Resolved
Resolved : The submitted report was noted.
Gunnersbury Park Joint Advisory Panel noted this item on Friday 7 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved : The submitted report was noted.
And Progress Report Sports
Charles Blake, Project Officer, LBE 26/06/2017 Gunnersbury - Phase 3 Sports - Summary Designs have now been completed for Tender and are being collated by the team. The Leisure Operator procurement is ongoing, final 2 invited to interviews Tennis construction ongoing and on track Other opportunities in development
Detail GP Sports Facility All designs completed for tender, designs for Stage E approved by board. Awaiting final compilation and supporting narrative
GP Sports pitches Designs adapted to include improved drainage solution (also more cost effective) Designs completed for tender.
Tennis Court Construction Construction programme underway due to Complete July 2017. Asbestos found in ground removed at cost (absorbed within contingency)
Operator Procurement Currently out to final 2 bidders, final tenders due back 21/07/17.
Other Opportunities High wire activities tender documents in final draft version. Projected issue July 2017.
Remaining Milestones Target
ITT Receive final tender for Construction Contractor July 2017 Appoint project construction contractor August 2017 High wire activities tender to market July 2017 Complete construction of tennis courts July 2017 Appoint Leisure operator August 2017 Start on site for main contractor October 2017 Completion on site December 2018
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sports Progress ReportReport | 1 pages | DownloadRead as text |
Follow Gunnersbury Park Joint Advisory Panel at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2017 | Heritage Progress ReportThe submitted report was noted. | Noted | Open |
| 28 Apr 2017 | Dates of future meetingsIt was agreed to move the July 21 date forward to 7 July 2017. James Wisdom submitted apologies for the new date and ... | Agreed | Open |
| 18 Nov 2016 | Presentation on Sports HubIt was agreed that revised images would be circulated the following week to members of the Panel, as well as to other... | Agreed | Open |
| 21 Oct 2016 | Update on Park Events Licence ProposalIt was agreed to arrange an additional meeting with appropriate officers attending to discuss the licensing policy. | Agreed | Open |
| 15 Jul 2016 | Update on Park Events Licence ProposalIt was resolved that this should be a standing Agenda item in the future. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.