London Borough of Hounslow
Cabinet, Tuesday 11 February 2014 at 7.00pm

CR 90 - Monthly Financial Monitoring

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 11 February 2014. Below is the council's own wording, with the papers it was decided on.

Item126

Resolved

That the Cabinet agreed the recommendations of the report as follows: 1) Cabinet members noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019. 2) Cabinet members approved the following: 6. The Cabinet approved the additions to the Annual Procurement Plan (detailed in Appendix D of the report). That the Cabinet agreed the recommendations of the report as follows: 1) Cabinet members noted the following: 1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019. 2) Cabinet members approved the following: 6. The Cabinet approved the additions to the Annual Procurement Plan (detailed in Appendix D of the report).
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Report for: ACTION

Contains Confidential No or Exempt Information Title CR90 - Monthly Financial Monitoring Report Member Reporting Councillor Jagdish Sharma, Leader of the Council Contact Details Name: Clive Palfreyman, AD Strategic Finance Telephone: 020 8583 2430 Email: [email protected] For Consideration By Cabinet Date to be Considered 11 February 2014 Implementation Date if 7 days after decision Not Called In Affected Wards All Keywords/Index Financial Monitoring, Period 9

1 Details of Recommendations Cabinet members are asked to note the following:-

1. Projected revenue outturn for the General Fund. 2. Projected revenue outturn for the Housing Revenue Account (HRA). 3. Performance against the key corporate financial indicators. 4. Performance against the capital programme. 5. £85k allocation from the Performance Improvement Fund to support the delivery of the corporate property strategy 2014-2019.

Cabinet members are asked to approve the following recommendations:-

6. To approve the additions to the Annual Procurement Plan (detailed in Appendix D).

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can expect to benefit, link to Values notice a difference The Council will manage its cost pressures to ensure - that costs are managed within the approved budget.

2 Report Summary This report presents the projected General Fund revenue outturn for 2013/14 and reports a £0.5m over spend against revised budget on departmental revenue spend and a £7.3m under spend against revised budget on corporate budgets, giving a total net under spend of £6.8m.

It is anticipated that the 2013/14 under spend will be set aside to provide specific contingency reserves for 2014/15 spending pressures as outlined in the budget report.

The surplus for the 2013/14 HRA is projected to be £1.26m with a favourable variance of £1.34m against the revised HRA budget. 3 Reason for Decision and Options Considered 3.1 Members are asked to approve the additions to the Annual Procurement Plan. This will enable the Council to deliver the services as outlined in Appendix C.

4 Key Implications 4.2 There are no key implications to be considered.

5 Financial Details Financial Impact On The Budget 5.2 There are no decisions proposed in this report that have an impact on the overall Council’s revenue budget. An update on the Council’s financial performance is provided below.

General Fund 5.3 The table below provides a summary of each directorate’s performance against the Council’s approved 2013/14 revenue budget and is based on department’s projections of their anticipated outturn for the year. See Appendix A for the detailed analysis. Variance Original Revised Projected Reported Department Budget Budget Outturn Variance last period Movement £M £M £M £M £M £M Chief Executive 7.0 7.0 6.7 (0.3) (0.2) (0.1) Corporate Resources 38.8 39.3 39.4 0.1 0.2 (0.1) Regeneration, Economic Development & Environment 32.3 32.4 32.4 0.0 0.2 (0.2) Children's & Adults' 100.4 100.4 101.1 0.7 0.8 (0.1) Net Service Spend 178.5 179.1 179.6 0.5 1.0 (0.5) Corporate Items 10.8 10.2 2.9 (7.3) (7.3) 0.0 Total 189.3 189.3 182.5 (6.8) (6.3) (0.5) 5.4 The projected revenue outturn anticipates a £0.5m over spend on departmental revenue spend and a £7.3m under spend on corporate budgets. Further detail is provided in Appendix A and paragraph 5.14 outlines our proposed treatment of the corporate items underspend.

5.5The key issues impacting on each key area are:-

Directorate Explanation

Chief Executive The Chief Executive directorate is projecting an overall under spend of £0.3m against budget for the year. There are currently no significant budget pressures within this area.

Corporate The Corporate Resources directorate is projecting an overall over spend Resources of £0.1m against budget for the year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Department Outturn P9Appendix A 255 KB Download
PDF
Key Corporate Financial IndicatorsAppendix B 19 KB Download
PDF
Capital Programme updatesAppendix C 144 KB Download
PDF
Annual Procurement Plan UpdateAppendix D 38 KB Download
PDF
CR 90: Monthly Financial MonitoringReport 87 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. CR 90 - Monthly Financial MonitoringThis decision
  2. Monthly Revenue Financial Monitoring -Decided
  3. CEX 166 - Monthly Financial MonitoringAgreed
  4. CEX 148 - Monthly Financial MonitoringAgreed
  5. CEX 140 - Monthly Financial Monitoring ReportAgreed
  6. CEX 136 - Monthly Financial Monitoring ReportDecided

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies