REG 144 - Gunnersbury Park Regeneration - Funding and Governance Arrangement
AgreedExecutive1 paper
Cabinet Member Single Member Decision agreed this item on Monday 3 February 2014. Below is the council's own wording, with the papers it was decided on.
That the Cabinet Member for Leisure and Public Health, together with the Cabinet Member for Environment agreed the recommendations in the report as follows: · Noted progress on the Gunnersbury Park Regeneration Project. · Agreed to the principle of developing a Joint Venture which had been recommended as the most appropriate form of governance for the estate by the project board. Agreed that further detail would be brought back as a report to the Cabinet for approval. · Gave authority to the Director of Regeneration, Economic Development & Environment in consultation with the Portfolio holder(s) in Ealing and Hounslow to develop and set up a fundraising body to support the future Joint Venture and to approve the detail of the HLF submissions in February 2014 and April 2014 including the Business Plan.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title REG144 Gunnersbury Park Regeneration – Funding and Governance arrangement Member Deciding Councillor Ajmer Grewal - Lead Executive Member for Leisure and Public Health Councillor Colin Ellar, Lead Member for Gunnersbury Contact Details Peter Matthew, Assistant Director Housing, Leisure & Public Health 020 8583 5321 [email protected]
Date to be Considered 3 February 2014 Implementation Date if 14 February 2014 Not Called In Affected Wards (All) Brentford, Turnham Green Chiswick Riverside
Keywords/Index Gunnersbury Park Museum Heritage Lottery Funding Governance
SINGLE MEMBER DECISION
1. Details of Recommendations
Members are asked to: • Note progress on the Gunnersbury Park Regeneration Project. • Agree to the principle of developing a Joint Venture which has been recommended as the most appropriate form of governance for the estate by the project board. Further detail will be brought back as a report to the Cabinet for approval. • Give authority to the Director of Regeneration, Economic Development & Environment in consultation with the Portfolio holder(s) in Ealing and Hounslow to develop and set up a fundraising body to support the future Joint Venture and to approve the detail of the HLF submissions in February 2014 and April 2014 including the Business plan If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Innovating – Learning from experience Improved facilities, access The progress made by the project team has and services in Museum developed good practice in working with the public, and Park within three years private and third sectors and take the steps necessary to improve access at both Gunnersbury museum and the Park Spending wisely – every penny counts Significant savings should Identifying opportunities to increase the revenue and be made within six years reduce the cost of managing the Gunnersbury Estate will save the council money. Listening - Responding A new management structure ,including Exploring options to regenerate Gunnersbury Estate community representatives will respond to proposals that have come from could be in place by 2014 consultants, government agencies and local community organisations.
2. Report Summary
1. This report provides an update on the Gunnersbury Park project and suggests a form of governance for the future management of the estate. 2. The Project Board recommends that the council develops a Joint Venture form of governance in partnership with Ealing Council that will be responsible for the on-going management and operation of Gunnersbury. To support this a development trust will be responsible for fundraising support both during the delivery of the capital project and on-going works 3. This recommendation and changes to the scope and funding of the project are being made because the Heritage Lottery Fund (HLF) have carried out a stage C review and made a number of comments which need to be addressed. 4. If adopted, the key financial implications for the Council are • A requirement to release the £2.35m approved capital bid • To allow the project to progress members will need to consider and agree a further capital bid for £1.8m which has not yet been submitted. • The potential to reduce the cost to the council of providing community access to Gunnersbury from Financial year 2017/18 onwards. 5. An additional point to note is that this is a three phase project. We cannot afford to address all the issues at Gunnersbury with the phase 1 HLF applications but there is a Master plan which considers a holistic way forward and how this plan might be achieved
3. Reason for Decision and Options Considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.