Resolved
Resolved - That progress on the on the West London Residual Waste Services procurement be noted.
West London Waste Authority noted this item on Friday 27 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That progress on the on the West London Residual Waste Services procurement be noted.
WEST LONDON WASTE AUTHORITY
Report of the Director and Chief Technical Advisor 27 January 2012
Joint Municipal Waste Management Strategy: Procurement Update
SUMMARY This report provides an update on the procurement of the West London Residual Waste Services contract. It includes the short listing of bidders for the next round of the procurement, recent discussions with the Mayor of London’s GLA officers and an update on High Speed Rail Link 2 (HS2).
RECOMMENDATION(S) The Authority is asked to:-
1) Note the progress on the West London Residual Waste Services procurement
1. Introduction – The procurement of new residual waste treatment services supports a number of the Joint Municipal Waste Management Strategy policies and will address the increasing costs of landfilling waste.
2. Background - The Authority published its OJEU notice for the procurement on Thursday 12 May 2011. Following a pre-qualification (PQQ) process eight bidders were invited to take part in dialogue to develop outline solutions.
3. ISOS Bids received: all eight of the short listed the PQQ applicants invited to participate in dialogue returned submissions by the deadline of noon on 31 October 2011. The companies who submitted ISOS bids were:- • Cory Environmental Ltd • Covanta Energy • E.ON Energy from Waste • FCC /Waste Recycling Group Ltd • SITA UK Ltd • Veolia ES Aurora Ltd • Viridor Waste Management Ltd • Wheelabrator Technologies Incorporated
4. Overview of outline solutions – As part of the procurement process, dialogue meetings took place with all of the bidders. A range of issues were discussed focusing mainly on technical, planning and sites issues. Legal and commercial breakout sessions took place with most bidders. Common proposals of all the outline solutions follows:
• The Authority received eight compliant bids from the eight organisations invited to participate in dialogue • All bidders wish to use some or all of the Authority sites at least as delivery points
• The potential impact of HS2 on the Victoria Road site has been addressed by bidders in their submissions
• A small number of bidders brought forward additional partners as part of their ISOS submission. This is not unusual in a procurement of this nature and was envisaged by the terms of the PQQ and ISOS documentation. The introduction of additional partners is acceptable subject to PQQ checks and a “no worse” (or improved) position for the Authority as a consequence
• All bidders are proposing a “two part” treatment process using more than one site as part of their solution
• Most bidders have met with both the GLA and local planners to discuss their solutions
5. Evaluation and short listing - Detailed evaluation of the solutions submitted by bidders was completed by the Authority Project Team supported by the external advisors. At its meeting on 16th December the Project Board agreed to shortlist four companies to be invited to continue dialogue and develop detailed solutions (ISDS).
• Cory Environmental Limited • EON Energy from Waste consortium including Tata Chemicals Europe Ltd and Grundon Waste Management Ltd • SITA UK Ltd; and • Viridor Waste Management Ltd
6. Notification of Shortlisting: The Authority wrote to all the bidders informing them of the outcome of the ISOS process on 21st December. Briefings for Authority staff who will be subject to TUPE transfer were held the same day and a press release published. Authority members and borough Directors of Environment and Finance received a confidential briefing note on 20th December. The unsuccessful bidders were provided with detailed feedback on scoring and meetings were held with all four unsuccessful bidders on 9th January 2012.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Joint Municipal Waste Management Strategy Procurement UpdateReport | 270 KB | DownloadRead as text |
Follow West London Waste Authority at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Mar 2016 | Budget Monitoring Report Period 10 (January)Resolved - (a) That the current financial position in 2015/2016 to Period 10 and Key Performance Indicators be noted.... | Noted | Open |
| 18 Mar 2016 | Annual Procurement PlanResolved - (a) That the Annual Procurement Plan for 2016/2017 be approved. (b) That that the Authority’s contract reg... | Approved | Open |
| 18 Mar 2016 | Corporate GovernanceResolved - (a) That the business plan for 2016/2019 set out in appendix 1 be approved. (b) That the arrangements for ... | Approved | Open |
| 18 Mar 2016 | Exclusion of Press and PublicResolved - That the public and press be asked to leave the meeting during discussion of the following item because ex... | Decided | Open |
| 29 Jan 2016 | Budget Monitoring Report Period 8 (November)Resolved - a) That the current financial position in 2015/16 to Period 8 and Key Performance Indicators be noted. b) ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.