To note that : i.) That the appointed auditors for 2018/19 Financial Statements for both the London Borough of Hounslow and London Borough of Hounslow Pension Fund is Mazars under the new Public-Sector Audit Appointers (PSAA) contract. ii.) That the audit approach to be undertaken by Mazars will be in line with the audit plan as attached in Appendix A and B. iii.) That the statutory deadline for the 2018/19 draft financial statements is the 31 May 2019 and for the final audited statement is 31 July 2019. iv.) That the first draft of the financial statements will be submitted to external audit for review and would be signed off by the Section 151. The Committee will be able to review and scrutinise the draft financial statements during June and will be required to sign the final 2018/19 Statement of Accounts at its meeting in July (date yet to be confirmed).
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
The Audit & Governance Committee are asked to note the following:
a) That the appointed auditors for 2018/19 Financial Statements for both the London Borough of Hounslow and London Borough of Hounslow Pension Fund is Mazars under the new Public-Sector Audit Appointers (PSAA) contract.
b) That the audit approach to be undertaken by Mazars will be in line with the audit plan as attached in Appendix A and B.
c) That the statutory deadline for the 2018/19 draft financial statements is the 31 May 2019 and for the final audited statement is 31 July 2019.
d) That the first draft of the financial statements will be submitted to external audit for review will be signed off by the Section 151. The Committee will be able to review and scrutinise this during June and will be required to sign the final 2018/19 Statement of Accounts at its meeting in July (date yet to be confirmed).
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will benefit, Dates by which they can link to Values expect to notice a difference An ambitious council delivering quality services and ongoing value for money
2. Report Summary The Public-Sector Audit Appointers (PSAA) have appointed Mazars as the London Borough of Hounslow’s external auditor for 2018/19.
The statutory deadline for the draft 2018/19 financial statements is the 31 May 2019 and for the final audited Statement of Accounts is 31 July 2019. As in previous years, the first draft of the financial statements will be submitted to external audit for review will be signed off by the Section 151. The Audit and Governance Committee will be able to review and scrutinise this during June and will sign the final 2018/19 Statement of Accounts at its meeting in July (date yet to be confirmed).
The appointed auditors, Mazars, have produced an outline audit plan for the audit of the London Borough of Hounslow financial statements (Appendix A) and for the London Borough of Hounslow Pension Fund financial statements (Appendix B).
The purpose of the audit plan is to summarise details of their engagement, their audit approach, highlight significant audit risks and areas of key judgements and where their work will be focused.
3. Reason for Decision and Options Considered The are no decisions outlined in this report.
4. Key Implications There are no other key implications for consideration.
5. Financial Details The financial implication of the award of the external auditor through the PSAA procurement are as outlined in the appendices attached to this report.
There are no further comments from the Strategic Director of Finance and Corporate Services.
6. Legal Details/Comments of Head of Governance Any legal implications with the Statement of Accounts have been presented at previous Audit & Governance Committee meetings and have been outlined in this report.
7. Value for Money The PSAA are appointed as the public sector audit appointers to ensure that through economies of scale the procurement delivers good value for money.
8. Sustainability Impact Appraisal A sustainability impact appraisal is not necessary.
9. Risk Management The council must ensure that costs are kept within the approved balanced budget and the appropriate levels of reserves are maintained. Key financial risks are reported in the Councils risk register.
10. Links to Council Priorities Financial management pledge. 11. Equalities, Human Rights and Community Cohesion No direct implications arising
12. Staffing/Workforce and Accommodation Implications There are no implications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.