REG392 Fountain Leisure Centre

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 20 September 2016. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

The Cabinet agreed the following: 1. That the site shall be taken forward as a New Build Project in conjunction with London & Quadrant, as part of a wider master planning process, to deliver a like for like leisure facility. 2. That a budget of £150,000 be made available for due diligence and professional and legal fees, in order to bring the site forward to a contractual agreement. This will be allocated from the feasibility reserve. 3. That the cabinet recognised the need to provide a new leisure facility at the cost of nil affordable housing provision on the leisure site. (This will be subject to a full viability assessment with planning colleagues – Appendix 1) 4. That the risk of build costs inflation, planning and sales risk sits with London & Quadrant, as adjoining land owner and special purchaser. 5. That delegated authority be given to the Executive Director of Regeneration, Economic Development & Environment to execute contractual agreements with London & Quadrant for the provision of a new leisure centre.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 10 pages

Report for: ACTION / INFORMATION

Contains Confidential YES – Appendix 1 or Exempt Information Exempt from publication under Schedule 12A of the Local Government Act 1972 as it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing it.

Title REG 392 – Proposal for Fountain Leisure Centre Member Reporting Councillor Corinna Smart – Lead Member for Public Health & Leisure. Contact Details Brendon Walsh – Executive Director of Regeneration, Economic Development & Environment Tel: 020 8583 4707 Email: [email protected] For Consideration By Cabinet Date to be Considered 20th September 2016 Implementation Date if 30th September 2016 Not Called In Affected Wards Brentford Keywords/Index Proposal for Fountain Leisure Centre, Brentford

1. Details of Recommendations

The Cabinet is asked to agree the following: 1. That the site is taken forward as a New Build Project in conjunction with London & Quadrant, as part of a wider master planning process, to deliver a like for like leisure facility. 2. That a budget of £150,000 be made available for due diligence and professional and legal fees, in order to bring the site forward to a contractual agreement. This will be allocated from the feasibility reserve. 3. That the cabinet recognised the need to provide a new leisure facility at the cost of nil affordable housing provision on the leisure site. (This will be subject to a full viability assessment with planning colleagues – Appendix 1) 4. That the risk of build costs inflation, planning and sales risk sits with London & Quadrant, as adjoining land owner and special purchaser. 5. That delegated authority be given to the Executive Director of Regeneration, Economic Development & Environment to execute contractual agreements with London & Quadrant for the provision of a new leisure centre. If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Residents will benefit from a new modern facility fit 2021 for purpose. A new leisure facility will encourage health and 2021 wellbeing for local residents. A new leisure facility will bring more economic spend 2021 to the area, with visit from outside of the local ward area. The site would form part of a wider master planning 2021 approach for major regeneration in the area. Resulting in increased employment opportunities for local people, and improved state of the art facilities

2. Report Summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REG392 Fountain Leisure CentreReport 10 pages DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies