a) That the current programme for delivery of the TfL (Transport for London) funded ‘Major Scheme’ for Feltham Town Centre be noted. b) That clarification of the details for the funding of projects included within the scheme to be reported back to the Area Forum. c) That the design work, which has been undertaken to reduce the impact of the new retaining wall on Bridge House Pond be noted. d) That the development into detailed designs for implementation of the Bridge House Pond retaining wall concept designs be agreed.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Bedfont, Feltham, Hanworth Area Forum, 4 pages
Recommendations
That Members:-
(a) note the current programme for delivery of the Transport for London (TfL) funded ‘Major Scheme’ for Feltham town centre; (b) note the design work that has been undertaken to reduce the impact of the new retaining wall on Bridge House Pond park; and (c) agree for the Bridge House Pond retaining wall concept designs to be developed into detailed designs for implementation.
Background
2.1The purpose of this briefing note is to update Members on the Transport for London funded ‘Major Scheme’ for Feltham town centre. 2.2 As reported previously to the Area Forum, the Council received funding from TfL to develop proposals for Feltham Town Centre that: a) facilitates the closure of the level crossing; b) improves pedestrian facilities; c) improves cycle facilities; d) benefits bus passengers; and e) improves journey time reliability
2.3The proposals were approved by the Area Forum in January 2016 and by Planning Committee in March 2016.
3. Business Case
3.1A business case requesting £8.5m of TfL ‘Major Scheme’ funding was submitted to TfL in February 2016. During a review of the business case TfL requested a 10% saving to be made and as a result the proposals for Victoria Road and Mono Lane were removed from the scheme.
3.2The reduced scheme was considered by TfL’s Surface Board in May 2016. Unfortunately, TfL’s Surface Board approved only a proportion of the funding requested; £3.3m of the original £8.5m asked for, and thereby effectively split the scheme into two phases. 3.3 The £3.3m of funding was approved for works that are required to facilitate the closure of the level crossing by Network Rail, and what is now Phase 1 of the scheme. This includes: a) Closure of the Bedfont Lane level crossing and the provision of a new shared use pedestrian and cycle bridge over the railway, replacing the existing network rail stepped footbridge, and the ramped footbridge leading into The Centre. The new structure would connect with The Centre and both sides of Bedfont Lane; b) Changes to Bedfont Lane and its junction with New Road. c) Provision of traffic signals and controlled pedestrian crossings at the junction of New Road and Hounslow Road. The introduction of traffic signals at the junction ensures that traffic exiting New Road is able to do so safely and reduces the traffic delays that would otherwise occur. d) New bus stops on Hounslow Road, near to New Road, for routes 285 and 490. These stops would be located on a direct route into the station via new pedestrian ramps. These stops on Hounslow Road remove the need for routes 285 and 490 to loop via the bus interchange on New Road as they currently do, reducing bus journey times. e) Widening of Hounslow Road on the approach to the Hanworth Road junction to provide an additional lane for left-turning traffic. The additional width will increase capacity at the junction and thereby reduce delays that would otherwise occur. The widening of Hounslow Road will result in the loss of trees and vegetation. A new retaining wall will however be erected and this will be screened with vegetation. f) Retention of the controlled pedestrian crossing at the Hounslow Road and Hanworth Road junction and the addition of a controlled crossing on the southern arm parallel to the Longford River. g) Widening of the bridge over the Longford River to provide two traffic lanes on the approach to Hanworth Road, cycle lanes in both directions and improved footway widths. h) Removal of the existing traffic signals at Bedfont Lane converting it to a give- way junction as a result of the much reduced traffic volumes using the southern end of Bedfont Lane following the level crossing closure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.