That Cabinet agreed to allocate an additional £16.6m capital funding to support the future waste and recycling service, which included the securing of a new depot and material handling facility that would in turn facilitate the release of two current Council depot sites for the development of new homes.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title REG 406 Adjustment to Capital Programme to reflect Cabinet decision on Waste and Recycling Service Member Reporting Cllr Amrit Mann, Deputy Leader of the Council and Lead Member, Environment Contact Details Andrew Baker, Interim Head of Commissioning – Waste and Recycling, Highways PFI and Parking Services 020 8583 2976 [email protected] For Consideration By Cabinet Date to be Considered 14 June 2016 Implementation Date if 28 June 2016 Not Called In Affected Wards All Keywords/Index Waste, Capital, Borrowing
1. Details of Recommendations
To agree to an additional £16.6m capital funding to support the future waste and recycling service, including secure a new depot and material handling facility which will in turn facilitate the release of two current Council depot sites for the development of new homes.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why Dates by which they can expect to they will benefit, link to Values notice a difference Innovating – learning from experience Retaining kerbside-sort collections Continuation of the current approach for dry recyclables is familiar to to recycling. residents.
There is substantial upfront Transfer of service delivery to investment in new vehicles and ICT Lampton 360, Teckal-compliant technology which will improve Local Authority company is a service delivery to our residents. significant innovation. The new depot allows both the waste Delivery of a new depot at Southall and recycling services to operate Lane and associated materials from a common depot – improving handling facility resilience. The materials handling facility allows the council to sell the high quality materials which will be collected at a higher value than co- mingled materials. The release of our current depots at Ashmead Road, Feltham and Bridge Road, Hounslow for the development of new homes will be facilitated by the creation of a new depot at Southall Lane Spending wisely – every penny counts Reduced landfill costs. Kerbside-sort The changes envisaged are offers larger net savings than expected to increase recycling by comingled collections and will 15% by 2018/19 – leading to a therefore contribute more to the reduction of 15,000 tonnes of waste council’s overall spending reduction going to landfill each year. targets. It is estimated this will save £1.35m Landfill is the most expensive (and in landfill costs each year. least desirable environmentally) method of waste management.
2. Report Summary
1. This report deals with approving additional capital investment required to implement the December 2015 Cabinet decision on the Council’s future waste and recycling service. 2. It recommends approval of £16.65m additional capital funding. 3. If adopted, the key financial implications for the Council are additional capital costs of £16.65m with an additional financing cost of £2.0m.
3. Reason for Decision and Options Considered 3.1 In December 2015 Cabinet approved plans for the future recycling collection methods and delivery mechanism of the waste and recycling service. The report asked members to note the financial impact of the decision. This report seeks to approve the capital investment required to facilitate that decision.
3.2Capital investment is required for new bins and containers changes to the garden waste service a new fleet of waste and recycling collection vehicles a new depot at Southall Lane to accommodate the waste and recycling fleet a Materials Handling Facility at Southall Lane to enable the collected recyclable materials to be processed prior to collection by materials recycling contractors new IT systems to manage the service
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.