Huntingdonshire District Council
Cabinet, Tuesday 17 November 2026 at 7.00pm

Finance Performance Report Q2

Approved Executive 4 papers

AI summaryHuntingdonshire District Council Cabinet approved a £3.576m capital budget increase, raising the programme from £34,631 to £38,207. It also reviewed revenue and capital performance for quarter two of 2026/27. [D] [P30]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme rises from £34,631 to £38,207. [P30]
Money£3.576m [D]Approved increase: £3.576m (£3.381m + £0.195m). [D]
What happens nextFurther funding report planned [P40]One Leisure funding source and preliminary costs. [P40]
Who it affectsNot stated

What was decided

Cabinet reviewed quarter two General Fund revenue performance and the forecast final result for 2026/27. Report 1.1

Cabinet reviewed quarter two Capital Programme performance and its forecast final result for 2026/27. Report 1.2

The approved capital budget increase was £3.576m (£3.381m + £0.195m). Report 1.3

Why

The General Fund was forecast at £27.785m against a budget of £28,151m. This was an underspend of approximately (£0.366m) before reserve transfers and a net forecast underspend of (£3.639m) after them. Report P15

Priory Centre funding was already approved, so £3.176m was needed to align the capital budget with the agreed funding, project scope and financing. Report P46, P47

The One Leisure project cost fell, but external funding fell further. The Council therefore still needed extra funding to proceed, with a further Cabinet report planned. Report P35, P40

What happens next

A further report will go to Cabinet with the proposed funding source for the One Leisure project and any confirmed preliminary costs. Report P40

Financial resource changes will be reflected in quarterly monitoring reports, future budgets and the MTFS. Report P94

Effective public budget monitoring and reporting will continue, as required by the Constitution and financial regulations. Report P85

The money

  • £3.576m (£3.381m + £0.195m) Approved increase to the capital budget Report 1.3
  • £34,631 Capital programme budget before the increase Report P30
  • £38,207 Capital programme budget after the increase Report P30
  • £3.176m Priory Centre capital expenditure budget increase Report P47
  • £0.205m Properties Houses budget movement linked to returned Government resettlement funding Report P48, P49
  • £836,883 Latest estimated One Leisure project cost Report P33
  • £27.785m Forecast General Fund revenue outturn Report P15
  • (£3.639m) Net forecast underspend after reserve transfers Report P15

Options considered

  • Chosen: Option 3: Deliver through the HDC Capital Programme. Withdraw from the Football Foundation funding offer and deliver the project directly. The current estimated cost creates an additional HDC capital funding requirement of approximately £217,000. Report P38, P39
  • Rejected: Option 1: Do not proceed. Discontinue the project and avoid the need for existing HDC and CIL funding. Report P38, P39
  • Rejected: Option 2: Proceed with Football Foundation funding. Accept the revised grant offer of approximately £217,000 and deliver the project subject to the funding conditions. Report P38, P39

Implications

  • Financial: The capital programme rises from £34,631 to £38,207 after the £3,576 increase. Report P30
  • Financial: The Priory Centre budget increases by £3.176m to match funding already agreed. Uncommitted Government resettlement funding was returned because suitable remaining homes could not be secured within the available funding and viable values. Report P47, P49
  • Financial: One Leisure still needs more Council money because the grant reduction exceeded the project cost reduction. The additional HDC requirement is approximately £217,000. Report P35, P38, P40
  • Financial: The General Fund forecast is a net underspend of (£3.639m) after a (£3.272m) transfer from reserves. Report P15
  • Legal: The Constitution and financial regulations require effective budget monitoring and public reporting to Cabinet and the Overview and Scrutiny Panel. Report P85
  • Risk: Budget and service risks will be recorded on local risk registers and the Council's overall risk register. Report P98
  • Climate: The impacts of expenditure in climate and environment related budgets need to be noted, particularly for the Parks service. Report P89
  • Other: Resource changes will be handled through later quarterly reports, budgets and the MTFS. The retrospective report has limited local government reorganisation impact. Report P94, P97

Who and where

  • Services funded through the General Fund Report P15, P28
  • The Priory Centre project Report P47
  • The One Leisure St Ives Outdoor 3G Football Pitch project Report P32, P40
  • The Football Foundation Report P38, P39
  • Council Tax and Business Rates taxpayers Report P62, P63
  • Ukrainian and Afghan families supported through the Government resettlement scheme Report P49
  • Parks and climate related services Report P89
  • Council debtors Report P68, P70

Timeline

  • February 2026: The 2026/27 General Fund revenue budget and Capital Programme were approved. Report 2.1, 2.2
  • February and March: Council Tax and Business Rates collection was expected to recover as later instalments fell due. Report P65
  • July 2026: A proposal to allocate remaining Cambridgeshire Horizons legacy funding was presented, with the Priory Centre identified as eligible. Report P42
  • 28 July 2026: The One Leisure project options report went to the Treasury and Capital Management Group. Report P37
  • end September 2026: The quarter two General Fund revenue and Capital Programme reporting period ended. Report 1.1
  • 15 September 2026: Cabinet approved the Priory Centre funding proposals and supported Option 3 for the One Leisure project. Report P37, P39, P46
  • 30 September 2026: Outstanding debt was analysed, including balances that were not yet overdue. Report P68, P69
  • 2026-11-17: Cabinet reviewed quarter two finances and approved the capital budget increase.

