West London Waste Authority - Audit Committee agreed this item on Wednesday 15 January 2014. Below is the council's own wording, with the papers it was decided on.
It was agreed that the internal audit report should in future include a note on progress of reviews indicating any issues or trends. Susan Dickson confirmed that there had been some delay in finalising the Audit Review of Contract Management as this had been a quite complex review and the Authority had needed time to consider its response to the recommendations. It had also been the case that there had been some delay as had had to divert its resources to priority work elsewhere for a period. Resolved - (a) That the Contract Audit Report attached as a confidential appendix together with the Management Response to the recommendations be noted. (b) That the Cash Audit Report attached as Appendix 2 together with the management response to the recommendations be noted. (c) That the updated memorandum on the income and expenditure report be noted as set in Appendix 3 to the report. (d) That progress on the Plan for 2013-2014 as set out in Appendix 4 to the report be noted. (e) That the Treasurer seek tenders for the provision of internal audit services for the next 3 years.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to West London Waste Authority - Audit Committee
WEST LONDON WASTE AUTHORITY
AUDIT COMMITTEE 15 January 2013
Report of the Treasurer
Internal Audit
SUMMARY This report provides an update on the Internal Audit Plan for 2013 together with two new reports on Contract Management and Cash. There is also a progress report on Income and Expenditure.
RECOMMENDATION(S) The Authority is asked to:-
1) Note the Contract Audit report, Appendix 1, together with management responses to recommendations
2) Note the Cash Audit report, Appendix 2, together with management responses to recommendations
3) Note the updated memorandum on the Income and Expenditure Report, Appendix 3
4) Note progress on the Internal Audit Plan for 2013-14, Appendix 4
5) Agree that the Treasurer should seek tenders for the provision of Audit Services for the next 3 years.
1. Introduction – This report provides the Committee with an update report on two internal audit reports that have been completed in the last three months, together with an update on the earlier audit of Income and Expenditure.
2. Contract Audit – This red report contains 44 recommendations, 21 of which have been rated as High Risk, 21 Medium Risk, and 2 were rated as low risk. Only one of the recommendations was not agreed by for implementation. The auditor recommended risk registers for all contracts. The Authority felt that this was too high a burden that it could not maintain. A risk register will be held for the principal contracts, but all smaller ones will be included in the corporate risk register as and when an issue is identified. A significant number of the recommendations will be resolved as older contracts expire over the next three months.
3. Cash Audit –. This is an Amber report with 7 recommendations, 3 High Risk, 3 Medium Risk and 1 Low Risk. All the actions have been agreed
4. Income and Expenditure Review – The report highlights that the Authority has implemented 28/36 recommendations. Appendix 3 sets out the recommendations which were outstanding at the time of the review. Since the review one more recommendation has been implemented as there have been a number of new vendors set up on SAP. All have been emailed either by the Interim Head of Finance or by a member of her team and copied in to the Head of Finance. Credit checks are performed on all new Vendors prior to set up.
5. Outstanding audit recommendations. A table of all high risk recommendations which remain outstanding is attached at Appendix 5.
6. Internal Audit Work plan – during quarter three no further fieldwork has been undertaken. The plan included two further reports for the current year, Data Security and Fixed Assets.
7. The Treasurer has commissioned Sector to undertake a review of our policy and process for the charging of Minimum Revenue Provision (MRP). This work is being undertaken by Sector as opposed to Internal Audit as they have the specialist knowledge on best practice in this area. The audit of Data Security is being postponed until 2014-15 as the Authority has now agreed to a change of provider which it is believed will address the current concerns. It would be more appropriate to undertake a review once the new arrangements are in place.
8. Provision of audit services – The Internal Audit Service has been provided by the London Borough of Harrow since 1986. There have been significant advantages to the Authority in engaging Harrow Internal Audit Services as West London Waste utilised their finance systems and relied upon Harrow for a range of financial services.
9. The Authority has a duty to ensure that it obtains best value for money from all its outsourced services and it is therefore proposed to market test the provision of internal audit services for a three year term. This would not prevent any of the six boroughs from tending for the work. The results of this process would be benchmarked against existing framework agreements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow West London Waste Authority - Audit Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.