Progress report on the work of internal audit and anti-fraud (Q3)

Noted Finance 1 paper

Audit and Governance Committee noted this item on Thursday 13 March 2025. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the Audit & Governance Committee noted the performance of the Internal Audit and Investigation team and key issues arising during Quarter 3.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Audit and Governance Committee, 14 pages

Background

3.1This report outlines the performance of the Audit & Investigations Shared Service for quarter 3.

3.2Internal Audit and Investigations activity within the Council is delivered under a shared service arrangement with the London Borough of Ealing. 4. Reason for Decision and Options Considered

4.1The Audit & Governance Committee is presented with details in the attached report.

5. Key Implications

5.1Internal audit is an assurance function that provides an independent and objective opinion to the Council on the control environment comprising of risk management and control and governance, by evaluating its effectiveness in achieving corporate objectives. It objectively examines, evaluates, and reports on the adequacy of the control environment as a contribution to the proper, economic, efficient, and effective use of resources. While assurance will also be sought from third parties, the assurance gained from the programme of work set out in the 2024/25 Plan will form the main input for the development of the 2024/25 Head of Audit opinion for the Council.

6. Internal Audit performance 6.1 This report provides a progress update on the work of internal audit for quarter three.

6.2The 2024/25 Plan was approved by the Audit & Governance Committee in March 2024. The plan presented was indicative and can be subject to revision during the year to take account of changing priorities and emerging risks, which is aligned with good internal audit practice.

6.3The table below provides a guide to how the assurance levels are defined.

Assurance Level Definition Substantial There is a sound system of internal control designed to achieve the client’s objectives. The control processes tested are being consistently applied. Reasonable While there is a basically sound system of internal control, there are weaknesses, which put some of the client’s objectives at risk. There is evidence that the level of non- compliance with some of the control processes may put some of the client’s objectives at risk. Limited Weaknesses in the system of internal controls are such as to put the client’s objectives at risk. The level of non- compliance puts the client’s objectives at risk. Nil Control processes are generally weak leaving the processes / systems open to significant error or abuse. Significant non- compliance with basic control processes leaves the processes / systems open to error or abuse. 6.4 The following table shows progress against the 2024/25 audit plan, illustrating the status (draft/final/in progress etc) of each review:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress report on the work of internal audit and anti-fraud (Q3)Report 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Progress report on the work of internal audit and anti-fraud (Q3)This decision
  2. Progress Report on the Work of Internal Audit and Anti-Fraud (Q2)Noted
  3. Progress Report on the Work of Internal Audit and Anti-Fraud (Q2)Noted
  4. Progress report on the work of internal audit and anti-fraud (Q3)Noted
  5. Progress report on the work of internal audit and anti-fraud (q3) - Mike PinderNoted
  6. Progress report on the work of the Internal Audit and Anti-FraudNoted

More from Hounslow Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absence, declarations of interest or any other communication from MembersThere were no apologies for absence, declarations of interest or other communications. Decided Open
8 Sep 2026 Minutes of the meeting held on 3 February 2026The minutes of the meeting held on 3 February 2026 were agreed as an accurate record. Agreed Open
8 Sep 2026 Matters arising from the minutesThere were no matters arising from the minutes. Decided Open
8 Sep 2026 Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)Please see the report by Sarah Filby, Director Strategy, Performance & Commissioning (agenda item 4) The report was p... Decided Open
8 Sep 2026 Treasury Management Annual Report 2025/26Please see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 5) The report was pre... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies