That Cabinet agreed the recommendations of the report as follows: That all Hounslow Council tenants and leaseholders on be consulted on draft plans for: I). incorporating the management and maintenance of all Housing Revenue Account (HRA) estate roadways, footways, and communal grounds (the Housing network) into the existing Hounslow Highways PFI contract from April 2017 to December 2037, subject to satisfactory completion of due diligence on the detailed proposals and consultation with tenants and leaseholders; II). developing and designing parking management and control arrangements across the entire Housing network; III). the appointment of specialist consultancy advice and HRA funding of up to £200,000 to provide legal advice, and undertake due diligence and value for money assessments of the Hounslow Highways proposals; IV). c arrying out a full tenant and leaseholder consultation on the proposals to transfer the management and maintenance of the Housing Networks into the PFI contract, and for introducing parking management arrangements; and V). to delegate to the Director of Housing authority to negotiate the details of the proposals with Hounslow Highways, design proposals for parking management, commission a survey of tenants and leaseholders, seek advice on how best to meet leaseholder consultation obligations, and to submit a further report to Cabinet for final approval and to award the contract.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title CAS 499 Housing Estate Roads and Grounds Member Reporting Councillor Katherine Dunne Lead Member for Housing, Equalities and Inclusion [email protected] Contact Details Peter Matthew, Director of Housing 0208 583 5321 [email protected] For Consideration By Cabinet Date to be Considered 26 April 2016 Implementation Date if 9 May 2016 Not Called In Affected Wards Borough-wide Keywords/Index Estate roadway, footways, infrastructure, Hounslow Highways, street cleaning
1. Details of Recommendations
Cabinet is asked to agree consult all Hounslow Council tenants and leaseholders on draft plans for:
I). incorporating the management and maintenance of all Housing Revenue Account (HRA) estate roadways, footways, and communal grounds (the Housing network) into the existing Hounslow Highways PFI contract from April 2017 to December 2037, subject to satisfactory completion of due diligence on the detailed proposals and consultation with tenants and leaseholders;
II). developing and designing parking management and control arrangements across the entire Housing network;
III). the appointment of specialist consultancy advice and HRA funding of up to £200,000 to provide legal advice, and undertake due diligence and value for money assessments of the Hounslow Highways proposals;
Cabinet is asked to agree consult all Hounslow Council tenants and leaseholders on draft plans for:
IV). incorporating the management and maintenance of all Housing Revenue Account (HRA) estate roadways, footways, and communal grounds (the Housing network) into the existing Hounslow Highways PFI contract from April 2017 to December 2037, subject to satisfactory completion of due diligence on the detailed proposals and consultation with tenants and leaseholders;
V). developing and designing parking management and control arrangements across the entire Housing network; VI). the appointment of specialist consultancy advice and HRA funding of up to £200,000 to provide legal advice, and undertake due diligence and value for money assessments of the Hounslow Highways proposals;
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference This report seeks approval for activities which will Contract Start April 2017 enable officers to develop the proposal to accrue the (lighting and energy) Housing Estate roadway and footway network into April 2018 for trees and the Hounslow Highways existing long term roadways arrangements. The benefits to residents out of the contract which may result include: Improved lighting on Housing estates Improved condition of roadways and footways Improved cleanliness Safer estate environment Better maintained trees Energy efficiency resulting in lower day to day service charges
2. Report Summary
2.1This report sets out the proposal for entering into a long-term agreement with Hounslow Highways (with whom the Council has a Private Finance Initiative agreement to maintain the Borough’s highways and associated land for a 25 year period) to maintain the roadways, footways and communal grounds on our housing estates (the Housing network).
2.2Hounslow Highways have now submitted a detail proposal for this purpose which involves: the accrual of the Housing network into the existing PFI contract, based on similar standards and price principles; an upfront five-year capital investment period to benefit roadways, footways, lighting and trees; ongoing revenue funded maintenance (20 years and 9 months) of roadways and footways, street lighting, street cleansing, grounds maintenance; and the placing of the risk associated with these assets with the Hounslow Highways contractor.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.