Feltham Town Centre Traffic & Transport Improvements
DecidedCommittee6 papers
Bedfont, Feltham, Hanworth Area Forum decided this item on Thursday 28 January 2016. Below is the council's own wording, with the papers it was decided on.
a) That authority be delegated to the Executive Director for Regeneration, Economic Development & Environment ( REDe )to undertake detailed design for the proposals set out in paragraph 3.6 and appendix A of the report. b) The authority be delegated to the Executive Director for REDe to carry out the required statutory consultation on the proposals. c) That authority be delegated to the Executive Director for REDe to resolve, where possible, any objections received to the statutory consultation. d) In the event that any objections received remain unresolved, authority be delegated to the Chair of the Forum to determine the objections, in consultation with the Ward Councillors. e) If no objections are received or once any objections received are resolved, authority be delegated to the Executive Director for REDe to implement the scheme, subject to the successful determination of the required planning application and confirmation of available funding.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title Feltham Town Centre Traffic & Transport Improvements Officer Reporting Christopher Deakins Contact Details Christopher Deakins Team Leader – Capital Projects & Network Management Traffic & Transport, REDe 020 8583 4866, [email protected] For Consideration By Bedfont, Feltham, Hanworth Area Forum Date to be Considered 28 January 2016 Implementation Date if 8 February 2016 Not Called In Affected Wards Feltham West, Hanworth Park Keywords/Index public realm, highway improvements, Feltham station access
1. Details of Recommendations
That Members: 1.1 Delegate authority to the Executive Director for Regeneration, Economic Development & Environment (REDe) to undertake detailed design for the proposals set out in paragraph 3.6 and Appendix A. 1.2 Delegate authority to the Executive Director for REDe to carry out the required statutory consultation on the proposals. 1.3 Delegate authority to the Executive Director for REDe to resolve where possible any objections received to the statutory consultation. 1.4 In the event that any objections received remain unresolved, delegate authority to the chair of the Forum to determine the objections in consultation with the Ward Councillors. 1.5 If no objections are received or once any objections received are resolved, delegate authority to the Executive Director for REDe to implement the scheme, subject to the successful determination of the required planning application and confirmation of available funding. If the recommendations are adopted, how will residents benefit? Listening / Responding – Continue to liaise with January 2016 – July 2018 residents following the closure of the consultation
Many talents – One Aim. Staff focussed on January 2016 – April 2016 improving the quality of life for residents, by listening to resident’s comments and trying to achieve the optimum scheme design.
Innovating – Learning from experience. Learn from January 2016 – April 2016 the errors of the existing street design; develop a scheme that benefits all road users.
Spending Wisely – Subject to approval, this scheme January 2016 – July 2018 will be delivered in partnership with Hounslow Highways (HH). This provides time and cost efficiencies in commissioning and delivering the scheme
2. Report Summary
2.1This report details the results of the informal consultation on the proposed traffic and transport improvements around Feltham Station and for the High Street, between its junctions with Hounslow Road and Browell’s Lane. 2.2 It recommends that the detailed design and construction of the traffic and transport improvement scheme are undertaken as shown in Appendix A. This project aims to mitigate the effects of closing the level crossing in Bedfont Lane and improving the public realm particularly for pedestrians and cyclists, whilst making the road safer for all road users. 2.3 The scheme is jointly funded by Transport for London (TfL), Network Rail (NR) and the London Borough of Hounslow (section 106 funding). The cost estimate for the detailed design and implementation, based on the initial design work undertaken is £15.6m, of which £11.6m is for the highway works. The scheme is subject to detailed design to determine the final cost estimate and a pricing estimate by HH.
3. Reason for Decision and Options Considered
3.1The area of the Feltham Town Centre Traffic & Transport Improvement Scheme comprises of High Street, a very wide and straight street through the centre of Feltham; Victoria Road, a narrow street connecting Leisure West with the High Street; and Hounslow Road, New Road and Bedfont Lane - a triangle of roads around the railway station. It is the commercial and transport hub of the area, with the railway station, bus interchanges, parks, The Centre and Leisure West all within the area under consideration.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.