Plain English for the jargon

  • Quarter 2: The half year reporting point at the end of September 2026. [1.1]
  • Forecast outturn: The forecast final result for 2026/27 based on half year delivery. [1.1]
  • General Fund revenue budget: The revenue budget reviewed for quarter two performance and the full year forecast. [1.1] [2.1]
  • Capital Programme: The programme of capital scheme spending reviewed for quarter two performance and the full year forecast. [1.2] [2.2]
  • MTFS: Medium Term Financial Strategy. [2.1]
  • CIL: Community Infrastructure Levy funding. [P36]
  • HDC: Huntingdonshire District Council. [P38]
  • TCMG: Treasury and Capital Management Group. [P37] [P42]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter two and the forecast outturn for the financial year 2026/27 based on performance in quarter 2 as detailed in Appendix 1 and Appendix 2; (2) considered and commented on the Capital Programme’s financial performance in quarter two and the forecast outturn for 2026/27 as based on the performance in quarter, as detailed in Appendix 3; and (3) approved an increase to the capital budget of £3.576m (£3.381m + £0.195m), as set out within the Capital Forecast section of the report.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

OFFICIAL

Cabinet – 17th November 2026

Report by: Head of Finance

Lead Cllr: Cllr J E Harvey Executive Councillor for Finance and Resources

Wards Open / Exempt Key Decision? ALL wards Open No

2026/27 Finance Performance Report – Forecast at Quarter 2 Executive Summary:

This report provides the Council’s financial performance as at quarter 2 (end September 2026) for the General Fund and the Capital Programme, and the forecast outturn for the financial year 2026/27. The report forms part of the Council’s financial management processes for publicly reporting financial performance on a quarterly basis.

REVENUE FORECAST

Original Approved Current Forecast Transfer Forecast Approved 2025/26 Budget Outturn for to/(from) (Underspend) Budget Carry 2026/27 2026/27 Reserves / overspend 2026/27 Forward 2026/27 2026/27 £m £m £m £m £m £m £28.057m £0.094m £28.151m £27.785m (£3.272m) (£3.639m)

The current net revenue budget for 2026/27 is £28.151m, comprising the original approved budget of £28.057m plus £0.094m of approved budget carried forward from 2025/26.

The £0.094m carry forward relates to expenditure that was not incurred in 2025/26 due to unavoidable slippage, but where the underlying commitment remained. Approval to carry the budget forward into 2026/27 was subsequently granted as part of the 2025/26 Outturn Report.

The forecast outturn for 2026/27 is £27.785m, representing an underspend of approximately (£0.366m) before transfers from reserves. After allowing for planned and approved transfers of £3.272m to fund specific expenditure and commitments, the net forecast position is a (£3.639m) underspend.

OFFICIAL OFFICIAL

Reserve Movements

The (£3.272m) transfer from reserves should not be interpreted as the Council drawing on reserves to support its overall financial position. These transfers relate to specific expenditure and activities for which the use of reserves has previously been identified and approved as the appropriate source of funding. The associated expenditure is included within the forecast outturn, and the corresponding reserve transfer therefore provides the agreed funding for those commitments.

The reserve movements are also separate from the principal areas generating the overall forecast underspend of (£3.639m). For example, the detailed forecast includes reserve funding for specific activities such as Defence Cluster, Enterprise Zone infrastructure expenditure, Market Towns activity and elections-related expenditure. These reserves have been established and approved to support defined expenditure and their use remains necessary irrespective of the Council's overall forecast position.

It is also important not to view the (£3.639m) net underspend as an equivalent amount of uncommitted or ‘spare’ resource which could be used instead of the planned reserve transfers. As set out below, (£3.643m) of the favourable variance relates to items which are one-off in nature, timing-related, or where the ongoing financial impact has already been reflected within the 2027/28 budget and MTFP. The reserve transfers and the forecast underspends arise in different areas and for different reasons and should therefore be considered separately

Nature of Forecast Underspend

The Quarter 2 forecast indicates a (£3.639m) net revenue underspend for 2026/27. It is important to note that this position does not represent an ongoing reduction in the Council's underlying cost base and should not be regarded as a recurring level of underspend available in future years.

A significant proportion of the forecast variance arises from one-off income and expenditure, timing differences and the impact of capital programme rephasing. Where favourable variances are expected to continue, the relevant assumptions have already been incorporated into the 2027/28 budget and Medium-Term Financial Plan (MTFP). Consequently, the (£3.639m) forecast underspend should not be assumed to recur in future years.

The principal areas contributing to the 2026/27 position include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 547 KB Download
PDF
Appendix 2Appendix 2 198 KB Download
PDF
Appendix 3Appendix 3 265 KB Download
PDF
Finance Performance Report Q2Report 358 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 9 attended
SC
Councillor Stephen ClaffeyMember, expected
SJ
Councillor Sarah Joanne ConboyChair, expected
LD
Councillor Liam Dewey-BeckettMember, expected
JE
Councillor Joanna Elizabeth HarveyMember, expected
NJ
Councillor Nathan James HuntMember, expected
JE
Councillor Julie Elizabeth KerrMember, expected
BA
Councillor Brett Alistair MickelburghVice-Chair, expected
DL
Councillor Debbie Lydia MickelburghMember, expected
TS
Councillor Tom SandersonMember, expected

On this subject at Huntingdonshire

Search all
  1. Finance Performance Report Q2This decision
  2. Finance Performance Report Quarter 1Approved
  3. 2025/26 Finance Performance Report - Provisional OutturnDecided
  4. 2025/26 Finance Performance Report - Forecast at Quarter 3Decided
  5. 2025/26 Finance Performance Report - Forecast at Quarter 2Decided
  6. Finance Performance Report 2025/26 (Quarter 1)Decided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Treasury Management 6 Month Performance Review 2026/27The Cabinet has noted the treasury management performance included in the Treasury Management 6 Month Performance Rev... Noted Open