That the Cabinet noted and discussed the report on Quarter 3 performance data. That the Cabinet noted one correction to the report – BPI 61 at page 67 of the report – the commentary recorded that the number had reduced from 22 to 21 but the number should be 14 so that the target was not reflected as ‘red’. 1. That the Cabinet noted and discussed the report on Quarter 3 performance data. 2. That the Cabinet noted one correction to the report – BPI 61 at page 67 of the report – the commentary recorded that the number had reduced from 22 to 21 but the number should be 14 so that the target should not be reflected as ‘red’.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title CEX049 – Quarter Three (October to December 2014) Performance Monitoring Report 2014/15 Member Reporting Cllr Kamaljit Kaur
Contact Details Ian Carter, Assistant Director Strategy, Intelligence & Engagement. [email protected] Tel. 020 8583 2470 For Consideration By Cabinet Date to be Considered 17 March 2015 Implementation Date if Information only. Not Called In Affected Wards All Keywords/Index Council Priorities
1. Details of Recommendations
The Cabinet will be asked to: • Note and discuss this report on quarter three performance data.
If the recommendations are adopted, how will residents benefit?
The report sets out performance for the Council priorities that have already benefited residents and will continue to do so through the quarterly monitoring of specific targets and priorities in the Hounslow Business Plan 2014/16.
2. Report Summary
1. A new Business Plan (2014/16) was adopted by Council in November 2014 following the new Corporate Plan adopted in September 2014. The Business Plan sets out a revised set of measures that we will use to monitor progress on delivering the Corporate Plan. There are 50 new performance indicators and 3 new milestones, in addition to 14 pre-existing performance indicators and 1 milestone. The new set of indicators became effective from quarter three 2014/15 and this is the first report to use them.
Red/Amber/Green (RAG) rating for the pre-existing indicators will continue to be reported using the 2014/15 targets. Newly adopted performance indicators will not be RAG rated in 2014/15, as they do not have 2014/15 targets. RAG rating for these performance indicators will be effective from 2015/16. 2. This report deals with quarter three performance data, covering the period October to December 2014. It covers performance for each of the 64 Business Plan performance indicators (BPIs) and 4 Business Plan milestones (BPMs), under the seven themes of the 2014/16 Business Plan. It also includes approved Action Plans setting out how performance will be improved where indicators are currently rated amber or red.
In addition this report includes the Local Area Performance Solution (LAPS) dashboard showing Hounslow’s performance compared to the London average for the previous quarter (2014/15 quarter two).
3. It recommends Cabinet note and discuss the progress made and considers Action Plans for improving amber and red performance.
3. Overview of quarter three performance 2014/15 Below is an overview of performance under each of the Business Plan themes.
Annex A sets out the performance and other details for each of these measures. It is formatted so that it can be read in black and white if required. A guide to understanding the information contained in the pack is at the start of Annex A.
Annex B provides details of Approved Action Plans. Action plans are required where performance is not currently on track to meet the target (amber/red). Approved action plans have been ratified by the relevant Lead Member. There are 8 approved action plans in quarter three.
Annex C provides the Local Authority Performance Solution (LAPS) dashboard, comparing Hounslow with other London authorities for the period July to September 2014.
Keeping you safe
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.