Noted variations to the capital expenditure incurred by the Council in 2002/03 in comparison with the approved programme and the implications on the programme for the current year, agreed to fund the cost of rebuilding a retaining wall at Hen Brook in St Neots, estimated at £48,000, from savings in the 2002/03 programme, approved additional funding of £19,000 for the refurbishment of the Ramsey changing rooms and deferred consideration of a request for funds from St Neots Leisure Centre to extend the kitchen facilities to enable enquires to be made into the possibility of packaging the schemes in the Leisure Centres condition survey into one major contract to be managed by an External facility management company.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
BUDGETARY CONTROL CAPITAL PROGRAMME 2002/03 and 2003/04 (Report by the Head of Financial Services)
1. PURPOSE
1.1This report outlines the outturn position for 2002/03 and the implications for 2003/04. Progress during the current year is also considered and proposals are made for necessary cost variations.
1.2More detailed information on specific schemes can be obtained from the relevant Head of Service. Some figures may still be subject to minor changes as the accounts are not yet finally closed.
2. THE COUNCIL’S 2002/03 OUTTURN POSITION
2.1Over 80% of the capital schemes completed last year were on time or no more than 8 weeks late. Annex A shows details of estimated completion dates and cost variations on all current schemes.
2.2Planned capital expenditure (including the gross spending on Disabled Facilities Grants and Social Housing Grant) in 2002/03 amounted to £7,486k last year compared to an approved total of £9,397k. Most of the reduction (£1.8M) is due to slippage or deliberate deferral, of which £1.2M has been reported previously.
2.3A net saving of £54k has also been identified and Annex B contains the details of this.
3. MONITORING OF THE 2003/04 PROGRAMME
3.1The approved 2003/04 programme of £14,719k has been increased by £1,753k, as a result of slippage, resulting in a total of £16,472k.
3.2Towards the end of 2002/03 the Government changed the system for Social Housing so that funding would no longer be via local authorities. The full implications of this change cannot yet be assessed but the Council’s £2,755k capital provision for payments to Registered Social Landlords was conditional upon reimbursement by the Government so it can no longer take place without further approval. An update on the position will be presented to Cabinet in due course.
3.3Annex C details the variations that are already anticipated and shows slippage or deferral of £449k. Reference to Annex A will show the forecast change in completion dates. All schemes will be receiving a thorough review over the next month as part of the annual MTP process to ensure that forecast completion dates are realistic and achievable.
3.4Tenders have recently been received for two Leisure Centre projects which are significantly, in percentage terms, above the sums allocated. The refurbishment of the Ramsey changing rooms is £19k more than the £72k originally earmarked from the Condition Survey budget. It is essential that this scheme goes ahead in parallel with the closure for the roof replacement in order to minimise disruption. The other scheme is the Bar/Kitchen/Creche extension at the St Neots Leisure Centre where, following a meeting with the lowest tenderer, the price is still £69k above the budget of £272k.
3.5It is considered that the buoyant building works sector and the tendering of projects one at a time is resulting in limited competition and hence higher prices. The Ramsey project needs to go ahead but it is proposed that the St Neots scheme be deferred pending an investigation into how Leisure Centre building and maintenance work might be combined into a long-term contract with a suitable partner. The extra cost at Ramsey and for the investigation will be met from the Condition Survey provision.
3.6Problems have been identified with a retaining wall on Hen Brook in St Neots and although the Council’s legal liability is imprecise it is considered important that the wall and adjoining lengths are rebuilt as soon as possible to avoid future flooding problems. The estimated cost of the scheme is £48k and it could be funded from last year’s net savings of £54k shown in Annex B.
4. CONCLUSION
4.1Over 80% of schemes completed last year were on time or less than 8 weeks late. Capital spending delays were experienced in 2002/03 and there was a cost saving of £54k. Some delays are emerging for 2003/04 and Annex D gives the latest expected position on each scheme. A thorough review on completion dates is underway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.