Resolved
Resolved - (a) That the current position with the contracts as set out in the report be noted. (b) That progress with the wood and mattress tenders be noted.
West London Waste Authority noted this item on Friday 12 December 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - (a) That the current position with the contracts as set out in the report be noted. (b) That progress with the wood and mattress tenders be noted.
WEST LONDON WASTE AUTHORITY
Report of the Director and Chief Technical Advisor 12 December2014
Joint Waste Management Strategy Contracts Update
SUMMARY This report provides an update on the Authority’s waste treatment contracts.
RECOMMENDATION(S) The Authority is asked to:-
1) Note the current position with the contracts
2) Note the progress with the wood and mattress tenders
West London Residual Waste Services Contract
1. Introduction – The West London Residual Waste Services contract delivers Policy 6 of the Authority’s Joint Municipal Waste Management Strategy. “West London Waste Authority and constituent boroughs will seek a residual waste management solution in accordance with the waste hierarchy that presents value for money and offers reliability in the long term”.
2. Background – At the meeting on 27th June 2014 officers reported that the West London Residual Waste Services contract had mobilised on 19th January 2014. Construction of the extension to the Victoria Road waste transfer station had been delayed by five months due to a requirement to resolve planning preconditions. The construction of the EfW facility at Severnside was behind schedule by 35 days, but the contractor, SITA, were confident that this would be recovered. Construction of the upgrade work at Transport Avenue waste transfer station is on programme and due to be complete by March 2015.
3. Provision of Interim Services – SITA have been providing interim services for 10 months. Although there were a few minor issues in the first weeks of the contract with minor queuing of borough collection vehicles at Transport Avenue waste transfer station, the service has settled down and is currently running smoothly. For interim services, the waste is transported by rail to SITA’s New Crosby landfill site near Scunthorpe, Lincolnshire.
4. Planning consents – Planning consent for the construction of a new bulk waste reception hall at Victoria Road was granted by Hillingdon Council on the 11th February 2014. The consent contained a number of preconditions which needed to be discharged prior to construction commencing. On the 4th March SITA West London Ltd (SWL - the contracted SPV) wrote to the Authority stating that in their view they believe that the preconditions constitute an unsatisfactory planning decision due to requirements for sustainable drainage and land remediation. The Authority do not accept this position. There has been a chain of correspondence between the Authority and SWL. SWL have now discharged all the preconditions for Victoria Road, and the Engineering Procurement Construction EPC contractor (Interserve) mobilised to site on the 28th November 2014. It should be noted that the delay in commencement of the works at Victoria Road is not expected to affect the start date for full services in the summer of 2016.
5. Construction programme – The construction of the EfW plant at Severnside commenced in December 2013. . At the time of writing the delay, reported in paragraph 2 has been reduced to 7 days and it is anticipated that this will be recovered by the 4th February 2015 and that the planned completion date of August 2016 will be achieved. The works at Transport Avenue were commenced on programme on the 5th May by the EPC contractor (Interserve) and will be completed in Spring 2015 as programmed.
6. Capital Contributions – To date capital contributions of £21.4m (of a total contribution of £60m) has been made to SITA for the construction of the EfW plant. These payments are linked to construction milestones certified by an independent consulting engineer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Joint Waste Management Strategy Contracts UpdateReport | 4 pages | DownloadRead as text |
Follow West London Waste Authority at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Mar 2016 | Budget Monitoring Report Period 10 (January)Resolved - (a) That the current financial position in 2015/2016 to Period 10 and Key Performance Indicators be noted.... | Noted | Open |
| 18 Mar 2016 | Annual Procurement PlanResolved - (a) That the Annual Procurement Plan for 2016/2017 be approved. (b) That that the Authority’s contract reg... | Approved | Open |
| 18 Mar 2016 | Corporate GovernanceResolved - (a) That the business plan for 2016/2019 set out in appendix 1 be approved. (b) That the arrangements for ... | Approved | Open |
| 18 Mar 2016 | Exclusion of Press and PublicResolved - That the public and press be asked to leave the meeting during discussion of the following item because ex... | Decided | Open |
| 29 Jan 2016 | Budget Monitoring Report Period 8 (November)Resolved - a) That the current financial position in 2015/16 to Period 8 and Key Performance Indicators be noted. b) ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.