AI summaryHounslow Cabinet noted progress on its four Delivery Plan portfolios and approved closing the Adult Social Care System Reform and Children's Model of Care programmes, with underspends returned to the Transformation Fund.
Written from the decision and the officer reportPDF Pro
OutcomeAgreed
Money£537k delivered in Q4against a £2.06m target for FY25/26, with c. £1.3m outstanding
What happens nextUnderspends return to Transformation Fundremaining programme savings tracked through service-level assurance
Who it affectsAll four Delivery Plan portfoliosPeople, Place, Capital and Digital programmes
What was decided
Cabinet noted progress to date on the People, Place, Capital and Digital Portfolios, as set out in Appendices 1 to 4 of the report.
Cabinet approved closing the Adult Social Care System Reform Programme and returning its underspend to the One Hounslow Transformation Fund.
Cabinet approved closing the Children's Model of Care Programme and returning its underspend to the One Hounslow Transformation Fund.
Why
Regular monitoring supports the Council's best value duty under the Local Government Act 1999, which requires continuous improvement in how functions are exercised. Report 10.2, P53
Of the £2.06m savings target for FY25/26, £537k was delivered by year end, leaving c. £1.3m outstanding across the Adult Social Care, Transforming our Community Experience, Support Services and Third Party Spend programmes. Report 9.6, 9.8
Two programmes have completed their main delivery and remaining activity is now best managed through business as usual, with c. £3.18m and £955k of future savings previously attributed to them now tracked at service level. Report 9.11
What happens next
Up to c. £860k of Transforming our Community Experience (TCE) programme savings is expected to be deliverable in FY26/27 under tighter programme control and benefit monitoring. Report P26
Work to recover debt from high-cost Adult Social Care clients will continue in FY26/27 through business as usual, with monitoring through corporate savings assurance. Report P27
Income from commercialising events at Council buildings is expected to be delivered in full in FY27/28 following completion of the implementation phase. Report P28
The money
£5.2m indicative savings to be delivered by the People Portfolio by the end of FY27/28 Report 9.2
£365k savings delivered in FY24/25 across Third Party Spend, Organisation Design and Safer Communities Report 9.4, P10
£911k FY24/25 savings delayed and carried forward into FY25/26 Report 9.5, P15
£1.1m further savings agreed by Cabinet in February 2025 for inclusion in the 2025/26 Revenue Budget Report 9.6
£2,006,000 total Delivery Plan savings target for FY25/26 Report 9.7, P24
£537,000 savings delivered at end of Q4 FY25/26, including £87k accelerated from FY26/27 Report 9.7, 9.8, P24
£2,133,000 indicative additional savings identified for FY26/27 across remaining Delivery Plan programmes Report 9.10, P37
£1,916,000 indicative additional savings identified for FY27/28 across remaining Delivery Plan programmes Report 9.10, P37
£4,049,000 total indicative additional savings across FY26/27 and FY27/28 Report 9.10, P37
£6,939,000 total indicative benefits identified via business cases for programmes remaining open Report 9.12, P47
£1,230,000 total projected benefits delivered to date via Delivery Plan activity Report 9.12, P47
Options considered
Chosen: Close Adult Social Care System Reform Programme and move to Business as Usual. Main programme delivery is complete and remaining activity can be managed through services. Report 9.11
Chosen: Close Children's Model of Care Programme and move to Business as Usual. Main programme delivery is complete and remaining activity can be managed through services. Report 9.11
Rejected: Continue to track Adult Social Care and Children's Model of Care savings through the Delivery Plan. Activity has transitioned to services, so ongoing savings will be tracked at service level via corporate assurance rather than Delivery Plan monitoring. Report 9.11
Implications
Financial: c. £1.3m of FY25/26 savings are outstanding, with delivery expected in FY26/27 and FY27/28. Report 9.8
Legal: The Council's best value duty under the Local Government Act 1999 supports regular Delivery Plan monitoring. Report 10.2
Equalities: No direct implications arise from the Delivery Plan, but equalities considerations are built into each project's business case through an Equalities, Diversity and Inclusion case. Report 11.1, 11.2
Climate: No direct implications arise from the Delivery Plan, but climate considerations are built into each project's business case through a Climate Impact case. Report 12.1, 12.2
Staffing: A range of other implications, including staffing, workforce, accommodation and property, will be identified in business cases and managed under the Council's Constitution and relevant policies. Report 13.1, P62
Who and where
People using Adult Social Care services in the London Borough of Hounslow Report 9.11, P27
Children and families supported through the Children's Model of Care programme Report 9.11
Staff affected by the Support Services programme, including the transformation of the Council's HR function Report 9.8
Council services receiving funding from the One Hounslow Transformation Fund Report 9.1, P2
Users of Council buildings where events are commercialised to generate income Report P28
Timeline
Q4 2025/26: End of year position: £537k of savings delivered against a £2.06m target. Report 9.7, 9.8
FY26/27: Up to c. £860k of Transforming our Community Experience savings expected, plus delivery of recovered debt savings from high-cost Adult Social Care clients. Report P26, P27
FY27/28: Commercialisation of events at Council buildings expected to deliver the £150k saving in full. Report P28
By end of FY27/28: An indicative £5.2m of savings to be delivered by the People Portfolio. Report 9.2
Plain English for the jargon
Business as Usual: Activity managed through ongoing council services rather than as a separate project or programme.
