i. That Cabinet approved the Schools Capital Maintenance Programme 2016-17 as outlined in Appendix A. ii. That Cabinet agreed to include all listed items on the Council Annual Procurement Plan as Appendix A items (where decisions are delegated to the Director of the Service Area). iii. That Cabinet agreed to delegate authority to the Executive Director of Regeneration Economic Development and Environment or such officer authorised to act on his behalf to modify the schemes and budgets if necessary following site investigations and to agree the addition of emergency priority projects identified in future condition surveys or site investigations. If projects were changed, the overall budget would not be exceeded. iv. That Cabinet agreed that all future reports for approving Schools Maintenance Programmes are made as Single Member Decisions by the Cabinet Member for Education & Children’s Services.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No or Exempt Information Title REG 393 Schools Capital Maintenance Programme 2016-17 Member Deciding Cllr Tom Bruce Cabinet Member Education & Children’s Services Contact Details Bob Seera Head of Construction & Operations [email protected] Ext 2547 Date to be Considered 12 July 2016 Implementation Date if 25 July 2016 Not Called In Affected Wards All Keywords/Index Schools, Maintenance, Education
1. Details of Recommendations
The Cabinet is asked to agree the following:
1.1To approve the Schools Capital Maintenance Programme 2016-17 as outlined in Appendix A. 1.2 To include all listed items on the Council Annual Procurement Plan as Appendix A items (where decisions are delegated to the Director of the Service Area). 1.3 Delegate authority to the Executive Director of Regeneration Economic Development and Environment or such officer authorised to act on his behalf to modify the schemes and budgets if necessary following site investigations and to agree the addition of emergency priority projects identified in future condition surveys or site investigations. If projects are changed, the overall budget will not be exceeded. 1.4 That all future reports for approving Schools Maintenance Programmes are made as Single Member Decisions by the Cabinet Member for Education & Children’s Services.
If the recommendations are adopted, how will residents benefit?
Maintenance of existing school portfolio ensures 2017-18 schools are fit for purpose and enables brighter futures for the Borough’s children and young people. 2. Report Summary
1. This report seeks Member approval of the Schools Capital Maintenance Programme 2016-17 as outlined in Appendix A. 2. It recommends that all projects listed in Appendix A are approved and placed on the Council Annual Procurement Plan as Appendix A items, granting delegated authority to the Executive Director of Regeneration, Economic Development and Environment. 3. These recommendations are being made because the existing school portfolio requires regular maintenance to ensure it is fit for purpose. 4. There is no call on Council resources as the programme is funded from DfE funding. 5. All projects will be delivered at Local Authority maintained schools only as Academies and Free Schools are not eligible for this funding.
3. Reason for Decision and Options Considered
3.1A programme of condition surveys is ongoing. 95% of the school estate has been surveyed and maintenance works have been identified across the school portfolio. A programme of priority items has been identified.
3.2A contingency has been identified to enable priority works identified in the remaining conditions surveys to be undertaken if required. If they are not required the contingency will contribute to the 2017-18 programme.
3.3The projects identified are all necessary priority works required to ensure that capital investment needs for school premises are met, which in turn contributes to raising educational standards.
4. Key Implications
4.1Projects have not yet been commissioned and the individual project scope is yet to be determined. Targets and measures will be established on a project by project basis in conjunction with relevant stakeholders, in particular the schools.
5. Financial Details
5.1The projects identified by officers will be funded from the 2016-17 School Condition Allowance Grant allocated from the DfE and contingency from previous programmes. Any overspend will be met from the contingency sum. There is no call on council resources for these projects.
5.2The DfE School Condition Allowance Grant allocated to the London Borough of Hounslow for 2016-17 is £2,994,903.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.