REG 272 - Revisions to Proposed Hounslow High Street Quarter Development Scheme

Approved Executive 1 paper

Cabinet approved this item on Tuesday 10 February 2015. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

That the Cabinet approved the recommendations of the report as follows: That Cabinet in its capacity as Landowner approved the amendments to the proposed scheme submitted by BDW Trading Ltd under the terms of the Property Development Agreement between London Borough of Hounslow and BDW Trading Ltd, dated 11 March 2014. That Cabinet in its capacity as Landowner noted that: (i) As required under the Development Agreement the revisions have been confirmed to accord with the Council’s statutory duty imposed under Section 123 of the Local Government Act 1972 by the Council’s retained advisers, G L Hearn. (ii) Should the revisions be accepted by Cabinet (as now confirmed above), BDW Trading Ltd intend to submit a draft planning application for approval under the terms of the Development Agreement in February 2014. (iii) On receipt of approval, the planning application will be formally submitted as required under the Development Agreement. . That the Cabinet approved the recommendations of the report as follows: That Cabinet in its capacity as Landowner approved the amendments to the proposed scheme submitted by BDW Trading Ltd under the terms of the Property Development Agreement between London Borough of Hounslow and BDW Trading Ltd, dated 11 March 2014. That Cabinet in its capacity as Landowner noted that: (i) As required under the Development Agreement the revisions have been confirmed to accord with the Council’s statutory duty imposed under Section 123 of the Local Government Act 1972 by the Council’s retained advisers, G L Hearn. (ii) Should the revisions be accepted by Cabinet (as now confirmed above), BDW Trading Ltd intend to submit a draft planning application for approval under the terms of the Development Agreement in February 2014. (iii) On receipt of approval, the planning application will be formally submitted as required under the Development Agreement. .
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Report for: ACTION / INFORMATION

Contains Confidential YES Appendices A, B, C, D & E – Exempt from publication or Exempt Information under Schedule 12A of the Local Government Act 1972 as the report contains information relating to the financial or business affairs of commercial developers and in all the circumstances of the case the public interest in maintaining the exemption outweighs public interest in disclosing it. Title Revisions to proposed High Street Quarter development scheme Member Reporting Cllr. Steve Curran, Cabinet Member [email protected] Contact Details Heather Cheesbrough ([email protected]) For Consideration By Cabinet Date to be Considered 10th February 2015 Implementation Date if 23 February 2015 Not Called In Affected Wards Hounslow Central Keywords/Index High Street Quarter

1 DETAILS OF RECOMMENDATIONS

That Cabinet in its capacity as Landowner

(a) Approve the amendments to the proposed scheme submitted by BDW Trading Ltd under the terms of the Property Development Agreement between London Borough of Hounslow and BDW Trading Ltd dated 11 March 2014.

(b) To note that

(i) As required under the Development Agreement the revisions have been confirmed to accord with the Council’s statutory duty imposed under Section 123 of the Local Government Act 1972 by the Council’s retained advisors, GL Hearn.

(ii) Should the revisions be accepted by Cabinet, BDW Trading Ltd intend to submit a draft planning application for approval under the terms of the Development Agreement in February 2014.

(iii) On receipt of approval, the planning application will be formally submitted as required under the Development Agreement.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will benefit, link Dates by which they to Values can expect to notice a difference Good Quality Homes and Jobs. If the development proceeds, The proposal would facilitate the delivery of the proposed construction is High Street Quarter development, a mixed use scheme scheduled to which would regenerate Hounslow town centre and provide commence in 2016 new homes and over 400 full time jobs. with the first phases of development The development will also provide a total of 527 residential completed and apartments with 41% of these being affordable housing. handed over for fit out in 2018 The Scheme will make a positive contribution to the improvement of the economic, social and environmental well-being of the area.

2 REPORT SUMMARY

1. This report seeks approval for revisions to the arrangements between the Council and its development partner as set out in the Property Development Agreement.

2. BDW Trading Ltd was selected as the Council’s development partner by Cabinet at a meeting on 5th November 2013 after the Council had undertaken a selection competition under the EU Negotiated Procedure.

3. A Property Development Agreement was entered into by the parties dated 11 March 2014. This was based on the scheme and financial arrangements submitted by BDW in the competition.

4. Between the formal selection and the signing of the Agreement, having undertaken a significant amount of further technical and design work, BDW identified a number of issues which would necessitate amendments to the bid scheme. Also working collaboratively with Council officers, a number of opportunities were identified to enhance development proposals.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REG 272: Revisions to Proposed Hounslow High Street Quarter Development SchemeReport 138 KB DownloadRead as text

At this meeting

Whole meeting

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies