CEX477 Financial Monitoring Report P4 2020/21 (Cllr Shantanu Rajawat - Lead Member for Finance and Corporate Services)

Noted Executive 1 paper

Cabinet noted this item on Tuesday 8 September 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

a) That Cabinet noted the forecast General Fund revenue budget position of an underspend of £3.3m, including a £2.2m overspend as result of impacts of the Coronavirus, offset by a £5.5m underspend on ‘normal’ activities (paragraph 5.2). b) That Cabinet noted the forecast Schools Budget (DSG) position (paragraph 5.14). c) That Cabinet noted the forecast Housing Revenue Account (HRA) budget position (paragraph 5.16). d) That Cabinet noted the capital programme budget position (paragraph 6.1). e) That Cabinet noted the £163k of bad debts written off under delegated authority (paragraph 9.2). f) That Cabinet noted the performance against key corporate financial indicators (paragraph 10.1). That Cabinet agreed the following: General Fund Capital Programme g) Cabinet approved the re-phasing of £13.1m of the General Fund capital programme budget from 2020/21 into the 2021/22 and later years capital programme budgets (paragraph 7.3). h) Cabinet approved the net realignment of £3.1m of unused General Fund capital programme budgets into General Fund capital programme contingency budget for 2020/21 (paragraph 7.4). i ) Cabinet approved the addition of £1,113k to the General Fund capital programme for 2020/21, for highways and transport measures to increase pedestrian safety in response to the Coronavirus, funded by additional Transport for London and Department for Transport grants (paragraph 7.5). j) Cabinet noted the award of additional School Condition Allocations 2020/21 capital grant of £1,369k, and to approve the increase in the Schools Condition programme capital budget for 2020/21 by the £1,369k increase in this grant (paragraph 7.6). k) Cabinet approved the allocation of £58k from the General Fund capital programme contingency 2020/21 for the additional cost of special needs provision at Bolder Academy (paragraph 7.7). l) Cabinet approved the allocation of £52k from the General Fund capital programme contingency 2020/21 for additional costs of fitting out the ground floor of Eden House, Hounslow for use as a Children’s Services Young Persons Hub (paragraph 7.8). m) Cabinet approved the allocation of £182k from the General Fund Capital Programme contingency 2020/21 for the cost of refurbishment of a unit on Brentford High Street for use and a co located business space (paragraph 7.9). n) Cabinet approved an allocation of £482k from the General Fund Capital Programme contingency 2020/21 for the additional cost of the Feltham Major scheme (paragraph 7.10). o) Cabinet approved the allocation of £500,000 from the 2020/21 General Fund capital programme contingency to fund a further phase of the libraries capital programme (paragraph 7.11). p) Cabinet agreed the ... view the full minutes text for item 8.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 42 pages

Report for: ACTION

Contains Confidential NO or Exempt Information Title Budget Monitoring 2020/21 – Period 4 Member Reporting Councillor Shantanu Rajawat Cabinet Member for Finance and Corporate Services Contact Details Name: Clive Palfreyman Job Title: Executive Director of Finance and Resources Telephone: 020 8583 6682 e-mail: [email protected] For Consideration By Cabinet Date to be Considered 8 September 2020 Implementation Date if 17 September 2020 Not Called In Affected Wards All Keywords / Index Budget monitoring period 4, financial monitoring, revenue, capital, write-offs, KPIs

1. Details of Recommendations

Cabinet is asked to note the following:

a) To note the forecast General Fund revenue budget position of an underspend of £3.3m, including a £2.2m overspend as result of impacts of the Coronavirus, offset by a £5.5m underspend on ‘normal’ activities (paragraph 5.2). b) To note the forecast Schools Budget (DSG) position (paragraph 5.14) c) To note the forecast Housing Revenue Account (HRA) budget position (paragraph 5.16) d) To note the capital programme budget position (paragraph 6.1) e) To note the £163k of bad debts written off under delegated authority (paragraph 9.2) f) To note the performance against key corporate financial indicators (paragraph 10.1)

Cabinet is asked to agree the following:

General Fund Capital Programme g) To approve the re-phasing of £13.1m of the General Fund capital programme budget from 2020/21 into the 2021/22 and later years capital programme budgets (paragraph 7.3). h) To approve the net realignment of £3.1m of unused General Fund capital programme budgets into General Fund capital programme contingency budget for 2020/21 (paragraph 7.4).

i) To approve the addition of £1,113k to the General Fund capital programme for 2020/21, for highways and transport measures to increase pedestrian safety in response to the Coronavirus, funded by additional Transport for London and Department for Transport grants (paragraph 7.5).

j) To note the award of additional School Condition Allocations 2020/21 capital grant of £1,369k, and to approve the increase in the Schools Condition programme capital budget for 2020/21 by the £1,369k increase in this grant (paragraph 7.6).

k) To approve the allocation of £58k from the General Fund capital programme contingency 2020/21 for the additional cost of special needs provision at Bolder Academy (paragraph 7.7).

l) To approve the allocation of £52k from the General Fund capital programme contingency 2020/21 for additional costs of fitting out the ground floor of Eden House, Hounslow for use as a Children’s Services Young Persons Hub (paragraph 7.8).

m) To approve the allocation of £182k from the General Fund Capital Programme contingency 2020/21 for the cost of refurbishment of a unit on Brentford High Street for use and a co located business space (paragraph 7.9).

n) To approve an allocation of £482k from the General Fund Capital Programme contingency 2020/21 for the additional cost of the Feltham Major scheme (paragraph 7.10).

o) To approve the allocation of £500,000 from the 2020/21 General Fund capital programme contingency to fund a further phase of the libraries capital programme (paragraph 7.11).

p) To agree the following three allocations from New Homes Bonus of £23k to cover the revenue costs arising from the fitting out of the ground floor of Eden House, Hounslow, £36,500 for the development of the unit on Brentford High Street and £45k for carrying out initial feasibility studies on the potential for development of two operational buildings used by Children’s and Adults (paragraphs 7.8, 7.9 and 7.12).

HRA Capital Programme q) To approve the rephasing of the Council House Building programme over the period 2020/21 to 2023/24 as set out in paragraph 7.17 and the establishment of a COVID 19 contingency budget of £9.5M within the overall programme budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CEX477 Financial Monitoring Report P4 2020/21 (Cllr Shantanu Rajawat: Lead Member for Finance and Corporate Services)Appendix 42 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. CEX477 Financial Monitoring Report P4 2020/21 (Cllr Shantanu Rajawat - Lead Member for Finance and Corporate Services)This decision
  2. CEX632 Corporate Plan, Delivery Plan and Financial StrategyAgreed
  3. CEX613 Updated Scheme for Financing Schools and Schools Financial RegulationsApproved
  4. CEX573 Medium Term Financial Strategy 2021/22 - 2024/25Agreed
  5. CEX552 Medium Term Financial Strategy 2021/22 - 2024/25Noted
  6. CEX483 Financial Monitoring Report (Period 10) 2020-21Noted

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open