a) That the report be noted. b) That information be provided about appeal decisions starting from May 2017. The information in the table will include the application site and reference number and whether the decision had been delegated or made by the Planning Committee.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
REPORT ON PERFORMANCE OF DEVELOPMENT MANAGEMENT AND PLANNING ENFORCEMENT OCTOBER 2018 Report by: Head of Development Management
Summary This report summarises the planning and enforcement decisions made under delegated authority and by the Planning Committee in June 2018.
It is recommended that members note the report.
1.0DEVELOPMENT MANAGEMENT
1.1Planning decisions, Enforcement Notices and appeal decisions, as well as documents relating to the application such as plans and reports are published on the Council’s website here:
2.1Decisions made by Planning Committee have a significant impact on shaping the borough and improvements to its social, economic and environmental well-being. The committee considers and determines planning applications for major and strategic development.
2.2The Planning committee’s decisions in June granted permission for applications that included the following development and benefits
110 New Units (30 affordable)
138 sqm commercial floorspace
Reserved Matters for the detail of the Brentford Football club Scheme
£1,440,211 Affordable Housing contribution to the HRA fund.
£30,000 Open Space contribution
£99,298 Carbon Offset Fund contrition £873,323 Hounslow Community Infrastructure Levy
£282,705.50 for the Mayor of London Community Infrastructure Levy
2.3The Planning committee’s decisions since June 2018 have granted permission for applications that included the following development and benefits:
2.6Planning Committee resolutions recommending how CIL received (should a planning permission be implemented) will be recorded and forwarded to the CIL Infrastructure Advisory Group in accordance with the Hounslow CIL and s106 governance framework. Recommendations for 2017/18 are as follows:
Month & Site & Reference CIL Infrastructure Project Year
3.0PERFORMANCE
3.1Government places emphasis on the speed of decision making, requiring 80% of household applications to be determined within 8 weeks, 65% of minor applications to be determined in 8 weeks, and 60% of major applications to be determined within 13 weeks. Note that the government’s performance measures do not include all of the work carried out by our section. For example, applications for works to trees, for details of conditions, pre-application enquiries and permitted development applications are not included in the government performance targets.
3.2
2 Others (including September 2018 Majors householder) Target 50% in 13 weeks 65% in 8 weeks Total 4 134 Percentage within 50% 92.4% target
Others (including 1 April 2017 to date Majors householder) Target 50% in 13 weeks 65% in 8 weeks Total 24 907 Percentage within 66.6% 93.5% target
4.0PLANNING APPEAL STATISTICS
4.1The table below shows the performance in planning appeal decisions over the last year.
Period Appeals allowed Appeals dismissed Total September 2018 1 (33.3%) 2 (66.7%) 3
Appeals Period Appeals allowed Total dismissed 1 April 2016 to 86 (2 32 (37.2%) 52 (60.5%) date Withdrawn2.3%)
4.2Below sets out a summary of those appeal decisions in September 2018
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.