CEX593 Traffic and Transport Multi-year Delivery Programme 2022-2025

Approved Executive 3 papers

Cabinet approved this item on Tuesday 19 October 2021. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED – · To approve the implementation of the 3-year LIP/S106 funded Capital programme from 2022/23 through to 2024/25 as set out at Appendix A of the report and the inclusion of this programme in the Council’s general fund capital programme for 2022/23 to 2024/25. · To note that the community-led schemes as set out in paragraph 11 of the report will require funding to be allocated via the Council’s 2022/23 to 2024/25 general fund capital programme. · To delegate authority to the Assistant Director of Traffic, Transport & Parking, in consultation with the Lead Member, to vary the delivery of the multi-year programme to meet any operational needs.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 7 pages

Report for: ACTION

Contains Confidential No or Exempt Information Title CEX593 Traffic and Transport Multi-year Delivery Programme 2022-2025 Member Reporting Councillor Hanif Khan, Lead Member for Transport and One Hounslow Contact Details Victoria Lawson, Executive Director of Environment, Culture Customer Services [email protected]; 020 8583 4463

Jefferson Nwokeoma, Assistant Director of Traffic, Transport and Parking [email protected] For Consideration By Cabinet

Date to be Considered 19 October 2021 Implementation Date if Not Called In November 2021 Affected Wards All Keywords/Index Transport, Recovery, Public Realm

1. Details of Recommendations

The Cabinet is asked to:

1) Approve the implementation of the 3-year LIP/S106 funded Capital programme from 2022/23 through to 2024/25 as set out at Appendix A and the inclusion of this programme in the Council’s general fund capital programme for 2022/23 to 2024/25. 2) Note that the community-led schemes as set out in paragraph 11 will require funding to be allocated via the Council’s 2022/23 to 2024/25 general fund capital programme. 3) Delegate authority to the Assistant Director of Traffic, Transport & Parking, in consultation with the Lead Member, to vary the delivery of the multi-year programme to meet any operational needs. 2. Report Summary This report outlines a multi-year transport programme for Hounslow. The Council’s Transport Strategy is set out in a document known as the ‘Local Implementation Plan (LIP)’. Published in 2019, the Council’s Local Implementation Plan 3 (LIP3) transport strategy, details how the borough plans to spend grant funding awarded by Transport for London between 2020/21 until 2022/23. Schemes only qualify for grant funding if they are designed to help deliver the outcomes set out in the Mayor’s Transport Strategy.

Whilst TfL have approved the council’s LIP3’s spending plans for its full three-year duration, the funding available through the LIP grant is insufficient to fund the current capital programme. This report is seeking to formalise the arrangements for the 3- year period from 2022/23 to 2024/25 to ensure the council can deliver the infrastructure necessary to achieve the Mayoral Transport Strategy outcomes and the council’s transport key targets and vision of a transport network and public realm will enable and encourage the development of a prosperous, healthy, accessible and safe environment for all residents and visitors.

3. Reason for Decision and Options Considered

Introduction and Policy Context 1. The Council’s Transport Strategy is set out in a document known as the ‘Local Implementation Plan (LIP)’. This is a statutory document prepared under Section 145 of the GLA Act (1999) that sets out how the borough proposes to implement the Mayor of London’s Transport Strategy (MTS) in its area, as well as contributing to the other local and sub-regional goals.

2. Published in 2019, the Council’s Local Implementation Plan 3 (LIP3) transport strategy, details how the borough plans to spend grant funding awarded by Transport for London between 2020/21 until 2022/23. Schemes only qualify for grant funding if they are designed to help deliver the outcomes set out in the Mayor’s Transport Strategy.

3. Whilst TfL have approved the council’s LIP3’s spending plans for its full three- year duration, the funding available through the LIP grant is insufficient to fund the current capital programme (detailed in Appendix A). Historically reliance has been on S106 and CIL contributions to assist in making up the shortfall, however given the effects of the pandemic and the subsequent reduction of the 2020/21 LIP grant funding, there is now a significant backlog in the delivery programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CEX593 Traffic and Transport Multi-year Delivery Programme 2022-2025: Appendix A: Capital Programme 22-25Appendix 2 pages Download
PDF
CEX593 Traffic and Transport Multi-year Delivery Programme 2022-2025: Appendix B Community Led SchemesAppendix 2 pages Download
PDF
CEX593 Traffic and Transport Multi-year Delivery Programme 2022-2025Report 7 pages DownloadRead as text

At this meeting

Whole meeting

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies