That Cabinet agree to: a) Proceed with the submission of a second round grant application to the National Lottery Heritage Fund (NLHF) for the regeneration of Boston Manor (Phase 2-the Park) by August 2019. b) Subject to the above being successful i) To proceed to the delivery phase for the Boston Manor Regeneration Project – Phase 2 Parks for People Boston Manor Park project. ii) Delegate authority to the Director of Customer Relations, Environment & Culture, in consultation with the Director of Corporate Services and Finance and the Lead Member for Green Policy and Leisure, to take all necessary steps to implement the delivery phase and to include any necessary procurement, subject to complying with the council’s Contract Procedure rules. iii) Delegate authority to approve the Business Plan for the sustainable management of Boston Manor Park (currently under development) to the Director of Customer Relations Environment & Culture, the Director of Finance and Corporate Services and the Lead Member for Green Policy and Leisure. c) Authorise the release of up to £660,000 capital as match funding for the delivery phase of the Boston Manor Regeneration Project (Phase 2 Parks for People Grant Boston Manor Park). d) To underwrite the project fundraising targets in order to bid for £3.63m of Lottery funding, in line with Lottery bid requirements. That Cabinet note that: e) Phase 1 of the regeneration of Boston Manor (Boston Manor House) is now in delivery following a successful second round application to the Heritage Lottery Fund (HLF) Heritage Grant funding programme. f) A successful GLA Good Growth Fund award is in place for an Arts Market under the M4 and is currently being designed. The Lottery Bid will support the groundworks in this area and landscaping in the immediate vicinity. That Cabinet note: g) The Landscape Architect’s Design Report for the restoration and improvement of Boston Manor Park (appendix 1). h) The outline Project Delivery Plan (appendix 2).
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential YES – Appendix 1 or Exempt Information
Title CEX397 Boston Manor Regeneration – Phase 2 – Park - NLHF Bid and Business Plan Update
Member Reporting Councillor Samia Chaudhary – Lead Member for Leisure and Green Policy Contact Details Victoria Lawson – Director of Customer Relations Environment & Culture – 020 8583 4463 David Stockdale – Heritage and Arts Services & Major Projects Manager – 020 8583 3823 For Consideration By Cabinet Date to be Considered 9 July 2019 Implementation Date if Not Called In Affected Wards Isleworth and Brentford Keywords/Index Heritage, Boston Manor, Park, House
1. Details of Recommendations
The Cabinet is asked to agree the following:
1. To proceed with the submission of a second round grant application to the National Lottery Heritage Fund (NLHF) for the regeneration of Boston Manor (Phase 2 – the Park) by August 2019.
2. Subject to 1 above being successful to: a. Agree to proceed to the delivery phase for the Boston Manor Regeneration Project – Phase 2 Parks for People Boston Manor Park project.
b. Delegate authority to the Director of Customer Relations Environment & Culture in consultation with the Director Corporate Services and Finance and the Lead Member for Green Policy and Leisure to take all necessary steps to implement the delivery phase and to include any necessary procurement subject to complying with the Council’s Contract Procedure Rules.
c. Delegate authority to approve the Business Plan for the sustainable management of Boston Manor Park (currently under development) to the Director of Customer Relations Environment & Culture, the Director of Finance and Corporate Services and the Lead Member for Green Policy and Leisure. 3. Authorise the release of up to £ 660,000 capital as match funding for the delivery phase of the Boston Manor Regeneration Project (Phase 2 Parks for People Grant Boston Manor Park).
4. To underwrite the project fundraising targets in order to bid for £ 3.63 million of Lottery funding in line with Lottery bid requirements.
The Cabinet is asked to note that:
5. Phase 1 of the regeneration of Boston Manor (Boston Manor House) is now in delivery following a successful second round application to the Heritage Lottery Fund (HLF) Heritage Grant funding programme.
6. A successful GLA Good Growth Fund award is in place for an Arts Market under the M4 and is currently being designed. The Lottery Bid will support the groundworks in this area and landscaping in the immediate vicinity.
The Cabinet is asked to note the following :
7. The Landscape Architect’s Design Report for the restoration and improvement of Boston Manor Park (Appendix 1).
8. The outline Project Delivery Plan (Appendix 2.)
If the recommendations are adopted, how will residents benefit? Benefits to residents Timeline Innovation – learning from experience Improved facilities and access at Boston Phase 2 will provide improved facilities in the Park, increase Manor House by 2021 accessible paths around the Park and actively manage the ecology, water features, treed areas, meadowland and river for residents and Improved facilities and users. access in the Park by 2021/22.
Spending wisely – every penny counts
Boston Manor is in decline and further inaction will occur larger costs Income generation and jeopardise a valuable heritage and open space asset. Investment stream by 2022 for the alongside a business plan and management and maintenance plan Park. will secure its future and generate income into the site.
Listening – responding Full consultation has We have developed options to regenerate the whole site whilst taken place during the responding to proposals from consultants, government agencies, development phase of local community organisations, stakeholders and users of the park Phase 2 in 2018/19. and house. 2. Report Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.