Progress Report Heritage Bridget Gregory, Project Manager 26/06/ 2017
Gunnersbury Phase 1 – Heritage Grant (HG) and Parks for People Grant Gunnersbury (PfP) Joint Advisory 1.0 Summary Panel Report Since the last GPJAP meeting a great deal of activity has continued with a high th June 2017 number of Architect Instructions (AIs) being issued. Quinn London Ltd (QLL) the main contractor and the design team manage all works and costs against these AIs together with the original contract scope and change control items. To give an example of the extent of work involved, the last 10 AIs included 152 repair items.
There continues to be a number of site findings, primarily in the mansion, that require increased repairs or scope adjustment to suit site conditions. The team has set up processes to closely monitor these and to manage costs and future risk elements including weekly meetings to monitor the draft AI list with costs and regular walkabouts with contractors to identify areas of work that could be changed or omitted.
2.0PfP - Capital Works update,
Below is an update on works progress across the PfP Project
2.1Restore the historic parkland setting of the two mansions including planting and heritage tree work, and works to the Museum frontage and drive
Phase 1 planting complete on south lawns and in café area. Capel Manor college students will be planting the new long border for the south lawns in May. The student planting design for viewpoint rockery has been selected and will be planted in the autumn. Further planting works will take place in autumn 2017 around the mansion
2.2Relocate the pitch and putt course to open up the historic parkland and present a nature trail
The Pitch and putt course operator vacated the site in February and the railings have now been removed. Mown grass footpaths are being established and the area is proving popular with park users. A new family friendly golf offer at Gunnersbury will be developed to follow on form the Sports project somewhere on the west playing field. 2.3 Restore the Orangery for public access and use as an events venue, and reinstate the Horseshoe lake
Horseshoe Lake - Recreation of the horseshoe Pond is complete and the pond has been filled. 75 water lilies have been planted along with other aquatic plants. The banks have been planted with shrub beds and new turf laid. Works to complete the sham bridge are nearing completion with just the handrails and copings to install followed by resurfacing of the footpath.
Orangery - Final drawings from the specialist roof-glazing contractor have been received and are to be reviewed against the existing roof structure, following final opening up. Works to repair the existing stone cornice at eaves level are almost complete in preparation for the formation of the brickwork wall head and installation of the perimeter gutter.
Further to concerns raised by the HLF regarding the proposed replacement of the existing cast iron gutter with new aluminium sections, works have been undertaken to clean off and assess the existing cast iron gutter sections. Three priced options have been presented within a report prepared by the specialist fabricator each offering various degrees of repair or replacement with new cast iron sections. This report and its recommendations are under discussion with HLF, HE and the Conservation Planner
Works to re-render the rear wall face have been completed in new lime render. Consideration is currently being given to the proposed decoration of the render finish.
2.4Repair the round pond, incl. hydrology works and bring back public boating activities
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Heritage Progress ReportReport | 6 pages | DownloadRead as text |
Follow Gunnersbury Park Joint Advisory Panel at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2017 | Sports Progress ReportResolved : The submitted report was noted. | Noted | Open |
| 28 Apr 2017 | Dates of future meetingsIt was agreed to move the July 21 date forward to 7 July 2017. James Wisdom submitted apologies for the new date and ... | Agreed | Open |
| 18 Nov 2016 | Presentation on Sports HubIt was agreed that revised images would be circulated the following week to members of the Panel, as well as to other... | Agreed | Open |
| 21 Oct 2016 | Update on Park Events Licence ProposalIt was agreed to arrange an additional meeting with appropriate officers attending to discuss the licensing policy. | Agreed | Open |
| 15 Jul 2016 | Update on Park Events Licence ProposalIt was resolved that this should be a standing Agenda item in the future. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.