Cabinet, Tuesday 20 March 2018 at 7.00pm

CEX242 Ventilation Programme for Schools - Phase 2

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 March 2018. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

That Cabinet approved the proposal to install ventilation in school classrooms. 2. That Cabinet noted that the cost of the second phase would be reimbursed by Heathrow Airport Limited (HAL) but would require initial funding by the Council. 3. That Cabinet approved, subject to final agreement with HAL being reached, a further £10m addition to the Capital Programme (£20m in total) and allocation of funding associated with the scheme as identified in section 6. Costs to be reimbursed by HAL. 4. That Cabinet authorised the Director of Asset Management & Major Projects or such officers as may be authorised to act on his behalf to agree heads of terms with HAL and take all necessary actions to progress the procurement and letting of the contracts in consultation with the Lead Member for Education and Children’s Services; to accept and award the construction phase works and other associated costs, professional fees and surveys.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet

Report for: ACTION

Contains Confidential No or Exempt Information

Title CEX42

Ventilation Programme for Schools – Phase 2 Member Reporting Councillor Tom Bruce, Lead Member for Education and Childrens’ Services Contact Details David Birch, Corporate Property [email protected] Tel: 020 8583 2880

For Consideration By Cabinet Date to be Considered 20 March 2018 Implementation Date if 30 March 2018 Not Called In Affected Wards ALL Keywords/Index Schools, Heathrow Airport Limited

1. Details of Recommendations

The Cabinet is asked to agree the following:

1. Approve the proposal to install ventilation in school classrooms.

2. Note that the cost of the second phase will be reimbursed by Heathrow Airport Limited (HAL) but will require initial funding by the Council.

3. Approve subject to final agreement with HAL being reached, a further £10m addition to the Capital Programme (£20m in total) and allocation of funding associated with the scheme as identified in section 6. Costs to be reimbursed by HAL.

4. Authorise the Director of Asset Management & Major Projects or such officers as may be authorised to act on his behalf to agree heads of terms with HAL and take all necessary actions to progress the procurement and letting of the contracts in consultation with the Lead Member for Education and Children’s Services; to accept and award the construction phase works and other associated costs, professional fees and surveys. If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Improvements to the learning environment for local Dec 2020 children will improve outcomes

2. Report Summary

The first phase was approved at Cabinet on 8 September 2015, REG319. This paper presents the proposal to enter into an agreement with Heathrow Airport Limited for delivery of the second phase of the school ventilation and overheating avoidance measures in school classrooms and other learning areas to improve the learning environment and outcomes of local children.

The local authority, in conjunction with Heathrow Airport Limited, is seeking to improve the learning environments for local children by mitigating the effects of aircraft noise due to their proximity to Heathrow Airport. Previous acoustic insulation measures have resulted in reduced ventilation in learning environments and we are now seeking to work collaboratively with Heathrow Airport Limited to address these issues.

Heathrow Airport Limited will reimburse the local authority for the costs associated with this scheme however the local authority will be required to co-ordinate the programme and cover the initial layout of funding.

The Cabinet is invited to consider the proposal and approve its implementation.

3. Reason for Decision and Options Considered

3.1A residual issue with the introduction of secondary and replacement glazing in schools is the need to keep windows closed to enjoy the acoustic benefits. Keeping windows closed reduces ventilation which increases the risk of CO2 build up and overheating.

3.2To address these issues and improve the learning environment and outcomes, we have agreed to work with Heathrow Airport Limited to investigate and design a programme of works to address ventilation and overheating.

3.3Solar film has been applied to the external windows to reduce the heat transfer from the sun. This assists with overheating however more robust measures are required.

3.4Works for phase 1 commenced in January 2017. Ventilation has now been installed at 5 schools, with works completed in December 2017 at the following schools:-

 Springwell Infants & Nursery, £1.1m  Bedfont Primary, £1.6m  Cranford Primary, £1.1m  Beavers Community Primary, £1.5m  Chatsworth Primary, £1.3m

4. Background Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CEX242 Ventilation Programme for Schools: Phase 2Report 183 KB DownloadRead as text

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies