Approved Planning 2 papers

Planning Committee approved this item on Thursday 6 January 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That planning permission for retrospective planning application 00443/H/P1 for the retention of an outdoor rowing facility for a temporary period of two years at Ferry Wharf, land to the south east of Ferry Lane, Brentford be approved, subject to the conditions set out in the report.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Planning Committee, 15 pages

Summary

1.1The application seeks to gain retrospective planning permission for the retention of an outdoor rowing facility and associated structures for a temporary period of two years.

1.2The proposal would be an appropriate temporary use of the site; it would not lead to any significant adverse impacts to neighbouring residential amenity, the character of the area or local highway conditions.

1.3Therefore the application for temporary consent is recommended for approval subject to safeguarding conditions.

2.0SITE DESCRIPTION

2.1The site makes up part of Ferry Wharf to the south east of Ferry Lane and contains a parcel of land on the north eastern side of the Wharf. Ferry Wharf is enclosed to the south and east by the River Thames with a slipway to the south of the Wharf. Aerial photography suggests that the site has been vacant since at least 2003, but historically the site was used as a wharf accommodating structures used as a boathouse and for industrial purposes.

2.2To the east of the site are two residential moorings.

2.3The site is within an Archaeological Priority Area and Flood Zone 3. The site adjoins a Site of Importance for Nature Conservation (SINC) to the east, the boundary with the River. A section of this SINC runs up the slipway and stops just outside the site. Site location plan

Aerial image of wider site 3.0 HISTORY

3.1The application site made up part of the wider Ferry Quays redevelopment site. The Ferry Quays development has a complex planning history and development build-out, with a number of planning permissions and associated legal agreements including variations to those legal agreements. There were two main legal agreements relating to the site. One relates to an outline planning permission for the full site (00443/G/P3) which was completed on 2 July 1999, and the second to a detailed planning permission (00443/G/P7), for a smaller site excluding the land to the west of Town Meadow and Lots Ait, which was completed on 28 July 2000.

3.2The majority of the redevelopment of Ferry Quays has been completed however one of the elements has not, the provision of a building at Ferry Wharf, which, as approved, would provide public benefit in the form of a boat storage / repair facility and history wall, provision for mooring activities, and the enhancement of public realm areas and riverside walks.

Plan from Legal Agreement of Ferry Quays redevelopment showing Ferry Wharf b uilding

3.3The site has since been sold off separately and the boathouse was never constructed. No formal enforcement action was taken.

3.4Application reference 00443/M/P2 was refused on 7 th April 2005 for the erection of a three storey building comprising restaurant and boat storage/repair area at ground floor, gym and ancillary café at first floor and 2 x 4- bed ancillary staff flats at second floor. The reasons for refusal where:  Height, scale, bulk and design would be incongruent in this riverside location, incompatible with the surrounding development and compromise views from the opposing bank of the Thames.  Fails to provide a suitable or usable mix of riverside activities.  Would lead to a reduced floodwater storage volume for river water and increase the risk of flooding along the River Thames.  The location of residential units forward of local flood defences without dedicated permanent dry access would be inappropriately sited and harmful to residents’ safety.

4.0DETAILS

4.1The application seeks retrospective planning permission for the retention of an outdoor rowing facility for a temporary period of two years. The use commenced in March 2021.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ferry Wharf Committee Site PlanPlan 1 pages Download
PDF
Ferry Wharf, Land to the South East side of Ferry Lane, BrentfordReport 15 pages DownloadRead as text

At this meeting

Whole meeting

More from Hounslow Planning Committee

All decisions
MeetingDecisionOutcome
6 Aug 2026 80 - 82 Staines RoadResolved – that planning application P/2023/2705, erection of two apartment blocks of 3-5 storeys and 4-6 storeys to ... Approved Open
11 Jun 2026 64E Waldeck Road, ChiswickResolved – that planning application P/2026/0264, erection of a single storey rear extension to the house, was approv... Approved Open
5 Mar 2026 Central Park EstateResolved – that planning application P/2024/4226, erection of four commercial units of mixed uses B2 (General Industr... Approved Open
5 Feb 2026 Block B, Brentford Lock WestResolved – that planning application P/2025/1313, erection of part 10, part 11 storey building comprising 124 residen... Refused Open
5 Feb 2026 97 Devonshire RoadResolved – that planning application P/2025/0646 , erection of a rear roof extension with four front roof lights and ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies