a) To approve the £2,995,759 budget for Schools Capital Maintenance Programme 2017-18, as outlined in Appendix A. b) To waive this programme from the 2017-18 Annual Procurement plan. c) To agree the end of the Secondary School Partnership Funding agreement that requires LA secondary schools to contribute to School Capital Maintenance projects. d) To waive the financial contribution £136,198 by the Heathland School toward the Window Replacement project as previously agreed in REG393 Schools Capital Maintenance Programme 2016-17. e) To delegate authority to the Executive Director of Regeneration, Economic Development and Environment or such officer authorised to act on his behalf to modify the schemes and budgets, if necessary, following site investigations and to agree the addition of emergency priority projects as required. Any changes to the programme will be contained within the approved budget. f) That option A, to continue with no schools contributions, including secondary schools, be agreed.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title REG527 Schools Capital Maintenance Programme 2017-18 Member Deciding Cllr Tom Bruce Cabinet Member Education, Children’s Services and Youth Services
Contact Details Bob Seera Head of Capital Projects and Delivery [email protected] Ext 2547 Date to be Considered 21 July 2017 Implementation Date if 31 July 2017 Not Called In Affected Wards All Keywords/Index Schools, Maintenance, Education
SINGLE MEMBER DECISION Draft for Discussion at Schools Forum
1. Details of Recommendations
The Lead Member is asked to agree the following:
1.1To approve the £2,995,759 budget for Schools Capital Maintenance Programme 2017-18 as outlined in Appendix A
1.2To waive this programme from the 2017-18 Annual Procurement plan
1.3To agree the end of the Secondary School Partnership Funding agreement that requires LA secondary schools to contribute to School Capital Maintenance projects.
1.4To waive the financial contribution £136,198 by The Heathland School toward the Window Replacement project as previously agreed in REG393 Schools Capital Maintenance Programme 2016-17
1.5To note the procurement of Multi-Disciplinary Consultant Services to assist in the delivery of future Capital Maintenance programmes. 1.6 To delegate authority to the Executive Director of Regeneration Economic Development and Environment or such officer authorised to act on his behalf to modify the schemes and budgets if necessary following site investigations and to agree the addition of emergency priority projects as required. Any changes to the programme will be contained within the approved budget.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Maintaining existing school premises ensures they 2018/19 are fit for purpose and enables brighter futures for the Borough’s children and young people.
2. Report Summary
1. This report seeks Lead Member approval of the £2,995,759 budget to progress the Schools Capital Maintenance Programme 2017-18 as outlined in Appendix A and also seeks approval for the procurement of Multi- Disciplinary Consultant Services to assist the Corporate Property team in the delivery of this programme
2. These recommendations are being made because the existing school portfolio requires regular planned and preventive maintenance to ensure it is fit for purpose, safe to use and contributes to raising educational standards.
3. This report also seeks approval to end the Secondary School Partnership funding agreement and if agreed to also waive the Heathlands Schools financial contribution of £136,198 as previously agreed by Cabinet on 12 July 2016.
4. There is no call on Council resources as the programme is funded from DfE funding.
5. All projects will be delivered at Local Authority maintained schools only as Academies and Free Schools are not eligible for this funding.
3. Reason for Decision and Options Considered
3.1School Capital Maintenance Programme 2017-18 a. The council undertakes a regular programme of condition surveys across the school portfolio. The surveys have been scrutinised and maintenance works have been identified and prioritised across the school portfolio.
b. The DfE has made an allocation of £2,995,759 for 2017/18 through the School Condition Allowance Grant. The grant is calculated using the number of Local Authority (LA) maintained schools within the Borough, excluding all Academies and Free Schools. Therefore, all proposed projects identified in this programme will be delivered at LA maintained schools only.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.