a) That planning permission for planning application P/2022/2977 for the Erection of a sculpture on the roundabout on Grant Way, be approved subject to the conditions set out in the report and the prior completion of a satisfactory S.106 agreement, highways agreements or unilateral undertaking, as set out in section 11.0 of the report and heads of terms set out in section 8.4 of the report.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.1The proposal being considered under this application is for the erection of a sculpture on the roundabout at the northern end of Grant Way.
1.2The design of the sculpture would preserve the character and appearance of the surrounding area and would not harm neighbouring properties or highway safety.
1.3The proposed development, subject to conditions, would comply with Development Plan Policies.
1.4The application is therefore recommended for approval, subject to conditions and a legal agreement
2.0SITE DESCRIPTION
2.1The application site is part of the wider BskyB Osterley Campus with primary access from Grant Way, which is in turn served by Syon Lane.
2.2The wider campus contains a number of buildings including the Sky Central, the Sky Studios, the Innovation Centre building and the Hub Building. The Sky Studios is the largest building on site and falls outside the boundary of this application.
2.3The application site is within a Significant Industrial Location as allocated in the adopted Local Plan.
2.4The site has a Public Transport Accessibility (PTAL) level of 1a (Very Poor) and 2 (Poor). 2.5 Grant Way forms the primary access point from Syon Lane. The wider campus is accessed through a 24-hour security gate. There is an existing Traffic Order on Grant Way which prohibits pedestrians and vehicles from entering certain parts of Grant Way. Grant Way is an adopted highway.
2.6This application relates to the roundabout at the northern end of Grant Way.
Figure 1 Site Location Plan
3.0HISTORY
3.100558/A/P71(NMA) Non-Material Amendment – Proposed new ‘Sky Zero’ sculptural installation on the roundabout at the northern terminus of Grant Way. Refused 14 September 2022 3.2 00558/A/P71 Landscaping works to Grant Way on site. Approved 22 December 2022 3.3 00558/A/P70 Landscaping works to the Plaza in centre of site and the relocation of the existing satellite dishes to the roof of Sky 4 Approved 21 December 2022 3.4 00558/A/P72 External works to existing security gatehouse and turnstiles including erection of timber cladding and canopy, addition of new planters and associated landscaping, installation of lighting and illuminated sign. Approved 6 August 2021 4.0 DETAILS OF PROPOSAL
4.1The proposal presented under this application is for the erection of a sculptural installation on the roundabout at the northern terminus of Grant Way. The sculpture would form part of the wider improvements to public realm on the campus.
4.2The sculpture comprises a ‘floating tree’ suspended from three stainless supports. The entire structure would have a maximum height of 6.75 metres.
Figure 2 Visualisation of proposed sculpture
5.0CONSULTATIONS
5.1A site notice was posted on 4 October 2022. No responses were received.
6.0POLICY
Determining applications for full or outline planning permission
6.1The determination must be made in accordance with the development plan unless material considerations indicate otherwise. Local finance considerations must also be assessed.
National Planning Policy Framework
6.2The National Planning Policy Framework (NPPF) was revised on 20 July 2021. The National Planning Practice Guidance (NPPG) is an online guidance resource that supports the NPPF. These may be material considerations. They will be cited in application reports where relevant to the case at hand
Development Plan
6.3The Development Plan for the Borough comprises the Council's Local Plan (adopted by the Council on 15 September 2015), the West London Waste Plan and the London Plan 2021 (published by the Greater London Authority on 2 March 2021).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.