LAM 001 (previously REG 446) - Property 360 - JV Contractual Arrangements

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 13 December 2016. Below is the council's own wording, with the papers it was decided on.

Item69

Resolved

That Cabinet on behalf of the Council as shareholder agreed the recommendations of the report from Lampton 360 Ltd which was included in the confidential part of the agenda as a confidential Appendix, exempt from publication. The recommendations relate to the procurement exercise conducted to identify a Joint Venture partner for Lampton 360 Ltd, and/or its subsidiary company Lampton Development 360 LPP. That Cabinet on behalf of the Council as shareholder agreed the recommendations of the report from Lampton 360 Ltd which was included in the confidential part of the agenda as a confidential Appendix, exempt from publication. The recommendations relate to the procurement exercise conducted to identify a Joint Venture partner for Lampton 360 Ltd, and/or its subsidiary company Lampton Development 360 LPP.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 4 pages

Report for: ACTION / INFORMATION

Contains Confidential The report from Lampton 360 Ltd attached as an or Exempt Information Appendix contains exempt information as set out therein.

Title LAM 001 (previously REG446) - Property 360 - JV Contractual Arrangements. Member Reporting Katherine Dunne – Lead Member for Housing. Contact Details Peter Large – Head of Governance Tel: 020 8583 3974 Email: [email protected] For Consideration By Cabinet Date to be Considered 13th December 2016 Implementation Date if 3 January 2017 Not Called In Affected Wards Various where sites will be surplus to requirements and redeveloped for residential development through Lampton 360. Keywords/Index Joint Venture Development Partner Selection Process – Contract Award.

1. Details of Recommendations

The Cabinet on behalf of the Council as shareholder is asked to agree the recommendations in the report from Lampton 360 Ltd which is attached as a confidential Appendix. The recommendations relate to the procurement exercise conducted to identify a Joint Venture partner for Lampton 360 Ltd, and/or its subsidiary company Lampton Development 360 LLP.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Improvement of local facilities and services Identified in the Property 360 Business plan, over the next 6 years. Improvement of available affordable housing Improvement of housing solutions for the wider community Economic, Environmental and Sustainable developments, that add to the local economy, and create employment opportunities 2. Report Summary

1. This report recommends approval by Cabinet of a Joint Venture Contract with Lampton 360 Ltd’s selected partner, after a successful OJEU process, for the delivery of mixed use, mixed tenure residential lead projects planned as part of the Property 360 Business Plan.

2. The recommendations follow previous approval by Cabinet of the establishment of subsidiary companies by Lampton 360 to deliver a proposed non-HRA housing development programme, approval of the Property 360 Business Plan, and approval of a procurement exercise to identify a JV partner. I

3. Reason for Decision and Options Considered

3.1On 26 April 2016 Cabinet received a report on homelessness and temporary accommodation which set out the additional pressure on homelessness demand, and the continued scarcity of private rented accommodation and available social and affordable homes. Cabinet approved an overall approach to managing homelessness and temporary accommodation, part of which involved commissioning Lampton 360 Ltd to purchase up to 175 properties for direct lets and temporary accommodation.

3.2At the same meeting, and having regard to the recommendations in that report, Cabinet received a report on a proposed non-HRA housing development programme. Cabinet agreed to the release of 10 General Fund sites which had been identified as surplus to current use and requirements for the purpose of redevelopment for housing, and to the provisional release of one further site, and agreed to commission Lampton 360 Ltd to prepare a Non-HRA Housing Programme for developing the sites identified for housing, and detailed proposals for taking forward individual sites, having regard to the Council’s housing needs and supply requirements as identified.

3.3Pursuant to those decisions, Cabinet on 19 July approved the Business Plan for Lampton Property 360, incorporating Lampton Development 360 LLP and Lampton Investment 360 Ltd. The Business Plan identified each site available for housing redevelopment, and the number of new homes that could be created on each, subject to planning approval and site constraints. Lampton Development 360 LLP were authorised to progress the development programme, on the basis of 40% affordable housing (24% social rent and 16% intermediate), 40% private sale homes and 20% private rented homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LAM 001 (previously REG 446): Property 360: JV Contractual ArrangementsReport 4 pages DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies