That the Cabinet agreed the recommendations of the report as follows: 1) Cabinet members noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019. 2) Cabinet members approved the following: 6. The Cabinet approved the additions to the Annual Procurement Plan (detailed in Appendix D of the report). That the Cabinet agreed the recommendations of the report as follows: 1) Cabinet members noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019. 2) Cabinet members approved the following: 6. The Cabinet approved the additions to the Annual Procurement Plan (detailed in Appendix D of the report).
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title CR90 - Monthly Financial Monitoring Report Member Reporting Councillor Jagdish Sharma, Leader of the Council Contact Details Name: Clive Palfreyman, AD Strategic Finance Telephone: 020 8583 2430 Email: [email protected] For Consideration By Cabinet Date to be Considered 11 February 2014 Implementation Date if 7 days after decision Not Called In Affected Wards All Keywords/Index Financial Monitoring, Period 9
1 Details of Recommendations Cabinet members are asked to note the following:-
1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019.
Cabinet members are asked to approve the following recommendations:-
6. To approve the additions to the Annual Procurement Plan (detailed in Appendix D).
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can expect to benefit, link to Values notice a difference The Council will manage its cost pressures to ensure - that costs are managed within the approved budget.
2 Report Summary This report presents the projected General Fund revenue outturn for 2013/14 and reports a £0.5m over spend against revised budget on departmental revenue spend and a £7.3m under spend against revised budget on corporate budgets, giving a total net under spend of £6.8m.
It is anticipated that the 2013/14 under spend will be set aside to provide specific contingency reserves for 2014/15 spending pressures as outlined in the budget report.
The surplus for the 2013/14 HRA is projected to be £1.26m with a favourable variance of £1.34m against the revised HRA budget. 3 Reason for Decision and Options Considered 3.1 Members are asked to approve the additions to the Annual Procurement Plan. This will enable the Council to deliver the services as outlined in Appendix C.
4 Key Implications 4.2 There are no key implications to be considered.
5 Financial Details Financial Impact On The Budget 5.2 There are no decisions proposed in this report that have an impact on the overall Council’s revenue budget. An update on the Council’s financial performance is provided below.
General Fund 5.3 The table below provides a summary of each directorate’s performance against the Council’s approved 2013/14 revenue budget and is based on department’s projections of their anticipated outturn for the year. See Appendix A for the detailed analysis. Variance Original Revised Projected Reported Department Budget Budget Outturn Variance last period Movement £M £M £M £M £M £M Chief Executive 7.0 7.0 6.7 (0.3) (0.2) (0.1) Corporate Resources 38.8 39.3 39.4 0.1 0.2 (0.1) Regeneration, Economic Development & Environment 32.3 32.4 32.4 0.0 0.2 (0.2) Children's & Adults' 100.4 100.4 101.1 0.7 0.8 (0.1) Net Service Spend 178.5 179.1 179.6 0.5 1.0 (0.5) Corporate Items 10.8 10.2 2.9 (7.3) (7.3) 0.0 Total 189.3 189.3 182.5 (6.8) (6.3) (0.5) 5.4 The projected revenue outturn anticipates a £0.5m over spend on departmental revenue spend and a £7.3m under spend on corporate budgets. Further detail is provided in Appendix A and paragraph 5.14 outlines our proposed treatment of the corporate items underspend.
5.5The key issues impacting on each key area are:-
Directorate Explanation
Chief Executive The Chief Executive directorate is projecting an overall under spend of £0.3m against budget for the year. There are currently no significant budget pressures within this area.
Corporate The Corporate Resources directorate is projecting an overall over spend Resources of £0.1m against budget for the year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.