Resolved
Resolved : · Cabinet approved the completion of the Third Party Spend Programme and transition to Business as Usual (BAU). · Cabinet approved the return of the £121k underspend in programme budget to the One Hounslow Transformation Reserve.
Cabinet approved this item on Tuesday 15 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved : · Cabinet approved the completion of the Third Party Spend Programme and transition to Business as Usual (BAU). · Cabinet approved the return of the £121k underspend in programme budget to the One Hounslow Transformation Reserve.
Report for: ACTION
Contains Confidential N or Exempt Information
Cabinet Key Decision N
Report Title Completion of the Third Party Spend Programme
Councillor Shantanu Rajawat Member Reporting Leader of the Council and Portfolio holder for Strategy, Resources and External Affairs
Jake Bacchus Contact Details [email protected] Executive Director of Finance and Resources
For Consideration By Cabinet
Date to be Considered Tuesday, 15 April 2025
Deadline for call-in 23 April 2025
Implementation Date 24 April 2025 (if not Called In)
Affected Wards (All Wards);
Approved by 1. Recommendations
Cabinet is asked to:
1. Approve the completion of the Third Party Spend Programme and transition to Business as Usual (BAU)
2. Approve the return of the £121k underspend in programme budget to the One Hounslow Transformation Reserve.
2. Report Summary
2.1This report seeks Cabinet approval to formally close the Third Party Spend programme, following the completion of programme delivery.
2.2The report sets out how the objectives of the programme were met and the financial and non-financial deliverables that have been secured.
2.3The Third Party Spend programme commenced in July 2022 with the vision for the programme agreed as:
‘The Council has an effective commissioning cycle, driving value for money, high performing, and innovative supplier delivery, which generates savings, provides demonstrable value (economic and social) and ensures strategic fit with Council and community aims and need.’
2.4A number of projects, divided into two tranches, focused on delivery of:
• Ongoing reduction of general fund budgets of £2.28m by 2026/27.
• An options appraisal to determine the requirements of the Corporate Services Contract extension and implementation of arrangements for delivery of the services from October 2024.
• A new governance approach for successful partnership delivery with the Lampton Group, alongside a defined Strategic Intent, Growth Framework, Shareholder Agreement and updated Articles of Association.
• A commissioning, procurement and contract management operating model that maximises value to the council and residents from third party spend and that ensures compliance with the Procurement Act 2023.
2.5The report summarises delivery of each project, how its’ objectives were met and describes products handed over to BAU for ongoing management.
2.6£978k has been spent on the delivery of the Third Party Spend programme, leaving an underspend of £121k against the agreed programme budget, which following authorisation of programme closure, will be returned to the One Hounslow Transformation Reserve. 3. Background and links to Corporate Priorities
3.1The CEX632 Corporate Plan, Delivery Plan and Financial Strategy report, presented and approved at Cabinet in July 2022, set out a funding gap of £22.1M for FY23/24 and £5.6M for FY24/25.
3.2The Third Party Spend programme was included in the Delivery Plan as one of the key vehicles to address the funding challenge with the vision that:
‘The Council has an effective commissioning cycle, driving value for money, high performing, and innovative supplier delivery, which generates savings, provides demonstrable value (economic and social) and ensures strategic fit with Council and community aims and need.’
3.3Since the Delivery Plan was approved, the funding gap has increased significantly, owing to a multitude of factors including inflation and increased demand on services, strengthening the strategic case and financial driver for delivering this programme.
3.4Objectives set out for the TPS programme include:
• To identify and deliver net savings of £2.28m, to be realised between 2024/25 and 2026/27.
• To review, appraise options, and implement appropriate delivery solutions for services within the Corporate Services Contract, in line with the contract break point in September 2024.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Completion of the Third Party Spend ProgrammeReport | 8 pages | DownloadRead as text |
Follow Cabinet at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Budget Outturn 2025-2026Resolved : Cabinet agreed to the following: General Fund 1. Approve the General Fund net revenue o verspend of £1.6m ... | Agreed | Open |
| 14 Jul 2026 | Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ... | Agreed | Open |
| 14 Jul 2026 | Quarterly Performance Reporting 2025-2026 (Q4)Resolved : Cabinet noted the corporate performance report for Quarter 4 (January to March 2026) detailed in Appendix ... | Noted | Open |
| 14 Jul 2026 | Procurement Plan - July 2026Resolved : Cabinet approved the following: 1. Specialist Support and Therapies services: a) Approve commencement of p... | Approved | Open |
| 14 Jul 2026 | Updated West London Waste Plan - Regulation 19 Consultation and Submission to Secretary of State for ExaminationResolved : Cabinet recommended to Borough Council: 1. To approve the ‘Regulation 19’ publication of the Proposed Subm... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.