London Borough of Hounslow
Central Hounslow Area Forum, Tuesday 22 July 2014 at 7.30pm

Riverside Walk - Potential Environmental Improvements

Agreed Committee 1 paper

Central Hounslow Area Forum agreed this item on Tuesday 22 July 2014. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Resolved - a) That officers be authorised to consult with the local residents on the use of the remaining Environmental Improvement Section 106 Funding from Scheme 381 for works on Riverside Walk. b) That, subject to the consultation above, authority be delegated to Ward Councillors to agree the implementation of any environmental improvements. (c) That officers request Hounslow Highways to resurface Riverside Walk at the same time that the environmental improvements were undertaken.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Central Hounslow Area Forum, 2 pages

Briefing note for the Central Hounslow Area Forum 22 July 2014 Subject: Riverside Walk: potential environmental improvements.

There is approximately £75,000 of S106 funds still available for environmental improvements from scheme 381, which relates to development at Mogden Sewage Works. This takes account of work that has been completed already and the anticipated costs for proposed work on Weavers Close. Of this £75,000k approximately £35,000 is under the control of Isleworth and Brentford Area Forum, and £40,000 under the control of Central Hounslow Area Forum. The IBAF controlled funding has been allocated to ward Cllrs and they have suggested combining the remaining section 106 funds for environmental improvements centred on Riverside Walk, which lies on the boundary between the two areas (CHAF shown in blue on the map below).

The plan would be to make the riverside a place where people wanted to spend time. Improved Recommendations: planting on the banks is an option, along with repairing gaps in the railings on the east of the river bank and smartening up the appearance of the area.

Damaged railings and fallen trees

Existing riverside path Opportunities: A consultation with local residents could shape the exact nature of the proposed improvements. The Environment Agency (EA), who are responsible for the water course and the local Woodland Estate Resident’s Association have been contacted to inform this briefing note.

The EA were supportive of the idea and suggested a specific project that would contribute towards the aims of the Water Framework Directive (WFD):

 Remove toe-boarding and realign/reprofile banks (estimated cost up to £10,000) – there is a section of toe boarding (wooden bank reinforcement) on the left bank of the river to the north of Mogden that could be removed and replaced with a natural, re-landscaped bank planted with native vegetation, including reed margins.

The Woodlands Estate Resident’s Association provided a range of ideas that included:

 Improvements to the existing planting alongside the river  Improvements to the paths surfacing (which should be covered under Hounslow Highways resurfacing programme)  Clearing the river of rubbish and debris  New bins provided as existing ones overflow with rubbish  Measures to tackle drug dealing

Challenges: The eastern bank of the river is not registered with the land registry and the owner would need to be identified before any works could be carried out.

Recommendations: 1. If members are in favour of using the remaining environmental improvement S106 funding from scheme 381 for works on Riverside Walk to authorise a consultation with local residents. 2. To decide on the approval mechanism for any proposed works: either a formal report to be approved by CHAF or delegated authority to ward councillors.

Kieran Taylor Transport Project Officer, Traffic & Transport 0208 5835 206 July 2014

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Riverside Walk: Potential Environmental ImprovementsReport 2 pages DownloadRead as text

More from Hounslow Central Hounslow Area Forum

All decisions
MeetingDecisionOutcome
16 Jan 2020 Budget 2020 - Councillor Shantanu RajawatResolved : The Budget 2020-21 presentation was noted. Noted Open
16 Jan 2020 Inwood Park maintenance and security (23 signatories)The Area Forum noted the submitted petition and response. It was agreed that a copy of the response should be sent to... Noted Open
16 Jan 2020 Smoking on Hounslow High Street (63 signatories)Resolved : Following discussion on the item, members asked officers to investigate further whether consideration coul... Decided Open
16 Jan 2020 Request for zebra crossing at Heath Road in front of Maswell Park Church (23 signatories)The Area Forum noted the submitted petition together with the response from the borough’s Traffic and Transport Team.... Noted Open
27 Jun 2019 Confirmation of the Chair of Central Hounslow Area ForumThe clerk opened the meeting and sought confirmation of the appointment of Cllr Ajmer Grewal as Chair of the Central ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies