That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted and approved alternate funding of £560,757 from revenue in order to make up the shortfall of previously approved capital funding for the Heritage Lottery Phase of the Gunnersbury Project. 2. Cabinet noted and approved a revenue contribution to capital of £500,000 to match the Gunnersbury element of a borough –wide ParkLife funding offer (Sports Phase). 3. Cabinet authorised allocation of £96,984 of s106 Brentford schemes to the Gunnersbury Regeneration Project to meet the October 2014 Cabinet report contribution target. 4. Cabinet gave approval for the procurement of an operator for the leisure facilities in the Sports Hub on a 10 year agreement, with an additional 5 year extension option. It is likely that this agreement will bring in additional capital funding required to complete the Sports Hub Phase of this project. That Cabinet agreed the recommendations of the report as follows: 1. Cabinet noted and approved alternate funding of £560,757 from revenue in order to make up the shortfall of previously approved capital funding for the Heritage Lottery Phase of the Gunnersbury Project. 2. Cabinet noted and approved a revenue contribution to capital of £500,000 to match the Gunnersbury element of a borough –wide ParkLife funding offer (Sports Phase). 3. Cabinet authorised allocation of £96,984 of s106 Brentford schemes to the Gunnersbury Regeneration Project to meet the October 2014 Cabinet report contribution target. 4. Cabinet gave approval for the procurement of an operator for the leisure facilities in the Sports Hub on a 10 year agreement, with an additional 5 year extension option. It is likely that this agreement will bring in additional capital funding required to complete the Sports Hub Phase of this project.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title REG 418 - Gunnersbury Regeneration Project – Updates and Approvals Member Reporting Councillor Corinna Smart – Portfolio Holder Contact Details David Stockdale – Heritage Services & Major Projects Manager – 0208 583 3823 – [email protected] Marianne Boyle - Major Projects & Service Manager: Sport & Physical Activity – 0208 583 4151 - [email protected] Imran Choudhury- Director of Public Health-0208 583 [email protected]
For Consideration By Cabinet Date to be Considered 15/11/2016 Implementation Date if 28/11/2016 Not Called In Affected Wards (All) Brentford, Turnham Green, Chiswick Riverside Keywords/Index Gunnersbury Park Estate, Regeneration, Governance, Heritage Lottery Fund
1. Details of Recommendations
The Cabinet is asked to: 1. Note and approve alternate funding of £560,757 from revenue in order to make up shortfall of previously approved capital funding for the Heritage Phase of the Gunnersbury Project. 2. Note and approve a revenue contribution to capital £500,000 to match the Gunnersbury element of a borough-wide ParkLife funding offer (Sports Phase). 3. Authorise allocation of £96,984 of s106 Brentford schemes to the Gunnersbury Regeneration Project to meet October 2014 Cabinet Report contribution target. 4. Approval for the procurement of an operator for the leisure facilities in the Sports Hub on a 10 year agreement, with an additional 5 year extension option. It is likely that this agreement will bring in additional capital funding required to complete the Sports Hub Phase of this project.
1 If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Innovating – Learning from experience Secured funding of £ 6.03 m for Heritage and Sports 2018-19 Phases will be released between October 2016 and March 2018 to improve facilities and access at Gunnersbury Museum, Park and Sports Hub.
A cleaner, greener borough The creation of a ParkLife Hub site at Gunnersbury Pack increases the viability and likelihood of other 2018-19 ParkLife hub projects within the Borough, including Dukes Meadows. Should these be pursued, funding would be available from the Football Association, a suggested £3m. The council may be required to provide match funding to access this investment. Any such project will further benefit a great number of residents.
Active, healthy communities The leisure/sports facility will encourage residents to 2018-19 be more active, and create a community hub.
2. Report Summary
This report relates to the Gunnersbury Regeneration Project and Masterplan, which is being delivered in partnership with the London Borough of Ealing (LBE), and was originally agreed by Cabinet in November 2011.
This report recommends a change to previously agreed funding which supports the Heritage Phase, replacing a shortfall with other available funds. This report also recommends a new allocation to the Sports Phase to secure strategic funding from the Football Association (FA ParkLife) which has now been offered.
These recommendations are being made as some of the funding originally envisaged for the project is either unavailable or currently not available within the required delivery timeline. Furthermore, if the project cannot secure the additional funds we will have to scale back both Phases considerably which could result in other funders withdrawing their funding, risking project completion.
If adopted, the key financial implications for the Council are: o To contribute £560,000 of current revenue budget to capital in regard to the Gunnersbury Heritage Project. This is to meet the capital shortfall
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.