a) That the Schools Forum agree the proposed Schools Capital Maintenance Programme 2019-20, as outlined in appendix A of the report. b) That the Schools Forum note the delivery of a new programme of School Condition Surveys, which will be delivered on a phased basis.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
3.1School Capital Maintenance Programme 2018-19 a. The council undertakes a regular programme of condition surveys across the LA maintained school portfolio. The surveys have been scrutinised and maintenance works have been identified and prioritised across the LA maintained school portfolio. b. The DfE has made an allocation of £2,942,209 for 2019/20 through the School Condition Allowance Grant. The grant is calculated using the number of Local Authority (LA) maintained schools within the Borough, excluding all Academies and Free Schools. Therefore, all proposed projects identified in this programme will be delivered at LA maintained schools only.
c. The projects identified in Appendix A are all priority works required to ensure that capital investment needs for school premises are met. Following Lead Member approval, schools will be notified of the project allocations. It should be noted that the costs identified for each project are indicative only. As with any list of projects across a wide portfolio of properties it may be necessary to modify the scope of the projects and/or project budgets due to unknown site factors and the outcome of procurement exercises. Any such modifications will need to be managed within the overall available budget.
3.2School Condition Survey Programme 2020-23
a. The current condition surveys are between four and six years old. The Council is committed to raising standards of attainment in all of its schools and believes that the quality of school premises plays a key part in achieving this aim. Therefore, there is an ongoing commitment to refurbishment / repair work of the LA maintained schools and through the strategic use of its Asset Management Plan data, the Council aims to continue to support the schools in the refurbishment & development of the property portfolio. The Council therefore needs to hold up to date information on the condition of our schools.
b. The Condition Survey Programme is funded using revenue contributions by LA maintained schools and will be undertaken in tranches during 2019/20 and 2020/21.
c. New surveys will be prioritised based on the age of the current survey, oldest first.
4. Next Steps
4.1Any feedback from Schools Forum on the proposed programme will be reflected included in the Single Member Decision to be approve the programme. This will be made by the Cabinet Member for Education, Children and Youth Services.
4.2Once the programme has been approved individual schools will be advised of an indicative programme. Once the Council has selected contractors timescales for the works to be undertaken can be agreed with individual schools.
5. Financial Details
5.1Financial Impact On The Budget (Mandatory)
The Schools Capital Maintenance Programme 2019-20 is to be funded from the DfE School Condition Allowance Grant 2019-20 of £2,942,209. The School Condition Survey Programme 2020-23 is being procured as a schedule of rates to facilitate the surveys being undertaken on a phased basis during 2019/20 and 2020/21.
5.2Comments of the Strategic Director – Finance and Corporate Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.