The Cabinet agreed the recommendations of the report as follows: The Cabinet approved the trial (to commence in May 2013) for a Wheeled Bin for the collection of black sack rubbish only, from 7,500 properties across the borough, including a budget for hiring a vehicle with bin lifting equipment, procurement and delivery of 7,500 x 140 litre bins, and a budget to communicate the scheme. The total for the scheme will be £152,987, off set by £65,000 from the Innovation Scheme. This report asked for a further £87,987. The Cabinet approved a variation of the Sita contract to allow for the provision of the trial for Wheeled Bins as set out in recommendation 1 above (1.1 of the report). There are no financial implications to vary the contract for this scheme. The Cabinet agreed the recommendations of the report as follows: The Cabinet approved the trial (to commence in May 2013) for a Wheeled Bin for the collection of black sack rubbish only, from 7,500 properties across the borough, including a budget for hiring a vehicle with bin lifting equipment, procurement and delivery of 7,500 x 140 litre bins, and a budget to communicate the scheme. The total for the scheme will be £152,987, off set by £65,000 from the Innovation Scheme. This report asked for ... view the full minutes text for item 145.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.1To approve the trial (to commence in May 2013) for a Wheeled Bin for the collection of black sack rubbish only, from 7,500 properties across the borough, including a budget for hiring a vehicle with bin lifting equipment, procurement and delivery of 7,500 x 140 litre bins, and a budget to communicate the scheme. The total for the scheme will be £152,987, off set by £65,000 from the Innovation Scheme. This report is asking for a further £87,987.
1.2To approve a variation to the Sita contract to allow for the provision of the trial for Wheeled Bins as set out in recommendation 1.1. There are no financial implications to vary the contract for this scheme.
Background
2.1Hounslow residents currently living in houses receive a black sack collection for their household rubbish. Black sacks are placed out at the front edge of each property, by 7am on the collection day. There is no limit to the number of sacks placed out by each household.
2.2Black sacks often get ripped open by vermin leading to littering and spillage of rubbish over the roads and pavements, particularly if the sacks contain food waste. 2.3 Evidence shows that by containing this waste it reduces incidences of rubbish being accessed by vermin and therefore leads to an improved street scene. Additionally as the waste is contained it limits the capacity of waste that can be placed out, and as a result encourages people to use the other available option of recycling it instead. This leads to increased recycling, and less waste going to landfill.
2.4The trial will be rolled out within 5 areas of the borough with 1,500 properties in each of the areas. The suggested wards for the trial are Chiswick Riverside, Syon, Heston West, Hounslow West and Feltham West. A smaller area within each of these wards will receive the bins for the trial.
2.5Each household will receive a 140 litre bin to use for the disposal of residual waste. This method will be replacing the current collection through black sacks.
2.6The collection of residual rubbish will remain weekly, and there will be no impact or changes to the day of collection. All residents will continue to have their waste and recycling collected on the same day. There will also be no impact or changes to the recycling service these residents receive.
2.7The trial will run for 6 months, after which time there will be a review of its success. Any extension to the trial will be considered following this review, and subject to successful consultation with residents in the trial area.
2.8The trial will impact on only 1 residual waste collection vehicle. SITA are able to hire a vehicle through its internal Fleet Management which will take 1-2 weeks to order.
Financial implications
3.1The cost of hiring a vehicle with lifting equipment by SITA would be £600 per month (costing £3,600 over the trial period); this includes off hire of the vehicle that would then not be in use. However, there is no additional cost to the Counctil to vary the contract for the provision of this scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.