compares the approved revised budget for each department with the department’s projection of its anticipated out turn for 2010-11. The trends indicated by these figures have been discussed with the departments concerned and these are analysed in greater detail below. The issues that departments will need to address are also set out below the table.
2.3Departments have provided projections of their expected net expenditure up to the end of the financial year including the actions being taken by management to ensure that departments contain their expenditure within the approved budget. It is essential that such active steps continue to be taken to manage expenditure and remain within the budget.
2.4The table below shows the projected position at 31 March 2011. The revised budget represents the original approved budget, adjusted to take account of the cuts approved by Executive on 27 July 2010 and 19th October 2010, the loss of £2.1m Area Based Grant in 2010-11 and any other approved budget changes. The table also shows the variance between the projected year end expenditure and the revised budget. 1 PROJECTED OUT TURN 2010-11
Department Original Revised Projected Variance Budget Budget Out Turn £M £M £M £M
2.5The variance reflected above assumes that the departments concerned fully achieve the in year savings approved by Executive at earlier meetings.
2.6The Executive has asked that these monthly monitoring reports include a section dealing in more detail with variances in individual departments on a rolling programme, dealing with each department in turn. This report provides such details for the Environment department at Appendix A. In the next revenue monitoring report to Executive a similar level of detailed information will be provided for another department and so on for each future report.
2 3.0 CS&LL Budget Monitoring 2010-11
3.1At 31 October 2010 the Director of Children’s Services & Lifelong Learning had identified projected adverse variances of £0.6m for the year but action is being taken to ensure that the department’s overall expenditure is contained within the budget by the end of 2010-11.
3.2The main reasons for this £0.6m pressure are as follows: -
• £0.5m additional social workers required to address an increase in case loads • £0.2m overspend on integrated children system IT costs • £0.65m, unachieved Improvement Program Savings for which the department is seeking to identify savings • Less £0.4m potential savings from unfilled vacancies, delays in recruitment and other under spends. • Less £0.3m uncommitted under spends from the Building Schools for the Future program and other capital project work.
3.3A range of smaller measures are being taken to offset the net overspending of £0.65m referred to in paragraph 3.2. including managing, in year, the structural deficit of £0.65m. These measures include savings on staff advertising, making maximum use of available grant income and reviewing the charge to capital for staff involved on capital schemes. It is expected that these measures will save a further £0.1m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.