One Hounslow Transformation Fund: The Council's funding pot for delivering change programmes, with drawdowns approved by Cabinet or under officer delegation.
Best value duty: Legal duty under the Local Government Act 1999 requiring councils to secure continuous improvement in how their functions are exercised.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4
Resolved
Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in Appendix 1 of the submitted report. 2. Approve the transition of the Adult Social Care System Reform Programme into Business as Usual and return of the programme underspend to the Council’s Transformation Fund. 3. Approve the transition of the Children’s Model of Care Programme into Business as Usual and return of the programme underspend to the Council’s Transformation Fund. 4. Note progress to date with the projects within the Place Portfolio as set out in Appendix 2 of the submitted report. 5. Note progress to date with the projects within the Capital Portfolio as set out in Appendix 3 of the submitted report. 6. Note progress to date with the projects within the Digital Portfolio as set out in Appendix 4 of the submitted report.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Member Reporting Councillor Shantanu Rajawat, Leader of the Council
Contact Details Andrew Cox, Executive Director – Strategy and Transformation [email protected]
For Consideration By Cabinet
Date to be Considered 14 July 2026
Deadline for call-in N/A
Implementation Date N/A (if not Called In)
Affected Wards All wards
Approved by Andrew Cox – Executive Director – Strategy and Transformation
Official 1. Recommendations
Cabinet is asked to:
1. Note progress to date with the programmes within the People Portfolio as set out in Appendix 1
2. Approve the transition of the Adult Social Care System Reform Programme into Business as Usual and return of the programme underspend to the Council’s Transformation Fund
3. Approve the transition of the Children’s Model of Care Programme into Business as Usual and return of the programme underspend to the Council’s Transformation Fund
4. Note progress to date with the projects within the Place Portfolio as set out in Appendix 2
5. Note progress to date with the projects within the Capital Portfolio as set out in Appendix 3
6. Note progress to date with the projects within the Digital Portfolio as set out in Appendix 4
2. Report Summary
2.1The Delivery Plan was approved by Cabinet on 5 July 2022 and Council on 20 September 2022.
2.2This report provides an update to Cabinet on progress with the Delivery Plan, with a particular focus on progress to date on projects and programmes within all four portfolios, highlighting their overall status, what has been achieved and the key activity planned over the coming period.
2.3Two programmes in the People Portfolio – Adult Social Care System Reform and the Children’s Model of Care Programme – have concluded, with the deliverables and outcomes they have achieved set out in section 4.6, with the request through this report for approval to transition them to Business as Usual.
3. Background and links to Corporate Priorities
3.1The Delivery Plan, which was approved by Cabinet on 5 July 2022 and Council on 20 September 2022, describes the activity that the Council will deliver to meet the priorities, objectives and ambitions set out within the Corporate Plan 2022-2026, as well as the process and approach that will be followed to monitor progress and ensure success.
Official 3.2. It details the Council’s large, ambitious programmes and projects that impact across the whole (or large part of) the organisation, place or population. It also details the activity that is taking place to ensure that the Council has the required systems, processes and structures established and is prioritising its capital investment to enable the delivery of high-quality public services.
3.3All projects and programmes in the Delivery Plan follow the One Hounslow Approach to Project and Programme Management (PPM), with business case development, benefits tracking and regular monitoring being fundamental to this approach. The approach is recognised as adding rigour and corporate visibility to ensure well informed decision-making in accordance with the strategic priorities set out in the Corporate Plan. This approach also helps to ensure that due consideration is given to equalities, climate, value for money and risk management for each project or programme brought forward for approval.
3.4In December 2022, as part of the Delivery Plan Monitoring Q2 2022/23 report, Cabinet agreed that the Delivery Plan be split into two portfolios: People and Place. The People Portfolio is made up of programmes and projects associated with transforming the council’s services and offer to residents. The Place Portfolio is made up of programmes and projects associated with the development activity to the built and natural environment, primarily capital funded, to transform a place in line with the council’s strategic objectives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.