AI summaryHuntingdonshire District Council Cabinet approved a £3.576m capital budget increase, raising the programme from £34,631 to £38,207. It also reviewed revenue and capital performance for quarter two of 2026/27. [D] [P30]
What happens nextFurther funding report planned [P40]One Leisure funding source and preliminary costs. [P40]
Who it affectsNot stated
What was decided
Cabinet reviewed quarter two General Fund revenue performance and the forecast final result for 2026/27. Report 1.1
Cabinet reviewed quarter two Capital Programme performance and its forecast final result for 2026/27. Report 1.2
The approved capital budget increase was £3.576m (£3.381m + £0.195m). Report 1.3
Why
The General Fund was forecast at £27.785m against a budget of £28,151m. This was an underspend of approximately (£0.366m) before reserve transfers and a net forecast underspend of (£3.639m) after them. Report P15
Priory Centre funding was already approved, so £3.176m was needed to align the capital budget with the agreed funding, project scope and financing. Report P46, P47
The One Leisure project cost fell, but external funding fell further. The Council therefore still needed extra funding to proceed, with a further Cabinet report planned. Report P35, P40
What happens next
A further report will go to Cabinet with the proposed funding source for the One Leisure project and any confirmed preliminary costs. Report P40
Financial resource changes will be reflected in quarterly monitoring reports, future budgets and the MTFS. Report P94
Effective public budget monitoring and reporting will continue, as required by the Constitution and financial regulations. Report P85
The money
£3.576m (£3.381m + £0.195m) Approved increase to the capital budget Report 1.3
£34,631 Capital programme budget before the increase Report P30
£38,207 Capital programme budget after the increase Report P30
£3.176m Priory Centre capital expenditure budget increase Report P47
£0.205m Properties Houses budget movement linked to returned Government resettlement funding Report P48, P49
£836,883 Latest estimated One Leisure project cost Report P33
£27.785m Forecast General Fund revenue outturn Report P15
(£3.639m) Net forecast underspend after reserve transfers Report P15
Options considered
Chosen: Option 3: Deliver through the HDC Capital Programme. Withdraw from the Football Foundation funding offer and deliver the project directly. The current estimated cost creates an additional HDC capital funding requirement of approximately £217,000. Report P38, P39
Rejected: Option 1: Do not proceed. Discontinue the project and avoid the need for existing HDC and CIL funding. Report P38, P39
Rejected: Option 2: Proceed with Football Foundation funding. Accept the revised grant offer of approximately £217,000 and deliver the project subject to the funding conditions. Report P38, P39
Implications
Financial: The capital programme rises from £34,631 to £38,207 after the £3,576 increase. Report P30
Financial: The Priory Centre budget increases by £3.176m to match funding already agreed. Uncommitted Government resettlement funding was returned because suitable remaining homes could not be secured within the available funding and viable values. Report P47, P49
Financial: One Leisure still needs more Council money because the grant reduction exceeded the project cost reduction. The additional HDC requirement is approximately £217,000. Report P35, P38, P40
Financial: The General Fund forecast is a net underspend of (£3.639m) after a (£3.272m) transfer from reserves. Report P15
Legal: The Constitution and financial regulations require effective budget monitoring and public reporting to Cabinet and the Overview and Scrutiny Panel. Report P85
Risk: Budget and service risks will be recorded on local risk registers and the Council's overall risk register. Report P98
Climate: The impacts of expenditure in climate and environment related budgets need to be noted, particularly for the Parks service. Report P89
Other: Resource changes will be handled through later quarterly reports, budgets and the MTFS. The retrospective report has limited local government reorganisation impact. Report P94, P97
Who and where
Services funded through the General Fund Report P15, P28
The Priory Centre project Report P47
The One Leisure St Ives Outdoor 3G Football Pitch project Report P32, P40
The Football Foundation Report P38, P39
Council Tax and Business Rates taxpayers Report P62, P63
Ukrainian and Afghan families supported through the Government resettlement scheme Report P49
Parks and climate related services Report P89
Council debtors Report P68, P70
Timeline
February 2026: The 2026/27 General Fund revenue budget and Capital Programme were approved. Report 2.1, 2.2
February and March: Council Tax and Business Rates collection was expected to recover as later instalments fell due. Report P65
July 2026: A proposal to allocate remaining Cambridgeshire Horizons legacy funding was presented, with the Priory Centre identified as eligible. Report P42
28 July 2026: The One Leisure project options report went to the Treasury and Capital Management Group. Report P37
end September 2026: The quarter two General Fund revenue and Capital Programme reporting period ended. Report 1.1
15 September 2026: Cabinet approved the Priory Centre funding proposals and supported Option 3 for the One Leisure project. Report P37, P39, P46
30 September 2026: Outstanding debt was analysed, including balances that were not yet overdue. Report P68, P69
2026-11-17: Cabinet reviewed quarter two finances and approved the capital budget increase.
