The Cabinet noted the following: Projected revenue outturn for the General Fund. Projected revenue outturn for the Housing Revenue Account (HRA). Performance against the key corporate financial indicators and summary of debts approved for write off. Approval of £127,250 from the Performance Improvement Fund for the Civic Centre Relocation Outline Feasibility Study. Update on the delivery of 2013/14 savings. The Cabinet noted the following: Projected revenue outturn for the General Fund. Projected revenue outturn for the Housing Revenue Account (HRA). ... view the full minutes text for item 117.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title CR89 - Monthly Financial Monitoring Report Member Reporting Councillor Jagdish Sharma, Leader of the Council Contact Details Name: Clive Palfreyman, AD Strategic Finance Telephone: 020 8583 2430 Email: [email protected] For Consideration By Cabinet Date to be Considered 14 January 2014 Implementation Date if 7 days after decision Not Called In Affected Wards All Keywords/Index Financial Monitoring, Period 8
1 Details of Recommendations Cabinet members are asked to note the following:-
1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators and summary of debts approved for write off. 4. Approval of £127,250 from the Performance Improvement Fund for the Civic Centre Relocation Outline Feasibility Study. 5. Update on the delivery of 2013/14 savings.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can expect to benefit, link to Values notice a difference The Council will manage its cost pressures to ensure - that costs are managed within the approved budget.
2 Report Summary This report presents the projected revenue outturn for 2013/14 and reports a £1.0m over spend against revised budget on departmental revenue spend and a £7.3m under spend against revised budget on corporate budgets, giving a total net under spend of £6.3m.
This report also presents a projected surplus of £0.061m for the 2013/14 HRA. This represents a favourable variance of £0.137m against the revised HRA budget.
The report provides an update on the Council’s performance against the key corporate financial indicators and a summary of the write offs approved in this period. 3 Reason for Decision and Options Considered 3.1 Members are not asked to approve any recommendations in this report.
4 Key Implications 4.1 There are no key implications to be considered.
5 Financial Details Financial Impact On The Budget 5.1 There are no decisions proposed in this report that have an impact on the overall Council’s revenue budget. An update on the Council’s financial performance is provided below.
General Fund 5.2 The table below provides a summary of each Directorate’s performance against the Council’s approved 2013/14 Revenue Budget and is based on department’s projections of their anticipated outturn for the year. See Appendix A for the detailed analysis.
Variance Reported Original Revised Projected last Department Budget Budget Out Turn Variance period Movement £M £M £M £M £M £M Chief Executive 7.0 7.0 6.8 (0.2) (0.2) 0.0
5.3The projected revenue outturn anticipates a £1.0m over spend on departmental revenue spend and a £7.3m under spend on corporate budgets. Further detail is provided in Appendix A.
5.4The key issues impacting on each key area are:-
Directorate Explanation
Chief Executive The Chief Executive directorate is projecting an overall under spend of £0.2m for the year.
There are currently no significant budget pressures within this area. Corporate The Corporate Resources directorate is projecting an overall over spend Resources of £0.2m across the directorate for the year.
As previously reported, the key budget pressures are:-
a) The delivery of a £400k savings target within Supply Chain Management. This is dependent on implementation of a new Supply Chain Model. b) Unachievable income targets for the AVA Unit, Translation Unit and Print Unit.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.