Resolved
Representatives of maintained schools present at the meeting agreed the recommendations of the report
Schools Forum agreed this item on Monday 4 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Representatives of maintained schools present at the meeting agreed the recommendations of the report
School Capital Maintenance Programmes PROPERTY AND BUILDING SERVICES School Capital Maintenance Programme 2023-24
School Capital Maintenance Programme 2022-23 Delivery Update Most have tenders returning over budget The programme contingency is not sufficient resulting in the requirement to make ‘in year’ amendments to ensure that high priority projects are delivered 4 projects – cancelled as site investigations confirmed works are not required 6 projects – deferred to 2023-24 programme as site investigations have confirmed that the identified works are in a stable condition and can be safely maintained for a minimum of 12 months It is likely that additional ‘in year’ amendments will be required to fund higher priority projects School Capital Maintenance Programme 2023-24
The DfE have allocated £4,314,451 in School Condition Allowance Grant in 2022-23 The programme will be delivered in the 2023-24 Financial Year Only LA maintained schools are eligible for the grant Projects are prioritised using the 2020-21condition survey data held on Tf Cloud High priority works are categorised as follows: Mechanical and Electrical
Fabric
Health and Safety School Capital Maintenance Programme 2023-24 Given current economic trends, it is likely that the cost of prelims, overheads, materials and labour will increase over the next 12 months. Therefore, the 2023-24 programme budgets have been adjusted by 12% to allow for current inflation. To facilitate ‘in year’ amendments in the event of further price increases or difficulties in securing appropriate contractors, the 2023-24 programme has been further prioritised as follows: Priority 1: For completion 2023-24 Priority 2: Advised for completion during 2023-24 but site investigation may confirm deferment to 2024-25 Priority 3: Advised for completion 2023-25 but can be deferred to 2024-26 if required
The Public Sector Decarbonisation Scheme (PSDS) has been considered in the preparation of this programme School Capital Maintenance Programme 2023-24
The programme proposes:
24 projects at 13 sites
6 Mechanical and Electrical
8 Fabric
10 Health and Safety School Project Allocation School Capital 1 Beavers Investigate and replace flat roof £ 28,000 Maintenance 2 Belmont Re-align wrought iron fence to front elevation £ 24,000 Programme 3 Grove Park Rewire of original main building £ 160,000 2023-24 Priority 1 Projects 4 Marlborough Replacement of rooflights £ 152,000
Undertake recommended repairs following Structural 5 Southville Engineer's review (Provisional Sum) £ 24,000 Strand-on-the- 6 Green IN Upgrade heating system and pipework £ 176,000 Strand-on-the- 7 Green Jnr Upgrade heating system, controls and pipework £ 240,000
8 Victoria Jnr Replacement of all boilers £ 80,000
9 William Hogarth Fire Doors and internal fire screen Upgrade £ 40,000 School Project Allocation
School Capital 1 Beavers Replacement of internal doors £ 27,000
Roof leak resulting from poor levels and detailing. Form
Maintenance 2 Chatsworth new outlet and adapt falls £ 40,000
Programme 3 Crane Park Upgrade single glazed window units to DG units £ 67,000 The Heathland
2023-24 4 School Upgrade to heating and cooling installations £ 1,205,000 The Heathland External repairs fencing, hardstanding and mobile unit £ 378,000 Priority 2 Projects 5 School access The Heathland 6 School Internal door upgrade £ 90,000 Replacement of upper section to the perimeter fencing 7 Smallberry Green with metal wired fencing £ 29,000
8 Southville Drainage investigations and external repairs £ 267,000 Undertake all repairs and rectifications to brickwork Strand-on-the- following the structural engineers inspection 9 Green IN (Provisional Sum) £ 48,000 Undertake all repairs and rectifications to brickwork Strand-on-the- following the structural engineers inspection 10 Green Jnr (Provisional Sum) £ 80,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Schools Capital Maintenance Programmes 2023-24Appendix A | 1 pages | Download |
PDF |
Schools Capital Maintenance Programme 2023-24Report | 8 pages | DownloadRead as text |
PDF |
Schools Capital Maintenance Programmes 2023-24Report | 5 pages | Download |
Follow Schools Forum at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Feb 2026 | Finance UpdateTo note the finance update | Noted | Open |
| 23 Feb 2026 | Early Years Budget and Hourly Rates 2026/27Resolved : Schools Forum noted: 1. Feedback from the consultation with early years providers on the 2026/27 early yea... | Noted | Open |
| 23 Feb 2026 | High Needs Budget 2026/27Schools Forum noted 1. noted the provisional 2026/27 High Needs (HN) budget requirement of £83.37M as proposed by the... | Noted | Open |
| 23 Feb 2026 | SEND & Alternative Provision Improvement Programme UpdateResolved : To note the update | Noted | Open |
| 23 Feb 2026 | Forward PlanResolved : 1. Schools Forum agreed the change in format for future Schools Forum meetings. Action: Members requested ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.