Plain English for the jargon
Quarter 2: The half year reporting point at the end of September 2026. [1.1]
Forecast outturn: The forecast final result for 2026/27 based on half year delivery. [1.1]
General Fund revenue budget: The revenue budget reviewed for quarter two performance and the full year forecast. [1.1] [2.1]
Capital Programme: The programme of capital scheme spending reviewed for quarter two performance and the full year forecast. [1.2] [2.2]
MTFS: Medium Term Financial Strategy. [2.1]
CIL: Community Infrastructure Levy funding. [P36]
HDC: Huntingdonshire District Council. [P38]
TCMG: Treasury and Capital Management Group. [P37] [P42]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter two and the forecast outturn for the financial year 2026/27 based on performance in quarter 2 as detailed in Appendix 1 and Appendix 2; (2) considered and commented on the Capital Programme’s financial performance in quarter two and the forecast outturn for 2026/27 as based on the performance in quarter, as detailed in Appendix 3; and (3) approved an increase to the capital budget of £3.576m (£3.381m + £0.195m), as set out within the Capital Forecast section of the report.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
This report provides the Council’s financial performance as at quarter 2 (end September 2026) for the General Fund and the Capital Programme, and the forecast outturn for the financial year 2026/27. The report forms part of the Council’s financial management processes for publicly reporting financial performance on a quarterly basis.
REVENUE FORECAST
Original Approved Current Forecast Transfer Forecast Approved 2025/26 Budget Outturn for to/(from) (Underspend) Budget Carry 2026/27 2026/27 Reserves / overspend 2026/27 Forward 2026/27 2026/27 £m £m £m £m £m £m £28.057m £0.094m £28.151m £27.785m (£3.272m) (£3.639m)
The current net revenue budget for 2026/27 is £28.151m, comprising the original approved budget of £28.057m plus £0.094m of approved budget carried forward from 2025/26.
The £0.094m carry forward relates to expenditure that was not incurred in 2025/26 due to unavoidable slippage, but where the underlying commitment remained. Approval to carry the budget forward into 2026/27 was subsequently granted as part of the 2025/26 Outturn Report.
The forecast outturn for 2026/27 is £27.785m, representing an underspend of approximately (£0.366m) before transfers from reserves. After allowing for planned and approved transfers of £3.272m to fund specific expenditure and commitments, the net forecast position is a (£3.639m) underspend.
OFFICIAL OFFICIAL
Reserve Movements
The (£3.272m) transfer from reserves should not be interpreted as the Council drawing on reserves to support its overall financial position. These transfers relate to specific expenditure and activities for which the use of reserves has previously been identified and approved as the appropriate source of funding. The associated expenditure is included within the forecast outturn, and the corresponding reserve transfer therefore provides the agreed funding for those commitments.
The reserve movements are also separate from the principal areas generating the overall forecast underspend of (£3.639m). For example, the detailed forecast includes reserve funding for specific activities such as Defence Cluster, Enterprise Zone infrastructure expenditure, Market Towns activity and elections-related expenditure. These reserves have been established and approved to support defined expenditure and their use remains necessary irrespective of the Council's overall forecast position.
It is also important not to view the (£3.639m) net underspend as an equivalent amount of uncommitted or ‘spare’ resource which could be used instead of the planned reserve transfers. As set out below, (£3.643m) of the favourable variance relates to items which are one-off in nature, timing-related, or where the ongoing financial impact has already been reflected within the 2027/28 budget and MTFP. The reserve transfers and the forecast underspends arise in different areas and for different reasons and should therefore be considered separately
Nature of Forecast Underspend
The Quarter 2 forecast indicates a (£3.639m) net revenue underspend for 2026/27. It is important to note that this position does not represent an ongoing reduction in the Council's underlying cost base and should not be regarded as a recurring level of underspend available in future years.
A significant proportion of the forecast variance arises from one-off income and expenditure, timing differences and the impact of capital programme rephasing. Where favourable variances are expected to continue, the relevant assumptions have already been incorporated into the 2027/28 budget and Medium-Term Financial Plan (MTFP). Consequently, the (£3.639m) forecast underspend should not be assumed to recur in future years.
The principal areas contributing to the 2026/27 position include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.