Hounslow Heat Network Project

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 11 February 2025. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Resolved : Cabinet agreed that the could proceed to the next stage of its development of a phase 1 scheme, as referred to in Section 4.1 of the submitted report; · Cabinet agreed to the submission of a bid to the Green Heat Network Fund (GHNF) for £11m capital funding for commercialisation and construction of the Phase 1 scheme; · Cabinet noted that the recommended route to secure a commercial delivery and funding partner would be agreed following completion of activity identified in the Climate Emergency Action Plan update agreed by Cabinet in January 2025.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet, 18 pages

Report for: ACTION

Contains Confidential Y or Exempt Information Appendix 1

Cabinet Key Decision Y

Report Title Hounslow Heat Network Project

Councillor Katherine Dunne Member Reporting Portfolio holder for Climate, Environment and Transport

Andrew Cox, Director of Climate and Strategic Contact Details Programmes, [email protected]

For Consideration By Cabinet

Date to be Considered Tuesday 11 February 2025

Deadline for call-in Wednesday 19 February 2025

Implementation Date Thursday 20 February 2025 (if not Called In)

Affected Wards (All Wards);

Approved by 1. Recommendations

Cabinet is asked to:

1. Agree that the Hounslow Heat Network Project can proceed to the next stage of its development of a phase 1 scheme, as referred to in Section 4.1

2. Agree to the submission of a bid to the Green Heat Network Fund (GHNF) for £11m capital funding for commercialisation and construction of the Phase 1 scheme

3. Note that the recommended route to secure a commercial delivery and funding partner will be agreed following completion of activity identified in the Climate Emergency Action Plan update agreed by Cabinet in January 2025

2. Report Summary

2.1Since 2022, the Council has been investigating opportunities for a low-carbon heat network in the borough, as it committed to do in its Climate Emergency Action Plan. Following a feasibility study in 2023, more detailed proposals have now been developed for an initial phase of the network, which is suitable to be taken forward for Commercialisation.

2.2The proposed Phase 1 scheme would take heat from Mogden sewage treatment works to supply low-carbon heating to Council, public sector and private sector buildings in Isleworth and Brentford. This scheme was identified as the most viable of a range of options, through technical, economic and social metrics based on the project's critical success factors.

2.3A draft Outline Business Case (OBC) has been prepared for this phase 1 proposal. This sets out the economic, commercial and financial case for a possible initial network in Isleworth and Brentford, which is expected to meet criteria to be eligible for grant funding from the Green Heat Network Fund and be sufficiently attractive to private sector delivery partners for their investment.

2.4This scheme is anticipated to offer one of the most cost-effective means to decarbonise heating in the buildings proposed for connection. While the draft OBC will undergo further refinement, the underlying techno-economic basis is considered to be well-developed and so the key scheme characteristics are unlikely to change significantly.

2.5Results of soft market testing indicate that while most potential delivery partners would be open to a joint venture with the Council they do not actively seek equity investment from the Council. Some would prefer the Council to have a golden share or to provide non-cash assets, such as land for an energy centre, where this would facilitate network development.

2.6Implications for the Council are identified in the report, including potential capital costs of connection for those Council buildings proposed for connection to the network; other possible costs, such as upgrades to existing building infrastructure; and the impact on heating costs for the Council and other users.

2.7The main project risks are also identified in Section 5. While significant, these are not considered to be unusual for a project of this type, scale and complexity, and appropriate mitigation strategies are in place.

2.8Following Cabinet approval, a bid for £11m capital funding will be submitted to the Green Heat Network Fund (closes on 11 April 2025). This will enable the project to proceed to commercialisation and, subject to future Cabinet decisions, procurement of a delivery partner to construct the scheme. The Council will not be expected to provide any match funding for commercialisation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hounslow Heat Network ProjectReport 18 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Hounslow Heat Network ProjectThis decision
  2. Response to the initial stakeholder consultation on the proposal to amalgamate Hounslow Heath Infant & Nursery and Hounslow Heath Junior schoolsAgreed
  3. Hounslow Heath Post Office, 434 Staines Road, HounslowRefused
  4. Hounslow Heath Golf Course, Staines Road, HounslowApproved
  5. Hounslow Heath Golf Course, Staines Road, HounslowApproved
  6. CEX396 Hounslow Council's draft response to Heathrow Airport Ltd.'s statutory consultation on Airport Expansion - (Cllr Steve Curran, Leader of the Council and Lead Member for Corporate Strategy, Planning and Regeneration)Agreed

More from Hounslow Cabinet

All decisions
MeetingDecisionOutcome
14 Jul 2026 Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... Agreed Open
14 Jul 2026 Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... Agreed Open
14 Jul 2026 Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... Noted Open
14 Jul 2026 Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... Approved Open
14 Jul 2026 Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies