The Cambridgeshire Local Transport Plan Annual Progress Report and Huntingdonshire Statement were approved. The Director of Operational Services, after consultation with the Executive Councillor for Planning and Highways, was authorised to make minor amendments to the Annual Progress Report and to the Huntingdonshire Statement.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
2.1DfT (Department for Transport) require Cambridgeshire County Council to submit a joint Annual Progress Report (APR) by 31st July 2004 on the delivery of the Cambridgeshire Local Transport Plan. The APR informs the financial settlement, usually around December, provided to deliver the transport agenda for Cambridgeshire.
2.2This Authority, together with the other City and District authorities are required to submit a statement specific to their area outlining the commitment of the Council to the APR and also reporting on local delivery. A copy of the draft statement will be available for Members consideration at the meeting.
2.3Members will recall that we produced a replacement LTP last year for the period 2004-2011 in advance of the national requirement for replacement in July 2005. This APR is still, however, based on the work of the previous LTP with the APR for next year reflecting the new document.
2.4The APR is the mechanism by which Government allocates capital funds for transport on a year-by-year basis. Last year’s submission secured a much improved settlement of £22.040M (21% higher than the previous year) with an overall ‘above average’ ranking for the APR itself. In recognition of this improvement, an extra £1.8M was granted. The settlement also included continued funding for the A14 village traffic calming project, further details of which are included within this year’s submission.
2.5This year’s revised APR guidance is once again looking for clear identification of performance against targets and is looking for trajectory projections in order to assess expected performance for reported areas on a year-by-year basis. This is being specifically requested to provide a clearer indication of where earlier action may be required in order to address an action that may not be ‘on-track’ according to an overall stated target or objective.
3. 2003/04 DELIVERY
3.1Key areas relating to delivery within this year’s APR include;
3.1.1 A14 village traffic calming project is ‘on-track’ for implementation with a further bid now being made for Bluntisham, Buckden, Earith and The Stukeleys to be included from Spring/Summer 2005. Three other villages outside Huntingdonshire are also included in the bid. 3.1.2 An increase in Walking schemes of 32% delivered over the originally planned programme for 2003/04 is reported.
3.1.3 Under Cycling, a report on the completion of the jointly-funded County/District Eynesbury to railway station scheme in St. Neots is being submitted. This was delivered as part of the Market Town transport strategy and designed and delivered by this Council’s Project team.
3.1.4 Within the continuing improvement of Public Transport infrastructure, the replacement of all the bus stops in St Neots is reported, which included posts, flags, timetable cases and updated timetable displays.
3.1.5 For Road Crossing schemes, a 141% increase over the planned programme is reported. This includes 28 additional crossings as part of Market Town strategies and 25 in villages close to the A14 as part of the traffic calming project.
3.1.6 An all time low figure for the number of people killed or seriously injured on roads in Cambridgeshire is reported, which continues the downward trend. 2003/04 saw a figure of 471 people recorded against a target of 481.
3.1.7 In terms of Major schemes, details relating to the development of the Cambridgeshire Guided Busway scheme are included outlining current progress with public consultation, the development of the Transport and Works Act Order and proposed on-street measures between Huntingdon and St. Ives and within Cambridge City.
3.2Key areas relating to progress against targets and objectives include:
3.2.1 A drop in the overall satisfaction rate relating to local bus services. Currently 29.5% against 39% three years ago.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.