The Cabinet: Noted the progress of the project; and Agreed for the reasons set out in the report, the land parcels marked blue and yellow on Plan B appended to the report, are no longer required for the purpose for which they are held and accordingly officers be authorised to take all steps necessary for the appropriation of the land for planning purposes. The Cabinet: Noted the progress of the project; and Agreed for the reasons set out in the report, the land parcels marked blue and yellow on Plan B appended to the report, are no longer required for the purpose for which they are held and accordingly officers be authorised to take all steps necessary for the appropriation of the land for planning purposes.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
The purpose of this report is to provide an update of progress on the project and to seek authority for the appropriation to planning purposes of open space land and other land owned by the Council on the New Heston Road, Heston as marked blue and yellow on the attached plan under Section 122 of the Local Government Act 1972, in order to enable the powers in Section 237 of the Town and Country Planning Act 1990 to be used to facilitate the redevelopment of these plots.
Before authorising the appropriation, the Council is required to satisfy the statutory criteria (which are set out in the report) and acting in good faith to consider (a) whether or not the land is required for the purposes for which it is held, and (b) whether or not the land should be appropriated to planning purposes.
Background
2.1On 8 November 2011 Cabinet approved the proposals to replace the Heston leisure centre with a new improved leisure centre on the current footprint along with improvements to Heston Park which are to be primarily funded from enabling housing developments. Plan A in the appendix identifies the whole site that is subject to the redevelopment as outlined in a red line identifying the three sites that will be used for the enabling housing developments (namely sites A, B and C). In addition the plan also shows the site known as 21 New Heston Road (coloured purple) which is owned by Shepherds Bush Housing Association and is
-1- now included in the overall development proposals to provide an improved entrance and parking for the leisure centre. The area shaded green is currently designated open space of which parts are to be formally appropriated for planning purposes as set out in this report. Plan B in the appendix shows the parcels of land coloured blue (open space land) and yellow (other land) which form part of the development sites that are to be appropriated.
2.2A single hybrid planning application will be submitted in mid February 2013 for the whole development site. The planning applications will consist of outline planning for residential development of circa 220 units on Sites A and B which will then be sold on the open market for development by the purchasers subject to them obtaining full planning approval on any reserved matters. A full planning application will be submitted for the development of a new leisure centre, relocated scouts building, housing development of 14 units on Site C (on behalf of Shepherds Bush Housing Association) as well as improvements to Heston Park. Heads of Terms relating to the SBHA development are being negotiated where SBHA will be responsible for paying all costs for the planning application to be developed and submitted on their behalf. SBHA will be undertaking the development at their sole cost once the land swap is completed, subject to planning permission being granted.
2.3Following the Cabinet approval, the procurement of the design team was undertaken in accordance with the OJEU tender requirements where Studio E Architects LLP were appointed in June 2012 as the lead design team. The designs have now been progressed to the outline stages for a planning application to be submitted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.